You can obtain a service via the Portal:
You can obtain a service via the Portal:
After getting initial materials for a new construction:
- electronic copies of architectural planning specifications, vertical grade elevation, a copy of the detailed layout project, cross-section of roads and streets, technical specifications, external engineering networks diagrams.
After getting an architectural planning specifications and technical specifications:
- electronic copies of an architectural planning specifications and technical specifications.
After getting initial materials for re-construction (re-planning, re-equipment) of facilities (certain parts) of existing buildings and structures associated with changes in load-bearing and enclosing (external) structures, engineering systems and equipment:
- electronic copy of decision issued by a local executive body for re-construction (re-planning, re-equipment) of facilities (certain parts) of existing buildings and structures associated with changes in load-bearing and enclosing (external) structures, engineering systems and equipment, architectural planning specifications, technical specifications (when submitted by an applicant), external engineering networks diagrams (when submitted by an applicant).
Substantiated refusal to deliver the public service.
General requirements for the appeal
The appeal submitted in hard copy or electronic form shall indicate:
If the administrative procedure is on a paid basis, the applicant must submit a document confirming the payment.
Source: Administrative Procedural Code of Republic of Kazakhstan,
The Law of the RK "On Public services"
Free of charge
The deadline for consideration of the application for construction projects of technically and (or) technologically simple objects:
for the issuance of architectural and planning tasks and technical conditions for connection to sources of engineering and utilities - 6 working days;
it takes 15 working days to receive the initial materials for new construction.
The deadline for consideration of the application for construction projects of technically and (or) technologically complex objects:
for the issuance of APZ and technical conditions – 15 working days;
it takes 17 working days to receive the initial materials for new construction.
The deadline for consideration of the application for obtaining the initial materials and permits for the reconstruction of the premises of existing buildings and structures associated with the change of load–bearing and enclosing structures, engineering systems and equipment is 15 working days from the date of submission of the application.
Motivated refusal – 5 working days.