Under this program, in the village of Balpyk bi, on January 29, 2020, for the construction of 60 apartment rental residential buildings, the Public Procurement Department of the Almaty region announced a tender on the public procurement portal. According to the protocol of the results, the winner was JV NEFT LLP. On March 19, 2020, contract No. 19 for construction and installation work was concluded with JV NEFT LLP for a total of 550 million 655 thousand 493 tenge. The start of construction and installation work is scheduled for April 8, 2020.
For the construction of engineering and communication networks and the improvement of this house, the development of design and estimate documentation was completed and a positive expert opinion was received No. ETSKos-0015/20 dated 02.24.2020. For the construction of engineering and communication networks and the improvement of this house, on March 10, 2020, the Akim's Office of the Koksu district announced a competition on the public procurement portal. The deadline for accepting applications is scheduled for April 1, 2020.
Also, under this program for the construction of engineering and communication networks for IZHS (external water supply), on January 29, 2020, the Procurement Department of the Almaty region announced a tender on the public procurement portal. According to the protocol of the results, Daneker LLP was chosen as the winner. At this time, the competition is on appeal.
At the same time, the development of design and estimate documentation was completed and a positive expert opinion was received No. ETSKos-0008/20 dated 02/10/2020. on the object: "Construction of a 20 apartment rental residential building in the village of Balpyk bi, Koksu district, Almaty region" (Nusipov street). The estimated cost of the object was 247 million 288 thousand tenge. To date, letters and a budget application have been sent to allocate funds for construction and installation work.
A positive expert opinion No.SP-0015/20 of 13.03.2020 was developed and received. design and estimate documentation for the construction of engineering and communication networks and the improvement of this house. The estimated cost of the object was 39 million 088 thousand tenge. To date, letters and a budget application have been sent to allocate funds for construction and installation work.
At the same time, to develop design and estimate documentation for the object: “Construction of 21 four-room rental residential buildings (10 houses with an area of 80 m² each and 11 houses with an area of 100 m² each) in the village. Balpyk bi, Koksu district of Almaty region "On April 12, 2019, a tender was announced on the public procurement portal. According to the protocol of the results, ARS LTD LLP was chosen as the winner. On June 5, 2019, an agreement No. 55 was concluded with ARS LTD LLP for a total amount of 10 million 297 thousand 776 tenge. To date, work is underway to develop design estimates.
Also, for the development of design and estimate documentation for the object: "Construction of a 20 apartment rental residential building in the village of Balpyk bi, Koksu district, Almaty region" (Myrzabekova st.) On March 12, 2020, the Akim's Office of the Koksu district announced a tender on the public procurement portal. Due to the changes made to the tender documentation, the deadline for accepting applications was postponed to April 15, 2020.
For the construction of engineering and communication networks and the improvement of this house, on March 12, 2020, the Akim's Office of the Koksu district announced a competition on the public procurement portal. Due to the changes made to the tender documentation, the deadline for accepting applications was postponed to April 15, 2020.
At the same time, for the development of design and estimate documentation for the object: "Construction of 60 apartment rental residential buildings in the village of Balpyk bi, Koksu district, Almaty region" (Kablis street), an application was submitted to the Public Procurement Department of the Almaty region to announce a tender.
For the construction of engineering and communication networks and the improvement of this house, on March 12, 2020, the Akim's Office of the Koksu district announced a competition on the public procurement portal. Due to the changes made to the tender documentation, the deadline for accepting applications was postponed to April 15, 2020.
"According to the program for the development of territories"
Under this program for the construction of the facility: "Construction of a secondary school for 120 seats with a mini center for 25 seats in the village of Kyzyltogan, Koksu district, Almaty region" on January 31, 2019, a competition was announced on the public procurement portal. According to the protocol of the results, the winner was JV NEFT LLP. On April 22, 2019, contract No. 34 was concluded with JV NEFT LLP for a total amount of 717 million 653 thousand 234 tenge. Construction and installation work began on May 6, 2019. For the winter time, due to weather conditions, construction and installation work was suspended from January 1, 2020 to March 14, 2020. An additional agreement was concluded. The notification from GASK was extended, construction and installation work continued from March 15, 2020. The commissioning of the facility is scheduled for July 27, 2020.
Also for the development of design and estimate documentation for the object: "Construction of a secondary school for 120 places with a mini center for 25 places in the village of Beskaynar