- According to this program, it is planned to complete the construction of a 60-apartment rental residential building in the village of Balpyk bi, Koksu district. Contractor organization "JV "NEFT" LLP. On March 19, 2020, a contract No. 19 for the SMR was signed with JV NEFT LLP for a total amount of 550 million 655 thousand 493 tenge. Construction and installation work began on April 8, 2020. The completion date is scheduled for June 2021.
Balpyk bi 60 kv house:
Number of apartments - 60, including:
1 kom – 28 pieces
2 kom – 32 pieces
- For the construction of engineering and communication networks and the improvement of this house, on March 10, 2020, the Office of the Akim of the Koksu district announced a competition on the public procurement portal. The deadline for accepting applications is scheduled for April 1, 2020. According to the protocol of the results, the winner was determined by Monolit LLP. On April 23, 2020, a contract No. 24 for SMR was signed with Monolit LLP for a total amount of 75 million 688 thousand 397 tenge.
- Also, on January 13, 2021, the Office of the Akim of the Koksu district announced a competition on the public procurement portal on 40 hectares allocated for the construction of ICS for residential housing under this program for the construction of engineering and communication networks for residential housing (external power supply). The deadline for accepting applications is scheduled for February 4, 2021. After the completion of the construction of all engineering and communication networks, 186 sites will be provided for the construction of residential housing. In 2020, the construction of a water pipeline was completed on this site.
- Under this program, on January 12, 2020, the Public Procurement Department of Almaty region announced a competition on the public procurement portal for the construction of a 20-apartment rental residential building in Balpyk Bi village. The winner was determined by "Shymkent" LLP. Construction and installation work is scheduled to begin in April 2021. The estimated cost of the facility was 247 million 288 thousand tenge.
Number of floors of the building – 5
Number of apartments – 20 of them:
Two-room apartments – 10 pieces
Three-room apartments – 10 pieces
- For the construction of engineering and communication networks and the improvement of this house, on January 13, 2021, the Office of the Akim of the Koksu district announced a competition on the public procurement portal. The winner was determined by "Sem shogy kurylys Service" LLP. The estimated cost of the facility was 39 million 088 thousand tenge.
- At the same time, for the development of design and estimate documentation for the object: "Construction of the 21st four-room rental residential buildings (10 houses with an area of 80 m2 each and 11 houses with an area of 100 m2 each) in the village of Balpyk bi, Koksu district, Almaty region", a competition was announced on the public procurement portal on April 12, 2019. According to the protocol of the results, the winner was determined by "ARS LTD" LLP. On June 5, 2019, contract No. 55 was signed with ARS LTD LLP for a total amount of 10 million 297 thousand 776 tenge(the delivery period under the contract is 12.7 months from the date of conclusion of the contract, with the examination of 13.5 months). The design work has been completed. The POI is under examination. The allocation of funds for construction and installation works is planned for 2021-2022.
Number of floors of buildings – 1
Number of houses – 21
10 houses with an area of 80 sq. m.
11 houses with an area of 100 sq. m.
- Also, for the development of design and estimate documentation for the object: "Construction of a 20-apartment rental residential building in the village of Balpyk bi in the Koksu district of Almaty region" (Myrzabekov Street), on March 12, 2020, the Office of the Akim of the Koksu district announced a competition on the public procurement portal. The winner was determined by Remstroyproekt LLP. On May 18, 2020, contract No. 29 was signed for a total amount of 7 million 912 thousand 764 tenge(the delivery period under the contract is 8.5 months from the date of conclusion of the contract). To date, work is underway to develop design and estimate documentation. All technical specifications, APZ, state act are received.
- For the construction of engineering and communication networks and the improvement of this house, on March 12, 2020, the Office of the Akim of the Koksu district announced a competition on the public procurement portal. The winner was determined by Geodesy Service LLP. On May 12, 2020, contract No. 28 was signed for a total amount of 1 million 987 thousand 108 tenge(the delivery period under the contract is 6 months from the date of conclusion of the contract). To date, work is underway to develop design and estimate documentation.
- At the same time, for the development of design and estimate documentation for the object: "Construction of a 60-apartment rental residential building in the village of Balpyk bi, Koksu district, Almaty region" (Kablis street) To announce the competition, an application was submitted to the Office of the Akim of the Koksu district. The winner was determined by "Zhetisu saulet kurylysy" LLP. The total amount of the contract is 10 million 269 thousand tenge. To date, the work on the development of the POI is fully completed. Work is underway to pass the PSA examination.
- For the construction of engineering and communication networks and the improvement of this house, on March 12, 2020, the Office of the Akim of the Koksu district announced a competition on the public procurement portal. The winner was determined by "Zhetisu saulet kurylysy" LLP. On May 25, 2020, contract No. 33 was signed for a total amount of 6 million 919 thousand 709 tenge(the delivery period under the contract is 12.1 months from the date of conclusion of the contract). To date, work is underway to develop design and estimate documentation.
"According to the program development of territories»
- The development of design and estimate documentation has been completed and a positive expert opinion has been received No. ECCos-0022/20 t on 26.03.2020 for the object: "Construction of the building of the State Corporation" Government for Citizens "for 200 visits in the village of Baplyk bi, Koksu district, Almaty region". The estimated cost of the object was-435 million 839 thousand tenge, technical supervision-14 million 121 thousand tenge, design supervision-4 million 881 thousand tenge. The total amount is 454 million 842 thousand 030 tenge. To date, letters and a budget application have been sent to allocate funds for construction and installation work.
- Along with this, the development of design and estimate documentation was completed and a positive expert opinion No. 18-0041/20 t was received on 06.04.2020 for the object: "Construction of a 120-seat secondary school with a 25-seat mini-center in the village of 10 years of Kazakhstan in the Koksu district of Almaty region". The estimated cost of the object was 1 billion 73 million 765 thousand tenge, technical supervision-31 million 461 thousand tenge, design supervision-10 million 845 thousand tenge. The total amount is 1 billion 116 million 071 thousand 322 tenge. To date, letters and a budget application have been sent to allocate funds for construction and installation work.
- Also, for the development of design and estimate documentation for the project: "Construction of a secondary school for 120 places with a mini center for 25 places in the village of Beskainar in the Koksu district of Almaty region", a competition was announced on the public procurement portal on April 12, 2019. According to the protocol of the results, the winner was determined by the LLP "Research Institute of Standard and Experimental Design (Institute of Housing)". On June 16, 2019, a contract No. 61 was signed with LLP "Research Institute of Model and Experimental Design (Institute of Housing)" for a total amount of 36 million 123 thousand 840 tenge(the delivery period under the contract is 14.6 months from the date of conclusion of the contract, with the passing of the examination of 17.1 months). The design organization "NIITEP (Institute of Housing)" LLP, which has drawn up a contract for subcontracting work with "ARS LTD" LLP, has completed the design work to date. A positive expert opinion was obtained. To date, letters and a budget application have been sent to allocate funds for construction and installation work.
- At the same time, for the development of design and estimate documentation for the object: "Construction of a secondary school for 120 places with a mini center for 25 places in the village of Karatal, Koksu district, Almaty region", on March 12, 2020, the Department of Public Procurement of Almaty region announced a competition on the public procurement portal. The winner was determined by KAPREMPROEKT LLP. On July 24, 2020, contract No. 39 was concluded for a total amount of 35 million 137 thousand 944 tenge(the delivery period under the contract is 14.1 months from the date of conclusion of the contract) To date, the Construction Department of the Almaty region is working on the development of the POI.
- Also, for the development of design and estimate documentation for the object: "Construction of the building of the akim of Ainabulak rural district in the village of Ainabulak in the Koksu district of Almaty region", on March 12, 2020, the Office of the Akim of Koksu district announced a competition on the public procurement portal. The winner was determined by Stroytext LLP. On May 25, 2020, contract No. 31 was signed for a total amount of 7 million 717 thousand 773 tenge(the delivery period under the contract is 6.1 months from the date of conclusion of the contract). To date, the work on the development of the POI is being completed. All technical conditions, the state act on the land are received.
- At the same time, on March 12, 2020, the Office of the Akim of the Koksu district announced a competition on the public procurement portal for the development of design and estimate documentation for the object: "Construction of an extension of a food-canteen to the boarding school building in the village of Mambet in the Koksu district of Almaty region". The winner was determined by Stroytext LLP. On May 14, 2020, contract No. 30 was concluded for a total amount of 6 million 808 thousand 210 tenge(the delivery period under the contract is 4.6 months from the date of conclusion of the contract). 9 million 307 thousand tenge was allocated for 2020. The work on the development of the POI is fully completed. To date, the Construction Department of the Almaty region is working to pass the PSA examination.
- Also for the development of design and estimate documentation for the object: "Reconstruction of the building of the former sports school for the kindergarten "Zhuldyz" in the village of Balpyk bi, Koksu district" on October 15, 2020 on the public procurement portal. The winner was determined by Stroytext LLP. On December 2, 2020, contract No. 61 was signed for a total amount of 13 million 869 thousand tenge(the delivery period under the contract is 6.9 months from the date of conclusion of the contract). For 2020, 500 thousand tenge was allocated from the local budget. The technical conclusion is received. To date, the Construction Department of the Almaty region is working on the development of the POI.
- Also, the Construction Department of the Almaty region has started work on the development of design and estimate documentation for a standard project of the object: "Construction of a fire station for 2 exits in the village of Balpyk bi in the Koksu district of the Almaty region". Project organization "Zhetisu saulet kurylysy" LLP. To date, the work on the development of the POI is fully completed. The POI is under examination.
According to the program "7-20-25", " 5-10-20»
Also in 2020, the construction of 10 rental residential buildings of Stroyservice INC LLP on 14 ul. in Balpyk bi village was completed. A memorandum was created and signed with Stroyservice INC. LLP. It is planned that 5-7 houses will be sold through this program.
In 2020, the construction of a 20-apartment residential building was started by the individual developer "Barys-Beton" LLP in the village of Balpyk bi in the Koksu district. Currently, construction and installation work is underway.
The Department of Construction of the Koksu district weekly on Thursdays takes information on the pool under the program "7-20-25" from the Department of housing and Communal Services and housing inspection of the Koksu district. There are no recent changes.