"TETHYS AKTAU III" LLP
Project description
Current situation: The total readiness of the object "Shopping malls "Town Center" (8,9 ha) – 96,0%. Earthworks – 100%; Reinforced concrete structures of the whole complex – 100%; Metalwork – 100%; Wall construction – 99.7%; Facade – 96.7%; Roofing – 98.3%; Waterproofing and thermal insulation - 97.1%; Plaster – 92.2%; Finishing works – 93.0%; Engineering networks – 100%; Landscaping – 91.2%; Plumbing work – 94.4%; Electrical work – 94.8%).
Investment volume
16.2 billion tenge
Jobs
44
Project capacity
30 000 sq.m.