On the implementation of the employment road map for 2020 - 2021

Brief description

In 2020, in order to ensure uninterrupted water supply of irrigated lands, protect settlements from flooding during floods, within the framework of the Employment Roadmap for 2020-2021, 10 reservoirs on the balance sheet of the MSI "Zhambyl su Koymalary" in the amount of 121.6 million tenge were repaired - "Shetbulak", "Zhar-Bulak", "Bereke", "Kairat" in Zhualy district, "Sargau" in Shusky district, "Yeshkili-Korday" in Korday district, "Karabakyr", "Kenes-2" in Baizak district, "Altynkol" in Talas district, "BAM" in Zhambyl district.

Terms of execution

The deadline for starting work in accordance with the contract is August of 2020, ending in mid-November. The Department has repeatedly held meetings with contractors on the issue of current repairs of the above-mentioned reservoirs.

Execution status

To date, repair of reservoirs, "Kairat", "Bereke", "sharbulak" zhualy district and "Cargou" Shu area and "Keskil-Korday" Kordai area is fully completed at 100%. In addition,95% of work has been completed on the shetbulak reservoir in the zhualy district, and 75% on the Altynkol reservoir in the Talas district. Repair work on the Kenes-2 and Karabakyr reservoirs in the Baizak district is 90% complete. At the reservoir "BAM" in Zhambyl district, 50% was completed.
There are no obstacles to work on the part of the management.