About the work performed by the department of construction, architecture and urban planning of the Kazygurt district in 2019

INFORMATION

About the work performed by the department of construction, architecture and urban planning of the Kazygurt district in 2019

Kazygurt district department of construction, architecture and urban planning as a customer:

Construction of facilities during the transition period for 2018-2019, commissioned:

823.534 million tenge from the republican budget. 454.8 million tenge for the construction of a school named after M. Auezov with 300 seats in the village of Zhanabazar, the village of Ulgili, Karzhan Tau LLP, contractor in 2018, 40.0 million tenge. finances of the Republic of Belarus 286.307 million tenge 42.354 million tenge to date, the funds have been fully utilized, construction and installation works have been completed in accordance with the production schedule. The facility was commissioned on August 1, 2019 and transferred to the balance of the district education department.

From the republican budget of 855.659 million tenge, Ak Ordasy Corporation LLP contractor for the construction of a school named after Zhylybulak with 300 seats in the village of Zhanabazar, the village of Zhylybulak RB 550.0 million tenge in 2018, 40.0 million tenge. 220.093 million tenge was provided by the Republic of Belarus in 2019, 45.566 million tenge - OB. To date, the funds have been fully used, construction and installation works have been completed in accordance with the production schedule. The facility was commissioned on August 1, 2019 and transferred to the balance of the district education department.

From the local (regional) budget:

For the construction of a school for 200 seats in the village of Kakpak, Zangar village, a contractor for the construction of a school of Zhana ARNA 2002 LLP for 596.636 million tenge, for the construction of a school for 150 million tenge in 2018, in 2019 for the construction and installation at 446.636 million tenge. To date, construction and installation works have been completed in accordance with the production schedule. The facility was commissioned on August 1, 2019 and transferred to the balance of the district education department.

The construction of a school with 150 seats in Zhanabazar s / o., Village Tlektes today the funds are fully used, and construction and installation works are completed in accordance with the production schedule. The facility was commissioned on August 1, 2019 and transferred to the balance of the district education department.

From the local (district) budget:

s / o. Altyntobe, Akkum village, construction of a school for 100 students, MB 354.948 million tenge, contractor Umirzak LLP 62.087 million tenge in 2018, construction and installation work in 2019 - 292.861 million tenge. Construction and installation work was carried out in accordance with the production schedule. The facility was commissioned on August 1, 2019 and transferred to the balance of the district education department.

108.935 million tenge is provided for the construction of a school for 100 places named after Akbarov in the village of Karabau, s. Kularyk, 361.245 million tenge. To date, the funds have been fully used, and construction and installation works have been completed in accordance with the production schedule. The facility was commissioned on July 1, 2019 and transferred to the balance of the district education department.

Construction of a 1-storey 17-apartment communal rental housing for teachers, s / o. K. Abdaliev, village of Atbulak 196.342 million tenge for the contractor LLP "Arhua Group" 84.9 million tenge for 2018, construction in 2019 for installation work was allocated 111.442 million tenge. To date, the funds have been fully utilized, construction and installation works have been completed in accordance with the production schedule. The facility was commissioned on May 13, 2019 and transferred to the balance of the regional education department.

Program

Object name

Total cost of the object (million tenge)

Funds disbursed in 2018 (million tenge)

Financing for 2019 (million tenge)

contractor

Commissioning date

1

2

 3

 4

 5

6

7

Objects put into operation in Kazygurt district

3809.21

1610.9

    2237.6

   

RB / regional budget

Construction of a school for 300 places named after Zhylybulak in the village of Zhylybulak, Zhanabazar rural district

855,659

 

590.0

 

265,659

Ak Ordasy Corporation LLP

08/01/2019g

RB / regional budget

Construction of a school named after M. Auezov with 300 seats in the Zhanabazar rural district

823,534

494,873

328,661

Karzhan Tau LLP

08/01/2019g

Local budget

Construction of a school named after "Akkum" with 100 seats in the village of Akkum in the Altıntoben rural district.

354,948

 

62,087

 

292,861

Umirzak LLP

08/01/2019g

Local budget

Construction of a school to them. Akbarova for 100 places in the village of Kularyk, Karabau rural district

361,245

108,935

252,310

Karatau LTD LLP

07/01/2019g

Regional budget

Construction of a 200-seat school in the village of Zangar, s / o Kakpak.

596,636

150.0

446,636

LLP "NEW CHANNEL 2002"

08/01/2019g

Regional budget

Construction of a school with 150 seats in the village of Tlektes, c / o Zhanbazar.

660,078

 

120.0

 

540,078

LLP "NEW CHANNEL 2002"

08/01/2019g

Local budget

Construction of a 1-storey 17-apartment communal rented residential building for teachers in s. Atbulak, s / o K. Abdaliev.

 

196,342

 

 

84,962

111,442

Arhua Group LLP

05/13/2019g

Construction of 3 transitional schools by 2020 from the local (regional) budget; For the construction of the school named "Akparak" with 200 places in the village. Ondiris, s / o. Turbat. Contractor “AR-Kurylys” LLP total amount of 619.621 million tenge. 150.0 million tenge for 2019 mastered. For 2020, 178.443 million tenge was allocated, work is carried out in accordance with the production schedule. The facility will be commissioned in September 2020.

For the construction of a school for 200 places in with. Kazygurt, s / o. Kazygurt, contractor of Andas-Group LLP, the total amount of 665.280 million tenge in 2019 was provided and mastered 200.0 million tenge. 174.086 million tenge is provided for 2020, work is being carried out in accordance with the production schedule. The facility will be commissioned in September 2020.

The construction of an additional building for the Aschybulak comprehensive school in the village of Ashybulak in the Kazygurt rural district, contractor MD Construction Ltd LLP, the total amount of 337.865 million tenge in 2019, 150.0 million tenge mastered. For 2020, 192.372 million tenge is provided, work is carried out in accordance with the production schedule. The facility will be commissioned in September 2020.

Program

Object name

Total cost of the object (million tenge)

Funds disbursed in 2018 (million tenge)

Financing for 2019 (million tenge)

contractor

Commissioning date

1

2

 3

4

5

6

7

Objects under construction in Kazygurt district

1622.8

500,0

    544,901

   

 regional budget

Construction of a school named after Akparak with 200 seats in the village of Ondiris, c / o Turbat

619,621

150.0

178,443

LLP "ART-Construction"

2020zh mts. September

regional budget

Construction of a school for 200 places in the village. Kazygurt, s / o. Kazygurt

665,280

200,0

174,086 

Andas Group LLP

2020zh mts. September

 regional budget

Construction of an additional building to the secondary school "Ashibulak" in the village of Ashybulak, Kazygurt rural district

337,865

150.0

192,372

ТОО"MD Construction Ltd"

2020zh mts. September

In the field of housing;

In addition, as part of a public-private partnership in the center of the Kazygurt rural district, according to the plan, 3 multi-storey residential buildings, today a 2-storey 10-apartment building from an individual entrepreneur Kuat Kurylys LLP was allocated 56.9 million for the acquisition of state property tenge. 2 additional 2-story 10-apartment buildings are under construction.

8 social facilities will be provided with natural gas

Including:

6 House of Culture: The House of Culture is located in the village of Karabau, s. Ushbulak. s / o Zhanabazar, s. Zhanabazar, s / o Turbat, s. Turbat, s / o Saraphana, s. Saraphan, s / o S. Rakhimov, s. Kokibel and s / o Kyzylkiya, s. Kyzylkia contractor, TVIK LLP for 2019. MB was allocated 17.936 million tenge, today the funds have been fully utilized, construction and installation works were carried out in accordance with the production schedule and were connected to gas in the heating season and transferred to the balance of the district department of culture and language development.

2-schools: s / o. S. Rakhimov, s.Kokibel, s / o.Sarapkhan, s.Sarapkhan, hostel named after Y. Altynsarin, gas supply facilities, contractor TVIK LLP for 2019 allocated 11.914 million tenge, funds have been fully utilized, construction and installation works made in accordance with the production schedule and were connected to gas in the heating season and transferred to the balance of the district education department.

About construction projects being built in 2020;

s / o. Zhanabazar, s. XX years Kazakhstan school named after K.Azerbaeva for 200 places. The total estimated construction cost is 801.877 million tenge, OB 200.0 million tenge. The winner of the public procurement tender was the contractor TARAZSTROY-2004 LLP (technical supervision of Turan Kurylys LLP), and construction and installation works and conclusion of contracts are currently underway between the customer and the supplier.

The total estimated cost of building a school for 100 places in the village of Ainatas s / o. Kyzylkia is 645.082 million tenge; in 2020, 126.702 million tenge is provided. To date, a public procurement tender has been announced (opening date February 12, 2020).

The total estimated cost of the construction of the control center and the front office building of the district police station of the village of Kazygurt, s / o. Kazygurt is 50.526 million tenge. The Department of Passenger Transport and Roads announced a tender for state procurement on 01/28/2020 (opening date 02/21/2020).

6 social facilities will be provided with natural gas;

For the construction of natural gas supply to the school "Altyntobe" with 300 seats in the village. Altıntobe, s / o. Altintobe; school "Kosagash" with 300 places in with. Kosagash, s / o.Altyntobe, the school "Kyzylata" with 300 places in the village. Kyzylate. s / o. S. Rakhimova, the house of culture in the village of Sharbulak, s / o. Sharbulak, in with. Rabat, s / o. K.Abdaliev, provided from the local budget 118.195 million tenge. The Department of Housing and Communal Services and Passenger Transport and Roads, approved as the sole organizer of public procurement of the district on 01/17/2020, a public procurement contest was announced (opening date 02/09/2020).

Program

Object name

Total cost of the object (million tenge)

Financing for 2020 (million tenge)

Note

1

2

 3

5

7

Social facilities provided by natural gas

118,195

   

118,195

 

 

Local (district) budget

Altyntobinsky s / o, with. Altıntobe gas supply school "Altıntobe" with 300 seats

24,621

 

24,621

By 2020, construction will begin

Local (district) budget

Altyntobinsky s / o, with. Kosagash gas supply school "Kosagash" with 300 seats

22,416 

 

22,416 

By 2020, construction will begin

Local (district) budget

S. Rakhimov s / o, s. Kyzylat gas supply school "Kyzylat" with 300 seats

23,620

 

23,620

By 2020, construction will begin

Local (district) budget

gas supply of the house of culture in with. Sharbulak, s / o.Sharbulak

25,515

 

25,515

By 2020, construction will begin

Local (district) budget

gas supply of the house of culture in with. Rabat, s / o.K.Abdaliev

20,375

 

20,375

By 2020, construction will begin

Local (district) budget

gas supply of the house of culture in with. Altıntobe, s / o.Altıntobe

1,648

 

1,648

 

 

By 2020, construction will begin

On the construction of 9 schools;

The total cost of the examination No. ELTD-0039/19 of 10.25.2019 for the construction of the A. Baitursynov school for 300 places in the village of Maylyoshak s / o. Saraphan, the total cost of 1,262.5 million tenge. Zhanabazar s / o, in the village Zhanabazar (Beinetkesh) of the A.Akhabaev school with 200 places for the construction of No. SP-0086/19 of 10.28.2019, the total cost of 883.576 million tenge. On the construction of the school "P. Tazhibaeva "for 200 places in the village. Rabat, s / o. K. Abdalieva, the total cost of the examination No. SP-0046/19 of 07/10/2019 is 799.125 million tenge. For the construction of the Syrlysay school for 200 places in the village. Syrlysay, s / o. Kakpak ,. the total cost of the examination No. RE-0162/19 dated 05.12.2019. 800.395 million tenge. For the construction of a school with 150 places in the village. Akbastau, s / o. Sharbulak, the total cost of the examination of January 23, 2018 No. YuKPE-0013/18 632.520 million tenge, from the regional budget in 2019,

On the construction of the school “T. Kalkauli ”for 100 places in the village. Kyzylkia, the total cost of the examination No. ELTD-0088/19 dated 12.25.2019, 607.917 million from the local (district) budget were presented for allocation of funds to the district department of economy and finance.

s / o. K. Abdalieva, in the village of Enbekshi, the project for the construction of a model additional educational building for 100 places in the building of the Enbekshi secondary school was approved on 01/13/2020 with a positive conclusion of examination No. QS-0033/20 totaling 346.207 million tenge, from the local The (district) budget was presented to allocate funds to the district department of economics and finance.

For the construction of a school with 300 seats in the Bolashak microdistrict of the Kazygurt district, the total cost of the examination No. M-0001/20 dated January 16, 2020, a positive opinion was received in the amount of 1,275,239 million tenge, for consideration of funds from the regional budget, to the branch offices provided full version of documents.

On the construction of 4 culture houses; For the construction of a house of culture for 200 places in the village. Shanak, the total cost of examination No. 19-0324 / 18 of 10/19/2018 is 349.954 million tenge. For the construction of a house of culture for 200 places in the village. Zhigergen, the total cost of examination No. 19-0406 / 18 dated 12/20/2018 is 321.521 million tenge. For the construction of a house of culture for 200 places in the village of Altyntobe, in a village. Karzhan, the total cost of the examination No. 19-0396 / 18 dated 12/19/2018 of 326.157 million tenge. For the construction of a house of culture for 200 places in the village. Karabau, in the village Sintas, the total cost of the examination No. 19-0021 / 19 of 02/01/2019 is 380.631 million tenge, for consideration of funds from the regional budget, the full version of the documents is submitted to the industry departments.

On the construction of a 1-story apartment building; Kazygurt s / o, s. Kazygurt, 4.760 million tenge; Turbatsky s / o, with. Turbat 4.760 million tenge; Zhanabazar s / o, s. Zhanabazar 4.760 million tenge and s / o. Saraphana, p. Saraphan, 4.760 million tenge, to date, work is underway to obtain a positive expert opinion.

On the construction of 2 cultural facilities; Design and estimate documentation for the construction of a house of culture for 500 people in the district center (7.929 million tenge) of Kupol LLP and is recommended for obtaining a positive state examination opinion.

Design and estimate documentation for the construction of a museum in the Kazygurt rural district (4.250 million tenge) of Geo-Proekt LLP and is recommended for obtaining a positive state examination opinion.

On the construction of gas supply of 9 schools;To provide natural gas schools "Karzhan" s. Karzhan, s / o. Altıntobe in the amount of 26.310 million tenge. To provide natural gas to the school "Ө. Zhamalova" p. Karzhan. s / o. Altyntobe, the total cost of the examination No. GNK-0014/19 of 02.21.2019 is 23.571 million tenge. On the construction of gas supply to the school "1-Mamyr" s. Karzhan, s / o Altyntobe dated 02.21.2019 for a total of 22.659 million tenge. On the construction of a natural gas supply school 30 years of October with. Turbat, s / o Turbat dated February 21, 2019 No.GNK-0019/19, the total value of 22.521 million tenge. For the construction of a gas supply school S.O. Turbat, S. Enbek dated 02.21.2019 No. GNK-0018/19 with a total value of 21.462 million tenge. Gas supply school "Kyzildikhan" in the village. Kyzildikhan s / o Turbat, dated 08.02.2019, No. YuKPE-0004/19 totaling 24.977 million tenge. For the construction of gas supply to the Zhanatirlik school in the village of Andiris, Turbat village, the total cost is 16.922 million tenge. For the construction of gasification of the school "A.Orazbaeva" for 200 places Karabau, s / o. Karabau, for the construction of gasification of school No. YuKPE-0214/19 of 12/13/2019, the total cost of 9.531 million tenge. For the construction of gasification of the school "B.Kudainazarov", s / o.Zhigergen, s. Kyzylbulak, for the construction of gasification of the B. Kudainazarov school, the total cost of the examination No. YUKPE-0213/19 of 12/13/2019 for a total amount of 9.009 million from the regional budget was presented to allocate funds to the regional department of economy and finance. 2019, the total value of 9.531 million tenge. For the construction of gasification of the school "B.Kudainazarov", s / o.Zhigergen, s. Kyzylbulak, for the construction of gasification of the B. Kudainazarov school, the total cost of the examination No. YUKPE-0213/19 of 12/13/2019 for a total amount of 9.009 million from the regional budget was presented to allocate funds to the regional department of economy and finance. 2019, the total value of 9.531 million tenge. For the construction of gasification of the school "B.Kudainazarov", s / o.Zhigergen, s. Kyzylbulak, for the construction of gasification of the B. Kudainazarov school, the total cost of the examination No. YUKPE-0213/19 of 12/13/2019 for a total amount of 9.009 million from the regional budget was presented to allocate funds to the regional department of economy and finance.

On the construction of gas supply for 3 kindergartens; For the construction of gas supply for the kindergarten "Zhigergen", s / o Zhigergen, the total cost of the examination dated May 24, 2019 No. EA-0030/19 is 16.445 million tenge. To provide natural gas to the kindergarten "Balbobek" p. Sintas s / o. Karabau, the total cost of the examination No. EA-0028/19 dated 05/05/2019, 17.183 million tenge. For the construction of natural gas kindergarten In with. Sharbulak, s / o Sharbulak, No. YuKPE-0171/19 of 10.30.2019, the total cost of 28.839 million tenge, proposals were submitted to the regional department of the economy, to consider financial resources from the regional budget.

In the agricultural sector (construction of bathing baths for livestock);

for the construction of buying baths for livestock in with. Sharbulak, s / o. Sharbulak No. QS-0261/19 dated 12/12/2019, the total cost of the examination is 10.298 million tenge. On the construction of a bath in with. Sharbulak, s / o. Sharbulak No. QS-0262/19 dated 12/12/2019, the total cost of the examination is 10.202 million tenge. s / o. Altıntobe, with. Karzhan for the construction of a bathtub No. QS-0258/19 dated 12/12/2019, the total cost of the examination is 10.203 million tenge. s / o. Saraphan, in the village of Bakabulak for the construction of bath No. QS-0259/19 of 12/11/2019, the total cost of the examination is 10.230 million tenge. s / o. Karabau, in the village of Ushbulak, construction of a bathtub No. QS-0260/19 dated 12/12/2019, the total cost of the examination was 10.225 million tenge, a proposal was made to allocate funds from the district budget for 2020.

In the field of agriculture (construction of the Becquerean pit); For the construction of a pit in the village Karzhan, s / o. Altyntobe, the total cost of the examination dated 12/31/2019, 14.841 million tenge. For the construction of a pit of backyard in Akzhar, s / o. Shanak the total cost of the examination dated 12/31/2019 with a total value of 14.810 million tenge. For the construction of a pit in the village Eski Shanak, s / o Shanak, the total cost of the examination No. KSK-0105/19 dated 12/31/2019 is 14.833 million tenge. For the construction of a pit in the village Karabau, s / o. Karabau from 12/31/2019 with a total cost of expertise of 14.794 million tenge. For the construction of a pit of backyard in Kazygurt dated 12/31/2019, the total cost of the examination No. KSK-0107/19 was 14.785 million tenge, a proposal was made to allocate funds from the district budget for 2020.

According to the approved plan for 2019, with a total area of ​​19,100 square meters. In January-December of the current year, 160 individual residential buildings were registered, a two-story 10-apartment building, built as part of a public-private partnership and, at the expense of the regional budget, acceptance certificates for a 1-storey 17-apartment building in the village Atbulak. Compared to 2018, it was completed by 100.1%.

In addition, the department provides services for the provision of public services through the population service center in 3 areas: the address register certificate, architectural and planning assignment, and the design of outdoor visual advertising.

In the 1st direction, in the information system "Address Register" in 2019, through the PSC, 3004 requests were received, applicants received timely certificates.

In the 2nd direction, in 2019, through the PSC, 63 applications for architectural and planning assignments were received, including: 21 entrepreneurial facilities, 1 private residential facility, 41 public facilities, 1 mosque building completed on time and delivered to the applicants.

Under the E-license, 20 applications were received in the architectural and planning assignment, of which: 10 state-owned facilities, 10 business facilities completed on time and delivered to the applicants.

 In the 3-direction in 2019, 53 complaints were registered, in accordance with the law, answers were given in a timely manner.

 
Дата публикации
02 мая 2020
Дата обновления
02 мая 2020
Тип
Useful information

Сейчас читают

Information
04 мая 2020
Education
Useful information
02 мая 2020
Completed work on employment and the level of employment for the I quarter of 2020
Useful information
02 мая 2020
About the work performed by the department of construction, architecture and urban planning of the Kazygurt district in 2019

Социальные медиа

Меню подвал

State of the Nation Address of the President of Kazakhstan
Website of the President of Kazakhstan
Website of the Prime Minister of Kazakhstan
Digital transformation concept
Life situations
National symbols
Terms and explanations
Central communications service under the President of the RK
Screen Reader
Құпиялылық саясаты