Report on the activities of the Department of Energy and Housing & Communal Services of the Kyzylorda Region for the nine months of 2026
Drinking water supply
The region comprises 4 cities and 222 rural settlements. All cities have 100% access to drinking water. The proportion of the population with access to centralized drinking water supply stands at 100%.
In 2026, 11.9 billion tenge was allocated for the implementation of water supply and sanitation projects. A total of seven projects are currently underway. Upon their completion, plans are in place to reduce the wear and tear of water supply networks from 33% to 31% and that of sewage networks from 32% to 30%.
Additionally, a project is underway to construct a second branch of the Aral-Sarybulak group water pipeline—spanning 238 kilometers—which will supply drinking water to over 160,000 residents of the Aral and Kazaly districts. The project is valued at 43.7 billion tenge. In 2025, 5.5 billion tenge was allocated from the national budget, and 23 kilometers of the pipeline were completed.
For 2026, 1.9 billion tenge was earmarked to continue construction, with 10 kilometers of the pipeline built so far. Furthermore, 20.5 billion tenge has been allocated from the Infrastructure Development Fund of the Republic of Kazakhstan to continue construction work.
Gasification
Efforts to gasify settlements in the Kyzylorda region are actively proceeding.
Currently, all cities (Kyzylorda, Aral, Kazaly, and Baikonur) have 100% gasification coverage. The number of rural settlements connected to the gas network has reached 56.
By the end of 2025, the region's gasification rate had reached 83%.
In 2026, 4.3 billion tenge was allocated for the implementation of 14 projects (3.6 billion tenge from the national budget and 0.7 billion tenge from the regional budget). Of these, two are carry-over projects, and 12 are new.
Additionally, a budget request has been submitted during the national budget revision process for 19 projects with a total cost of 8.1 billion tenge.
Thus, plans are in place to complete gasification projects for 10 settlements (Akzharma, Kamystybas, Kogalykol, Shirkeili, Torebay Bi, Irkol, Bekarystan Bi, Zhankozha Batyr, Tuktibayev, and Maidakol) by the end of the year, raising the gasification rate from 83% to 85%.
Coal supply
The planned coal consumption for the region for the 2026–2027 heating season is 107,000 tons. This includes 88,000 tons for the population and 19,000 tons for social facilities. Currently, coal stocks at depots stand at 29,700 tons.
There are 20 regional operators (6 limited liability partnerships and 14 individual entrepreneurs) active in the region; coal is sold at prices ranging from 22,000 to 28,500 tenge, depending on the grade and delivery distance.
The issue of supplying coal to the population and social facilities is under the constant supervision of the regional Akimat.
Heat supply
Preparatory work for the upcoming heating season across the region has been carried out in accordance with the approved action plan. This year, 5.5 billion tenge has been allocated for the renovation of heat supply facilities. These funds have enabled the completion of a project to renovate 8.7 km of heating networks and the major overhaul of one gas turbine unit. Additionally, repair work has been fully completed on 1.3 km of heating networks, one boiler house, one turbine, and ten autonomous boiler units, as well as on primary and auxiliary equipment. Hydraulic testing of the heating networks has also been conducted.
Furthermore, during the upcoming heating season, heat will be supplied from a new thermal power plant utilizing four heating boilers.
Preparations for the heating season have been carried out across 1,079 social facilities in the region, including 505 educational institutions, 247 healthcare facilities, 322 cultural and sports facilities, and 5 social service facilities.
To date, certificates of readiness for the upcoming heating season have been issued for both energy and social facilities.
Preparations for the upcoming heating season are being continuously monitored.
Regarding the electric power sector:
Currently, the region's power supply infrastructure comprises 10,608 km of electrical networks and 2,058 substations of various voltage classes; the level of infrastructure wear and tear stands at 60%.
Plans for 2026 include the implementation of nine projects with a total value of 3.1 billion tenge, involving the renovation of 240 km of overhead power transmission lines and 52 substations. These measures aim to reduce the wear and tear level from 60% to 59%. In addition, the following works are planned:
Replacement of the 2.5 km 35 kV overhead power transmission line (L-33, 34)—which supplies electricity to the SPMK-70, Arai, Salet, and Sayakhat neighborhoods—with a cable line;
Reconstruction of the 35/10 kV "Zhanaaryk" substation, which supplies electricity to the settlements of Sabalak, Nauryz, Makhambet, and Aksuat;
Reconstruction of 30.6 km of 35 kV overhead power transmission lines (L-51, 52, 55, 56) supplying electricity to the Tasboget settlement; the villages of Besaryk, Amangeldy, Zhetikol, Aidarly, Zhambyl, and Makhambetov; and the central part of the Aksuat rural settlement.
Budget requests have been submitted for the 2026–2027 period, seeking funding from regional and republican budgets to continue construction and installation work on the following projects: "Reconstruction of the 110 kV overhead line L-105 (Ayteke Bi substation) in the Kazaly District of the Kyzylorda Region," "Power supply for the left-bank area of the Syr Darya River in the city of Kyzylorda" (Phase 2), and "Reconstruction of the 220/35/10 kV 'Shieli' substation in the settlement of Shieli, Kyzylorda Region."
Additionally, a list of 123 facilities has been approved for transfer to the balance sheet of JSC "KETTK," and the necessary documentation is currently being prepared.
Urban Improvement
In 2026, 8.9 billion tenge has been allocated from the regional budget to implement seven urban improvement projects.
These projects include the reconstruction of the First President Park; the construction of 27 children's playgrounds; major repairs to the facades of eight apartment buildings in Kyzylorda; the construction of pedestrian walkways in two settlements (Akzharma and Talsuat) within the Kyzylorda city area; the reconstruction of street and road infrastructure in Kyzylorda; and the reconstruction of irrigation ditch networks in the village of Nagi Ilyasov, Syrdarya District.
Furthermore, under public-private partnership agreements, 3.7 billion tenge has been allocated from the regional budget for 2026 to continue work on the projects "Greening and improvement of the city of Kyzylorda" and "Reconstruction and maintenance of outdoor lighting systems in the city of Kyzylorda"; these works are currently underway. Hot Water Supply
In accordance with the directive of the Head of State, a project is underway to provide hot water supply to multi-story residential buildings in the city of Kyzylorda. The project aims to supply hot water to 423 multi-story residential buildings at a total cost of 26.2 billion tenge.
The project is being implemented in two stages.
Stage One: In 2024, 11 billion tenge was allocated from the state reserve to provide hot water supply to 186 buildings.
Stage Two: 5 billion tenge was allocated from the reserve of the Government of the Republic of Kazakhstan, and construction and installation works were completed for 61 multi-apartment residential buildings in Kyzylorda.
Additionally, to fully execute the directive, 10.2 billion tenge was allocated from the Special State Fund to provide hot water to 176 multi-apartment residential buildings, and the associated construction and installation works have been completed. Currently, work is underway to connect these multi-apartment residential buildings to the hot water supply system.
Payments to specific categories of citizens for housing rented in the private sector
Work is proceeding in accordance with the Head of State's directive to provide affordable rental housing to socially vulnerable segments of the population; JSC "Otbasy Bank" (formerly Zhilstroibank) has been designated as the financial operator for making these rental payments to citizens.
For the year 2026, 161,854.5 thousand tenge has been allocated from the regional budget to make payments to specific categories of citizens for housing rented in the private housing stock. JSC "Otbasy Bank" makes monthly payments to over 900 citizens. Regarding Dilapidated Housing
In the Kyzylorda region, expert assessments have designated 69 apartment buildings as dilapidated (63 in the city of Kyzylorda, 3 in the Karmakshy district, 2 in the Syrdariya district, and 1 in the Zhalagash district).
There are 673 families on the housing waiting list whose only homes have been declared dilapidated. In 2025, 135 apartments were purchased and allocated using regional budget funds, and three dilapidated buildings were demolished.
For 2026, 1.7 billion tenge has been allocated from the regional budget to purchase apartments for families in the city of Kyzylorda whose only homes have been declared dilapidated.
Repair Work on Apartment Buildings
There are 1,505 apartment buildings in the Kyzylorda region, 601 of which (40%) require major repairs. The proportion of condominium properties requiring major repairs has decreased from 73% (in 2011) to 40%.
In 2024, repairs were carried out on 33 apartment buildings at a cost of 2.1 billion tenge, funded by republican budget loans; this included 18 buildings in Kyzylorda city, 6 in the Aral district, 2 in the Zhalagash district, and 7 in the Syrdariya district. For 2025, a budget request totaling 1.4 billion tenge was submitted to repair 14 buildings, but funds were not allocated.
For 2026, a budget request totaling 4.0 billion tenge has been submitted to the Ministry of Industry and Construction of the Republic of Kazakhstan for the repair of 24 apartment buildings.
Information on the work of the Kyzylorda Region Department of Energy and Housing and Public Utilities for the first six months of 2026
Gas supply:
Work to gasify populated areas is actively underway in the Kyzylorda Region.
Currently, there are 4 cities and 222 rural settlements in the region. Currently, all cities (Kyzylorda, Aral, Kazaly, and Baikonur) have 100% gasification. The number of rural settlements with gasification has reached 56.
By the end of 2025, the region's gasification rate will reach 83%.
In 2026, 4.3 billion tenge has been allocated for the implementation of 14 projects (3.6 billion tenge from the national budget and 0.7 billion tenge from the regional budget). Of these, two projects are ongoing, and 12 are new. In addition, budget requests for 19 projects totaling 8.1 billion tenge have been submitted for revision of the republican budget.
Thus, by the end of the year, gasification projects are planned for 10 settlements (Akzharma, Kamystybas, Kogalykul, Shirkeyli, Torebai bi, Irkol, Bekarystan bi, Zhankozha batyr, Tuktibayev, and Maidakul), increasing the gasification rate from 83% to 85%.
Concerning coal supply:
The regional coal consumption plan for the 2026-2027 heating season is 111,000 tons. This includes 92,000 tons for the population and 19,000 tons for social facilities. Currently, coal reserves in coal depots amount to 9,500 tons. There are 20 regional operators (6 limited liability companies and 14 entrepreneurs) operating in the region. Coal is sold at prices ranging from 17,000 to 26,000 tenge, depending on the grade and delivery distance.
The regional akimat constantly monitors the supply of coal to the population and social facilities.
Drinking Water Supply
There are 4 cities and 222 rural settlements in the region.
All cities have a 100% drinking water supply. The percentage of the population with centralized drinking water supply is 100%.
In 2026, 11.9 billion tenge has been allocated for water supply and sanitation projects. Seven projects are currently underway.
Following the projects, it is planned to reduce the depreciation rate of water supply networks from 33% to 31%, and sewerage networks from 32% to 30%. In addition, the project to build two branches of the Aral-Sarybulak group water pipeline, with a total length of 234 km, is ongoing. It supplies drinking water to over 160,000 residents of the Aral and Kazaly districts.
The total cost of the project is 43.7 billion tenge. In 2025, 5.5 billion tenge was allocated from the republican budget, which was used to complete the construction of 23 km of water supply networks.
In 2026, 2.5 billion tenge have been allocated for continued construction, including the construction of an additional 10 km of water supply network.
Regarding dilapidated buildings
In the Kyzylorda region, there are 69 apartment buildings that have been declared dilapidated by expert assessments. These include 63 buildings in Kyzylorda, two buildings in the Syrdarya district, one building in the Zhalagash district, and three buildings in the Karmakshin district. There are 700 residents registered on the housing waiting list whose only home has been declared unsafe. Of these, 669 families are in Kyzylorda, 18 in the Syrdarya district, and 13 in the Zhalagash district.
In 2025, 135 apartments were transferred from the regional budget, and three unsafe buildings were demolished.
In 2026, 1.7 billion tenge has been allocated from the regional budget for the purchase of apartments for 135 families whose only home has been declared unsafe.
Major Repairs of Multi-Story Residential Buildings
There are 1,505 multi-apartment residential buildings in the Kyzylorda region, of which 601 require major repairs (40%) (a decrease from 73% to 40% in 2011).
In 2024, capital repairs of 33 multi-story residential buildings (2.1 billion tenge) were carried out using a republican budget loan. These include 18 buildings in Kyzylorda, 6 in the Aralsky District, 2 in the Zhalagash District, and 7 in the Syrdarya Region. A budget request for 1.4 billion tenge was submitted for capital repairs of 14 buildings in 2025, but funds have not been allocated.
In addition, a budget request for 2.5 billion tenge was submitted to the Ministry of Industry and Construction of the Republic of Kazakhstan for capital repairs of 17 multi-story residential buildings.
On payments to citizens for housing
In accordance with the instructions of the Head of State, work is underway to provide socially vulnerable groups with affordable rental housing. JSC Zhilstroysberbank Otbasy has been appointed the financial operator for paying rent to citizens.
In 2026, the regional budget allocated 73,944,000 tenge for payments to certain categories of citizens for housing from the private housing stock. JSC Otbasy Bank makes payments to over 800 citizens monthly.
Regarding the housing waiting list
As of July 1, 2026, over 61,000 people were registered on the housing waiting list in the region. Effective May 24, 2025, Otbasy Bank JSC was assigned the functions of coordinating the waiting list system. From October 2025 to the present, the Akimat of the Kyzylorda Region transferred 9 projects to the Bank 62 apartments are being allocated to those on the waiting list, of which 805 (84%) have been allocated.
A total of 1,602 families were provided with housing in 2025, and 202 families in 2026.
In the Electric Power Sector
Currently, the region's total power supply system length is 10,608 km of power lines and 2,058 substations of various voltage classes, with a depreciation rate of 60.8%.
In 2025, 6 billion tenge was allocated for the implementation of six power supply projects, which included the reconstruction of 280 km of power lines and 87 substations (Kozhabahy village in Kazaly district, Kazaly town, Kalzhan akhun village in Syrdarya district, Shieli village in Shieli district, Kodamanov village in Shieli district, Zhanakorgan district, and Ainakol village in Kyzylorda). In 2026, nine projects totaling 3.1 billion tenge are planned for implementation, including the reconstruction of 240 km of overhead power lines and 52 substations. This will reduce the depreciation rate from 60% to 59%.
Additionally, the following work is planned:
Replacement of 2.5 km of the 35 kV L-33.34 overhead power line, which supplies power to the SPMK-70, Aray, Salet, and Sayakhat microdistricts, with a cable line;
Reconstruction of the 35/10 kV Zhanaaryk substation, which supplies power to the settlements of Sabalak, Nauryz, Makhambet, and Aksuat;
Reconstruction of 30.6 km of 35 kV overhead power lines L-51, 52, 55, and 56, providing power to the village of Tasboget, Besaryk, Amangeldy, Zhetikol, Aidarly, Zhambyl, and Makhambetov, as well as the central part of the rural settlement of Aksuat.
To date, construction and installation work has been completed and the project "Construction of a 40 MW thermal boiler plant on the left bank of the Syr Darya River in Kyzylorda. External networks" has been commissioned.
Budget requests for funding from the regional and national budgets were submitted for the 2026–2027 budget update to continue construction and installation work on the following projects: "Reconstruction of the 110 kV L-105 Power Line, Aiteke Bi, Kazaly District, Kyzylorda Region," "Power Supply to the Left Bank of the Syr Darya River in Kyzylorda City" (Phase 2), and "Reconstruction of the 220/35/10 kV Shieli Substation in Shieli Village, Kyzylorda Region."
Regarding Heat Supply
The 2025–2026 heating season in Kyzylorda Region ended on April 1.
During the heating season, all social facilities (1,079) and multi-story residential buildings were provided with a stable and uninterrupted supply of heat.
Essential utilities operated as normal. Heat supply was maintained in accordance with the outside temperature.
To ensure a stable and uninterrupted supply during the 2025–2026 heating season, the Kyzylorda Thermal Power Plant (KTPP) was allocated a subsidy of 375 million tenge for the purchase of gas fuel.
In 2026, 3.6 billion tenge was allocated from the republican budget to complete six ongoing heat network modernization projects. This year, construction work on the project was fully completed, and commissioning of the facilities is currently underway. As a result, the depreciation rate of the heating networks has decreased by 2 percent (from 42% to 40%).
New Thermal Power Plant
In accordance with the instructions of the Head of State, a new thermal power plant with a capacity of 240 megawatts of electricity and 277 gigacalories of thermal energy was built in the city of Kyzylorda.
The total cost of the project is 215 billion tenge. The Turkish company Aksa Energy is the investor in the thermal power plants.
The thermal power plant is currently operational and producing the electricity required by the project.
The new thermal power plant will be launched during the upcoming heating season and will provide residents with uninterrupted, high-quality heat and electricity.
Landscaping
For 2026, 6.4 billion tenge has been allocated from the regional budget to complete the "Reconstruction of the First President's Park in Kyzylorda (Adjustment)" project.
Additionally, as part of a public-private partnership, 3.7 billion tenge has been allocated from the regional budget for 2026 to continue work on the "Landscaping and Improvement of the City of Kyzylorda, Kyzylorda Region" and "Reconstruction, Maintenance, and Upkeep of Outdoor Lighting Systems in Kyzylorda" projects, and work is underway. In addition, 119.4 million tenge was allocated for the construction of pedestrian paths in two villages (Akzharma and Talsuat) in Kyzylorda, and construction on these projects is currently complete.
Furthermore, 1 billion tenge was allocated for the construction of 30 playgrounds on the grounds of multi-story residential buildings in Kyzylorda, and construction is currently underway.
Hot Water Supply
In accordance with the instructions of the Head of State, a project to provide hot water to multi-story residential buildings in Kyzylorda has been launched. The project plans to provide hot water to 423 multi-story residential buildings at a total cost of 26.2 billion tenge.
The project is being implemented in two stages.
Stage One:
In 2024, 11 billion tenge was allocated from the state reserve to provide hot water to 186 buildings.
Second stage: 5 billion tenge was allocated from the Government of the Republic of Kazakhstan reserve, and construction and installation work was completed on 61 apartment buildings in Kyzylorda.
Furthermore, to fully implement the order, 10.2 billion tenge was allocated from the Special State Fund to fully provide hot water to 176 apartment buildings. Construction and installation work is currently underway.
Information on the work done by the Department of Energy and Housing and Communal Services of the Kyzylorda Region for the 6 months of 2025
On gas supply
As of 30.06.2025, the level of provision of the region's population with natural gas was 81%.
In the region, all cities (Kyzylorda, Baikonur, Aral, Kazaly) and district centers (6 district centers) and 45 rural settlements are connected to natural gas.
For 2025, 6.1 billion tenge were allocated from the budget for the implementation of 11 gas supply projects. Including: the republican budget - 4.6 billion tenge, JSC Samuryk-Kazyna AK - 8.5 billion tenge, the regional budget - 1.5 billion tenge.
As of 30.06.2025, 7 gas supply projects have been completed for 6 rural settlements (Shizhaga, Ortakshil, Baymurat, Taldyaral, Aktan Batyr, N.Ilyasov) with a total population of about 7 thousand people. By the end of the year, it is planned to increase the level of gas supply to the region to 82%, the number of gasified settlements to 53.
Coal supply
The coal consumption plan for the 2025–2026 heating season in Kyzylorda region is 139.3 thousand tons. Of these: for the population – 117.4 thousand tons, for social facilities – 21.9 thousand tons.
To date, according to JSC Kazakhstan Temir Zholy, 5.9 thousand tons of coal have been delivered to the region.
There are 19 regional operators (6 LLPs and 13 entrepreneurs) operating within the region; coal is sold at a price of 19,000 to 26,000 tenge, depending on the grade and delivery distance.
The issue of providing the population and social facilities with coal is under the constant control of the regional akimat.
Water supply and sanitation
There are 4 cities and 223 rural settlements in the region.
All cities are 100 percent supplied with drinking water.
The share of the population provided with centralized drinking water supply is 98.6 percent.
In accordance with the instruction of the head of state, a special roadmap has been developed to provide the remaining 23 settlements with high-quality drinking water by the end of 2025. In accordance with the roadmap, it is planned to connect the settlements of Yerimbetzhaga and Tastubek of the Aralsky district to the group water supply line, as well as to build internal water supply networks in the settlements of Shaken, Shili, Sarbulak and Shitubek of the Kazalinsky district.
440 million tenge from the republican budget, 1.3 billion tenge from the special state fund and 432.6 million tenge from the regional budget are allocated for connecting the settlements of Yerimbetzhaga and Tastubek of the Aralsky district to the group water supply. For the projects of construction of internal water supply networks in the settlements of Shaken, Shili, Sarbulak and Shitubek of the Kazalinsky district, 347 million tenge from the republican budget, 847 million tenge from the special state fund and 298.9 million tenge from the regional budget have been allocated. Construction and installation work on the projects is currently underway. As a result, 83 km of water pipelines will be laid and about 6 thousand people will be connected to the centralized water supply system. As a result of the work carried out, the level of provision of settlements with high-quality drinking water will be 100 percent. Also, 3 billion tenge were allocated from the republican budget for the start of the project to build the second branch of the Aral-Sarybulak group water pipeline, 720.8 million tenge for the reconstruction of biological treatment facilities in the city of Kyzylorda, and 101.4 million tenge for the reconstruction of the sewage pumping station on Gagarin Street in Kyzylorda.
In addition, 1.2 billion tenge were allocated from the regional budget for the construction of 6 projects. Construction work is underway.
As a result of the work carried out, the level of wear and tear of water supply networks will decrease to 33 percent, and the level of wear and tear of sewer networks will decrease to 32 percent.
By power supply
The total length of the region's power supply systems is 10,491 km of electrical networks and 2,018 transformer substations of various voltages. Network wear is 62%.
In 2025, projects worth a total of 6 billion tenge are being implemented, including 3.1 billion tenge - modernization of 280 km of electrical networks, 2.9 billion tenge - reconstruction of 87 transformer substations.
Under the investment program of JSC "Kyzylorda Company for Distribution of Electric Networks", 40.2 km of overhead lines are being reconstructed for a total of 532.6 million tenge. At the same time, at the expense of JSC's own funds in the amount of 336.9 million tenge, repair work is being carried out on 59.5 km of electrical networks, including 14.59 km of 35 kV overhead lines (major repairs), 7.85 km (current repairs), 10 kV overhead lines - 10.2 km (major repairs), 3.1 km (current repairs), 18.56 km of 0.4 kV overhead lines (major repairs), 4.7 km (current repairs), 0.4 kV cable lines - 0.45 km, 97 transformer substations - major and current repairs (period: 01.05 - 31.08.2025). According to the project for the reconstruction of the 220/35/10 kV substation in Shieli: work on the 35 kV outdoor switchgear has been completed, consumers are being connected; for 220 kV outdoor switchgear - approval by JSC KEGOC.
According to the project for the reconstruction of 10/0.4 kV electric networks in Zhanakorgan, the reconstruction has been completed, meters are being installed.
Design and estimate documentation has been developed and a positive conclusion has been received from the state examination of the project "Power supply of the left-bank part of the Syr Darya River in the city of Kyzylorda (stage 2)".
At the same time, in 2025, it is planned to transfer 52 objects to the balance sheet of JSC KETTK, of which 19 objects have already been transferred.
On heat supply
In total, 13.5 billion tenge have been allocated for the modernization of heat supply facilities this year (5.2 billion tenge from the republican budget, 2.5 billion tenge from the Government reserve, 5.4 billion tenge from the regional budget, and 364 million tenge from the own funds of the State Enterprise "KTEC").
Including:
To complete the modernization of three steam boilers of the BONO ENERGY Yuzhny brand at the Kyzylorda Thermal Power Plant, 2,524 million tenge have been allocated from the Government reserve and 1,329 million tenge from the local budget. Construction work is underway.
In addition, preparations are underway for the upcoming heating season at the Kyzylorda Thermal Power Plant.
A generator and 1 power transformer are being modernized at the expense of the local budget and the company's funds, and 10 steam boilers and 21 autonomous boilers are being repaired. Currently, the work is 46 percent complete.
Modernization of heating networks
The budget has allocated 7,403 million tenge for the implementation of 6 projects to modernize heating networks. Construction and installation work is currently underway on the projects. As a result of the work carried out, the wear and tear of heating networks will decrease by 2 percent (from 42% to 40%).
On hot water supply
As you know, during the working visit of the Head of State to our region, an order was given to solve the problems of hot water supply to the city of Kyzylorda. In this regard, a project for 423 residential buildings with a total cost of 26.2 billion tenge was developed. The project is being implemented in 2 stages.
In 2024, the first stage allocated 11 billion tenge from the Government reserve to provide hot water to 187 houses.
At the second stage, it is planned to provide hot water to 236 multi-storey buildings for 15.2 billion tenge.
This year, 5 billion tenge were allocated from the Government reserve to provide hot water to multi-storey residential buildings in the Akmechet and Merey microdistricts.
New Thermal Power Plant
In accordance with the instructions of the Head of State, in order to eliminate the electricity deficit in the southern regions, a new thermal power plant with a capacity of 240 megawatts is being built in the city of Kyzylorda. The investor in the project is the Turkish company Aksa Energy, the total investment is 215 billion tenge. To date, more than 137 billion tenge have been invested in the construction of the thermal power plant. The commissioning of the station is planned for the 4th quarter of 2025.
On the improvement of settlements
For the current year, 18.4 billion tenge have been allocated from the regional budget for the implementation of 9 projects for the current repair of parks and the central square, the reconstruction of the amusement park, and major repairs of the facades of multi-story buildings in the city of Kyzylorda. Work is currently underway.
In addition, the public-private partnership projects "Reconstruction, maintenance and upkeep of outdoor lighting systems in the city of Kyzylorda" and "Greening and improvement of the territory of the city of Kyzylorda, Kyzylorda region" are being implemented.
On emergency housing
As of July 1, 2018, there are 69 apartment buildings in the Kyzylorda region that have been recognized as emergency housing based on expert assessments. Of these, 66 buildings are in the city of Kyzylorda, 2 buildings are in the Syrdarya district, and 1 building is in the Zhalagash district.
A total of 648 families are registered on the housing waiting list for apartment buildings whose only living space has been recognized as emergency housing. Of these, 617 families are in the city of Kyzylorda, 18 families are in the Syrdarya district, and 13 families are in the Zhalagash district.
In 2024, 135 apartments were purchased and transferred using 1.7 billion tenge allocated from the regional budget.
For 2025, 1.7 billion tenge has been allocated from the regional budget to purchase apartments for 135 families whose only housing has been recognized as emergency housing.
Major repairs of multi-storey residential buildings
As of July 1, 2025, the share of condominium properties requiring major repairs decreased from 800 in 2011 to 601 buildings (or decreased from 73% to 42.5%). For 2025, a budget application was submitted to the Committee for Construction and Housing and Public Utilities of the Ministry of Industry and Construction of the Republic of Kazakhstan to allocate funds from the republican budget for the major repairs of 14 multi-storey residential buildings.
On payment of housing fees by citizens
Work is underway in accordance with the instructions of the Head of State to provide socially vulnerable groups of the population with affordable rental housing. JSC Zhilstroysberbank has been appointed the financial operator for paying rent to citizens for housing. As of July 1, 2025, JSC Zhilstroysberbank has concluded agreements and makes monthly payments to 899 citizens.
By housing queue
As of 1 July 2025, the number of citizens registered in the housing queue is 36,680. Including:
- Orphans and children left without parental care - 1,859;
- Mothers with many children, families with many children, awarded with the pendants "Altyn Alka", "Kumis Alka" or previously received the title of "Mother Heroine", as well as awarded with the Order of "Maternal Glory" of the 1st and 2nd degrees - 9,850;
- Socially vulnerable groups of the population - 14,006;
- Civil servants, employees of budgetary organizations, military personnel and persons holding state elected positions - 10,562;
- Citizens whose only home is recognized as emergency in the manner established by the legislation of the Republic of Kazakhstan - 700.
Information on the work done for 12 months of 2024 by the Department of Energy and Housing and Communal Services of the Kyzylorda Region
On emergency buildings
In the Kyzylorda Region, 65 apartment buildings have been recognized as emergency buildings according to expert opinions (62 buildings in the city of Kyzylorda, 2 buildings in the Syrdarya district, 1 building in the Zhalagash district).
As of December 31.2024, 790 families of apartment buildings are on the waiting list, whose only housing has been recognized as emergency (763 families in the city of Kyzylorda, 18 families in the Syrdarya district, 9 families in the Zhalagash district).
In 2022-2023, 100 families received apartments in this category,
In 2024, KZT1672.7 million were allocated from the regional budget for the purchase of apartments for families in the city of Kyzylorda, whose only housing is recognized as emergency. Purchase agreements have been concluded for 123 apartments.
Carrying out repair work in apartment buildings
The share of condominium objects requiring major repairs has decreased from 800 to 601 buildings (from 73% to 42.5%).
In 2024, 2.1 billion tenge were allocated from the republican budget for the repair of 33 apartment buildings (Kyzylorda - 18, Aral - 6, Zhalagash - 2, Syrdarya 7 buildings).
A budget application for KZT 1.6 billion was submitted to the Ministry of Industry and Construction to carry out repair work on 18 buildings.
Implementation of payments to certain categories of citizens for housing rented in the private sector
Work is underway in accordance with the instructions of the Head of State to provide affordable rental housing to socially vulnerable groups of the population. JSC Zhilstroibank Otbasy Bank has been appointed as the Financial Operator for paying rent to citizens for housing. As of December 31, 2024, JSC Otbasy Bank supported 1,639 applications, of which 755 citizens receive monthly payments, 72 contracts are concluded.
By housing queue
The number of citizens on the housing queue is 33,234.
Including:
- Orphans and children left without parental care is 2020;
- Holders of the pendants "Altyn alka", "Kumis alka", "Batyr ana", "Ana danky" of the 1st and 2nd degree, mothers with many children and families with many children – 9490;
- Socially vulnerable groups of the population - 13909;
- Civil servants, employees of budgetary organizations, military personnel and persons holding state elected positions - 10025;
- Citizens whose only home is recognized as emergency in the manner established by the legislation of the Republic of Kazakhstan - 790.
In 2024, 1235 citizens on the housing queue were provided with housing.
Energy Information
There are 10491 km of power grids and 2008 substations in the Kyzylorda region. Their level of wear is 66%.
In 2024, KZT 5.7 billion were allocated for the implementation of 10 projects.
These funds were used to reconstruct 418 km of power grids and 73 substations.
In addition, the investment program of the Kyzylorda Distribution Electricity Grid Company Joint-Stock Company amounted to KZT 1,682.4 million, and 103.56 km of power grids were reconstructed.
As a result, the level of wear of the grids was reduced from 66.0% to 62%.
About drinking water supply
There are 4 cities and 223 settlements in the region.
The share of the city population connected to centralized drinking water is 100%.
In the region, out of 223 rural settlements, 201 or 98.6% of the population are connected to the centralized water supply system. About 6 thousand people or 1.4% of the rural population live in the remaining 22 villages.
In accordance with the instructions of the head of state, a roadmap has been developed to provide high-quality drinking water to the remaining 22 settlements by the end of 2025, and the work is being carried out according to plan.
As part of the roadmap, it is planned to connect 5 settlements to a group water supply system, build an internal water supply system in 3 settlements, install a CBM (complex block module) in 2 settlements and leave 12 settlements in their current state.
In 2024, KZT 2.7 billion were allocated for the implementation of 11 projects (including 5 new projects, 6 carry-over projects) (including KZT 2.4 billion from the Republican budget, KZT 0.3 billion from the regional budget). As part of the 2024 projects, 88 km of water pipes and 23 km of sewer networks were modernized, as a result of which the level of depreciation of water supply networks decreased to 35%, sewer networks to 32%.
For heat supply
KZT 12 billion were allocated for the modernization of heat supply facilities in 2024-2025 (from the republican budget – KZT 8.3 billion, from the regional budget – KZT 3 billion, from the own funds of the KTETs enterprise – KZT 566 million).
These funds are used to modernize three Bono Energy steam boilers at the KTEC, 2 gas turbine units, overhaul 11 boilers and 1 turbine, and carry out routine repairs on 15 boiler houses.
In addition, 9.3 km of heating networks were modernized to modernize heating networks. As a result, the level of wear and tear of heating networks decreased by 3 percent (from 45% to 42%).
In 2025, there are 6 projects to modernize heating networks with a length of 8.7 km. Of the total need of KZT 2.1 billion, KZT 7.4 billion have been allocated. As a result, the level of wear and tear of heating networks will decrease by 2% (from 42% to 40%). The heating season in the region this year, starting from October 10, 889 multi-storey residential buildings and 1067 social facilities (532 - education, 247 - health, 288 - culture and sports), connected to the centralized heating system, are fully provided with heat.
On hot water supply
During the working visit of the head of state to our region, an order was given to resolve the issue of hot water supply in the city of Kyzylorda.
In the city of Kyzylorda, hot water supply is planned for 624 multi-storey residential buildings. In particular, work is underway to connect 201 new residential buildings to the hot water supply. In addition, design and estimate documentation has been developed for 423 houses. The total cost of the projects is KZT 26.2 billion. This year, KZT 11 billion were allocated from the Government reserve for hot water supply to 187 houses, residential buildings have been connected to hot water. In addition, in 2025, it is planned to provide hot water to the remaining 236 multi-storey residential buildings.
New thermal power plant
In accordance with the instruction of the Head of State, in order to prevent a shortage of electric energy in the southern regions, 215 billion tenge of electricity with a capacity of 240 MW will be sold in the city of Kyzylorda. The investor in the project is the Turkish company - "Aksa Energy".
The investor invested more than KZT 133 billion in investments in the construction of the thermal power plant.
The preparation of the main installations is ordered from foreign companies, gas turbine units and thermal boilers are installed.
The launch of the station is planned for the 4th quarter of 2025.
In addition, the cost at the expense of the budget will be KZT 15 billion, the gas supply project of the thermal power plant is being implemented. To date, the work is 90% complete.
The new thermal power plant will fully cover the territory of the region with the need for electricity and send it to other regions.
Improvement
In 2024, a total of KZT 6.5 billion was allocated from the regional and republican budgets for 16 projects on improvement of the region, major repairs of pedestrian paths, facades, street lighting, and the corresponding work was carried out.
On gas supply
In 2024, funds from the republican budget of KZT 3.9 billion, from the regional budget of KZT 2.6 billion, and from the Samruk-Kazyna JSC fund of KZT 24 billion were allocated for gasification projects.
The work on gasification of 11 settlements planned for the specified funds has been fully completed and connected to natural gas. Instead of the planned 400 kilometers of gas pipelines, 461 kilometers (115%) of gas pipelines have been built. 11 settlements - Almaly, Aktogan, Bestam, Abay, Toretam, Tomenaryk, Aksu, Shamenov, Seifullin, Tokmaganbetov, Saksaulsk.
Thus, by the end of 2024, the level of gasification of the region increased to 78%, and the number of gasified settlements to 46.
At the beginning of 2025, gasification work in 4 settlements was fully completed and connected to the gas supply system.
4 settlements - Shizhaga, Ortakshil, Baymurat, Taldyaral.
At the same time, by the end of the year, it is planned to gasify 5 settlements and bring the gasification level to 83 percent.
5 settlements - Aktan Batyr, Dur Ongar, Shagan, N.Ilyasov, Sabalak.
On coal
The coal consumption plan for the 2024-2025 heating season in the Kyzylorda region is 162.5 thousand tons. Of these, 135.7 thousand tons are for residents, 26.8 thousand tons are for social facilities.
According to Kazakhstan Temir Zholy JSC, 137.9 thousand tons of coal have been delivered to the region to date. Currently, there are 26.5 thousand tons of coal in coal warehouses.
There are 26 regional operators (9 LLPs and 17 entrepreneurs) operating in the region, and coal is sold at 19,000-26,000 tenge, depending on the brand and delivery distance.
The issue of providing residents and social facilities with coal is under the constant control of the regional akimat.
Information on the work done in 9 months of 2024 by the department of energy and housing and communal services of the Kyzylorda region
Gasification report for the third quarter of 2024. Currently, the level of provision of the region's population with natural gas is 75%.
All cities (Kyzylorda, Baikonur, Aral, Kazaly) and district centers (6 district centers), as well as 29 rural settlements, are connected to natural gas in the region.
This year, KZT 3.9 billion will be allocated from the republican budget for gasification projects, KZT 2.6 billion from the regional budget, and KZT 24 billion from the Samruk-Kazyna JSC fund.
306 kilometers of gas pipelines were built with these funds. It is planned to implement 24 projects. Currently, 5 settlements (Almaly, Bestam, Aktogan, Toretam, Tomenaryk) have been completed and connected to natural gas. 216 km of the planned 306 km of gas pipeline have been built. Thus, it is planned to increase the level of gasification of the region to 78%, and the number of gasified settlements - to 46.
About coal supplies. The volume of coal required for the upcoming heating season in the region is 162.5 thousand tons, including: for residents - 135.7 thousand tons, for social facilities - 26.8 thousand tons. Currently, 31 thousand tons of coal reserves are stored in coal warehouses, or 19% (45.7 thousand tons have been sold). Coal (Shubarkol, Karazhira, Ekibastuz) is sold at a price from 17 thousand tenge to 23 thousand tenge. There are 26 regional operators registered in the region and 20 coal warehouses.
On water supply. 204 of the 230 rural settlements of the region, or 98.4% of the population, are connected to the centralized drinking water supply system. The remaining 26 villages are home to more than 7 thousand people, or 1.6% of the rural population.
In the message of the Head of State in 2021, the Government was instructed to provide 100 % of the population with clean drinking water within the next five years. In this regard, a phased plan for providing 100% of the population with drinking water in 26 settlements is being developed and work is underway.
In 2024, KZT 2.5 billion will be allocated from the republican and regional budgets for 11 drinking water supply and sanitation projects. Construction and installation work is currently underway.
As a result, 82 kilometers of drinking water supply and 18.4 kilometers of sewer networks will be modernized.
On power supply
Today, the total length of the region's power supply systems is 10,491 km of power lines and 2,008 substations of various voltages, the degree of wear of which is 66%.
This year, a total of 38 projects have been implemented to modernize electrical systems. KZT 9 billion was allocated. It is planned to build 786 kilometers of power lines and repair 175 substations with the allocated funds. To date, 140.4 power lines have been repaired and 42 substations have been installed. This year, 38 projects to modernize power grids have been implemented.
This year, KZT 9 billion have been allocated. It is planned to build 786 kilometers of power lines and repair 175 substations with the allocated funds. Currently, 140.4 power lines have been repaired and 42 substations have been installed. In addition, KZT 1.6 billion from the regional budget, major repairs and modernization of 46 transformer substations, modernization of 23.7 kilometers of power transmission lines are carried out. In addition, 4 units of special auto equipment will be purchased. KZT 460 million in 2024 under the investment program. For the repair of telemetry and SCADA systems, 33.36 kilometers of 10/0.4 kV power lines and 1 unit of 35/10 kV substation are planned.
As a result, it is expected that the level of wear of power lines will decrease from 66% to 62%.
For the project for the reconstruction of the 220/110/35/10 kV substation "Shieli" in the village of Shieli for 2024, a positive conclusion of the state examination was received and KZT 1.5 billion was allocated from the National Fund. Equipment was ordered by the contractor.
On heat supply
Preparations for the upcoming heating season in the region are being carried out according to the approved action plan.
Financing in the amount of KZT 12 billion (KZT 8.3 billion from the republican budget, KZT 3 billion from the regional budget, KZT 566 million from the enterprise's own funds) was considered for modernization of heating networks this year. Including:
KZT 2 billion from the budget for the modernization of three Bono Energy steam boilers of Kyzylorda thermal power station. 700 million tenge was allocated. Currently, a contractor has been determined and construction work is beginning.
At the expense of the local budget and the finances of the enterprise, major repairs are being carried out on 11 boilers with generators of 2 gas turbine units, routine maintenance of 1 turbine and 15 boilers. At the moment, the work is 59% complete.
The length of the region's heating networks is 216 kilometers, the degree of wear is KZT 44.6. 6 billion from the budget for the implementation of 6 projects to modernize heating networks this year. KZT 900 million were allocated. To date, out of 9.5 km of heating networks, 2.3 km have been completed by 24% . At the same time, the total number of 1067 social facilities in the region (532 educational facilities, 247 healthcare facilities, 288 cultural and sports facilities) is 59 percent (including educational facilities - 57%, healthcare - 62%, cultural and sports facilities - 60%). In general, preparations for the upcoming heating season are under constant control.
Improvement works
In 2024, KZT 6.5 billion will be allocated from the republican and regional budgets for the implementation of 19 improvement projects in the region. This funding includes the construction of 57 kilometers of pedestrian paths on 56 streets. Repair of the facades of 26 apartment buildings and lighting work will be carried out on 54 streets with a length of 62.5 km.
In addition, the cost at the expense of sponsors is KZT 1 billion. Improvement works have been carried out on the central square of Kyzylorda.
Timely and high-quality performance of improvement works is under constant control.
On emergency buildings
Currently, in the Kyzylorda region there are 54 apartment buildings recognized as emergency according to the expert opinion. Of these, 51 houses are in Kyzylorda, 2 houses in the Syrdarya district, 1 house in the Zhalagash district.
In total, 725 families are on the housing waiting list, whose only housing has been declared unsafe. Of these, 698 families are in Kyzylorda, 18 families in the Syrdarya district, and 9 families in the Zhalagash district.
In 2024, KZT 1.6 billion has been allocated from the regional budget for the purchase of apartments for 135 families whose only housing has been declared unsafe.
Capital repairs of apartment buildings
To date, the share of condominium properties requiring capital repairs has decreased from 800 buildings in 2011 to 550 (or from 73% to 43.5%).
From the republican budget for 2024, KZT 2.111 billion has been allocated for the capital repairs of 36 multi-story residential buildings.
Payment for housing rented in the private housing stock
In accordance with the instructions of the Head of State, work is being carried out to provide socially vulnerable groups of the population with affordable rental housing.
JSC Zhilstroysberbank Otbasy is the financial provider who pays rent for housing to citizens.
Currently, contracts have been concluded with JSC Otbasy Bank and are paid monthly.
On the housing queue
The number of citizens registered in the housing queue is 35,533.
including:
- orphans and children left without parental care - 2,068;
- mothers with many children, large families awarded with the pendants "Altyn alka", "Kumis alka", previously awarded the title "Mother Heroine", as well as awarded the orders "Maternal Glory" of the 1st and 2nd degrees - 9,190;
- socially vulnerable groups of the population - 13,719;
- civil servants, employees of budgetary organizations, military personnel and persons holding state elected positions - 9781;
- citizens whose housing has been recognized as emergency in accordance with the procedure established by the legislation of the Republic of Kazakhstan - 775.
Information on the work done for 6 months of 2024
Gas supply. In 2024, the villages Tazhibaev, Bestam of Shieli district were connected to gas, and the number of gasified settlements increased to 38. In addition, KZT 6 billion for 20 projects were alllocated from the regional and republican budget (NF-3 942 255 thousand. tenge, RB-9 373 thousand. tenge, OB-2 131 759 thousand. tenge). By the end of 2024, it is planned to supply natural gas to 8 rural settlements (Saksaul, Abai, Toretam, Aksu, Shamenov, S. Seifullin, A. Tokmaganbetov, Nizaryk) with an increase in the level of gas supply to the region by 78%, the number of gasified settlements by 46. In addition, in accordance with the instructions of the President of the Republic of Kazakhstan Kassym-Jomart Kemelevich Tokayev, a list of projects has been determined that will allow modernizing 306 km of gas networks in the region and providing gas to more than 20 thousand people. From government resolution No. 431 was adopted on May 31, 2024. According to this resolution, SWF “Samruk-Kazyna” JSC allocated KZT 24,020,307 thousand for 16 projects.
Water supply. 204 rural settlements from 230 or 98.4% of the population were connected to the centralized water system. The remaining 26 villages have more than 7,000 inhabitants or 1.6% of the rural population. In the 2021 Address of the Head of State, the government was instructed to provide 100% of the population with clean drinking water within the next five years. In this connection, a phased plan has been drawn up to provide 100 % of the population with drinking water in 26 settlements and work is under way. In 2024, KZT 2.5 billion were allocated from the national and regional budgets for drinking water supply and water sanitation projects. Construction and installation work is under way. As a result, 82 km of drinking water and 18.4 km of sewage networks will be upgraded.
In electric energy sector. To date, the total length of power supply systems amounted to 10490.82 km electrical networks and 2008 electric substations of various tension, level of wear is 66%. In 2023, power supply facilities that need priority of repair, were identified in the region, modernization and repair plan, changes created. KZT 1.6 billion was allocated from the regional budget for the first stage. 35 substations with voltage 10/0.4 Kv were changed, 27 old power transformers made of brick were completely repaired. In addition, 32 km of networks were updated. KZT 1.5 billion was allocated for the second stage.
Heat supply.
Preparations for the upcoming heating season in the region are being carried out in accordance with the approved action plan. KZT 12 billion (from the republican budget – KZT 8.3 billion, from the regional budget – KZT 3 billion, KZT 566 million from the own funds of the enterprise KUEO) for the modernization of heat supply facilities this year. Including: KZT 2 billion 700 million have been allocated from the budget for the modernization of three Bono Energy steam boilers of the Southern boiler house of the Kyzylorda thermal power plant. At present, a contractor has been selected, construction work has begun. At the expense of the local budget and enterprises, major repairs of 11 boilers, current repairs of 1 turbine and 15 boilers are underway at 2 gas turbine units. At present, 59% of the work is complete. The length of heating networks in the region is 216 kilometers, the wear rate is 44.6%. This year, KZT 6 billion 900 million was allocated from the budget for the implementation of 6 projects to modernize heating networks. To date, 2.3 km of 9.5 km of heating networks have been installed and 24% complete. In addition, the overall readiness of 1067 social facilities (532 educational facilities, 247 healthcare facilities, 288 cultural and sports facilities) in the region is 59% (including educational facilities - 57%, healthcare - 62%, cultural and sports facilities - 60%). In general, preparations for the upcoming heating season are under constant control.
Works on landscaping
In 2024, the implementation of 19 projects for improvement of the region from the republican and regional budgets allocated KZT 6.5 billion. These funds will be used to build 57 km of pedestrian roads on 56 streets, repair 26 facades of multi-storey residential buildings and light works will be carried out on 54 streets with a length of 62.5 km. In addition, the cost at the expense of sponsors KZT 1 billion carried out works on the improvement of the central square of the city of Kyzylorda. Timely and quality of the improvement work is constantly monitored.
On the issue of emergency housing
Currently, there are 55 apartment buildings in the Kyzylorda region that have been recognized as emergency based on expert assessments. Of these, 51 buildings are in the city of Kyzylorda, 3 buildings in the Syrdarya district, and 1 building in the Zhalagash district. In total, 663 families are on the housing waiting list, whose only living space has been recognized as emergency. Of these, 638 families are in the city of Kyzylorda, 18 families in the Syrdarya district, and 7 families in the Zhalagash district. In 2024, KZT 1.6 billion were allocated from the regional budget for the purchase of apartments for 135 families whose only living space has been recognized as emergency considered.
Major repairs of multi-story residential buildings
To date, the share of condominium properties requiring major repairs has decreased from 800 to 550 buildings in 2011. (or decreased from 73% to 43.5%). In 2024, KZT 2.111 billion were allocated from the republican budget for the major repairs of 36 multi-storey residential buildings. Finances were reviewed.
On the payment of housing fees by citizens
Work is underway in accordance with the instructions of the Head of State to provide socially vulnerable groups of the population with affordable rental housing. JSC “Zhilstroysberbank”, “Otbasy Bank” has been appointed the financial operator for paying rent to citizens for housing. Currently, JSC Otbasy Bank and 784 citizens have concluded contracts and payments are made monthly.
By housing queue
The number of citizens registered in the housing queue is 35,782.
Including:
- Veterans of the Great Patriotic War - 2;
- Orphans and children left without parental care - 2,251;
- Mothers with many children; families with many children, awarded with the medals "Altyn Alka", "Kumis Alka" or previously received the title "Mother Heroine", as well as awarded with the Order of "Maternal Glory" of the 1st and 2nd degrees - 8407;
- Socially vulnerable groups of the population - 13895;
- Civil servants, employees of budgetary organizations, military personnel and persons holding state elected positions - 10503;
- Citizens whose only home is recognized as emergency in the manner established by the legislation of the Republic of Kazakhstan - 725.
Information on the work done in the first quarter of 2024
Gas supply. At the end of the year, 75% of the population was provided with natural gas. Four cities (Kyzylorda, Aral, Kazaly, and Baikonur) have been completely gasified. Of the 230 settlements, 35 villages were gasified.
Last year KZT 9.2 billion was allocated for the implementation 26 projects.
11 projects were totally completed (Akay, Makhambetov-Nauryz, Byrlyk-Kyrash, Abay-Dosan, Kalzhan Akhun, Enbekshy, Zhidelyaryk, Tazhibaev, Zhaylma, Kuttykozha-Shalkya, Keyden).
14 projects (gasification of a poultry farm for raising broilers in the village of Toretam, Saksaul AGTS, Saksaul, Shokai AGS, Abay, Aksu, A. Tokmaganbet, Seifullinsky, Shamenovsky, Almalinsky, Bestamsky, Aktogan, Tomenaryk, Zhanakorgan districts) transition to 2024.
In 2024, KZT 5.3 billion was allocated for the implementation of 20 gas supply projects. Of these: KZT 4.2 billion from the RB, KZT 1.1 billion from the OB.
With these funds, from 2023, 14 transition projects will be continued and the construction of 6 new ones will begin.
With these funds, from 2023 14 bridging projects will be continued, and 6 constructions were started.
At the end of 2024, the natural gas will be connected to 11 settlement (Saksaulsk, Abay, Toretam, Aksu,Shamenov, S.Seifullin, A.Tokmaganbetov, Almaly,Bestam, Aktogan, Tomenaryk), it is planned to increase the level of gasification to 78%, the number gasified settlements to 46.
Water supply. 204 settlements or 98.4% from 230 are connected to the central water supply. The remaining 26 had a population of over 7000, or 1.6% of the rural population.
In the 2021 address, the Head of State instructed the government to provide the population with clean drinking water for another 5 years at 100%. Due to this, work is underway in 26 settlements to ensure 100% clean drinking water.
Of these< through the Ministry of Water Resources and Irrigation of the Republic of Kazakhstan in 3 settlements (Aral district – Akbasty, Abay, Tokabay), through Ministry of Industry and Construction up to 5 settlements Construction of water supply networks (Aral district - Tastubek, Yerimbetzhaga, Kazaly district - Shaken, Sarbulak, Shili) and reconstruction from the local budget of 24 settlements (Aral district (6) - Tastubek, Kazalinsky district (11) - Azhar, Birlik , Sarbulak, Zhuban, Shili; Shieli district (2) - Leskhoz, Aktam).
In 2024, KZT 2.5 billion was allocated from the republican budget for 12 projects related to drinking water supply and water disposal. At the current time the projects will be finished and commissioned.
Heat supply. The heating season in the region is steadily approaching. All 1067 social objects and 882 multi-storey residential buildings, which are connected to centralized heat networks, were fully heated. The functioning of life-support enterprises is normal.
In 2023, at the expense of regional budget KZT 1.5 billion was used to capital repairs of 2 gas turbine units and 1 water boiler room of Kyzylorda combined heat and power plant.
At the expense of the enterprise's own funds, 9 steam boilers, 1 steam turbine and 18 autonomous boilers were repaired.
The length of heating networks in the region is 208 km. In 2023, KZT 8 billion was allocated from the republican budget for 8 projects, and 8.7 km of heating networks were replaced. As a result, the wear rate decreased by 2.9% (from 47.5% to 44.6%).
In 2024, KZT 6.2 billion was allocated from the republican budget for the reconstruction of 9.5 km of networks. Contractors have been identified and contracts have been concluded. In addition, at the expense of the regional budget, design estimates for 8 projects are being developed and competitive work is underway for design estimates for 6 projects.
Electricity. To date, total length of power supply networks in the region amounts to 10490.82 electricity networks and 2008 units of electric substations of different voltage, level of wear, which amounts to 66%.
To reduce the level of wear and tear in power grids to 30%, KZT 153 billion is needed.
Thus, at the expense of regional budget in 2022 KZT 548 million was allocated, increased authorized capital of JSC “Kyzylorda electricity distribution company”. The power transformers of the 35/10 kV substations “Silikatnaya”, “Promyshlennaya” and “Komsomol” in the city of Kyzylorda were replaced.
Electrical supply facilities in need of priority repair have been identified, and a plan for modernization, repair and replacement has been developed. For the first stage, KZT 1.6 billion was allocated from the regional budget. These funds were used to replace 35 10/0.4 kV substations and overhaul 27 old brick power transformers.
In addition, 32 km of networks were replaced.
For the second stage in 2024, KZT 1.5 billion was allocated from the regional budget. Transfer of 10/0.4 kV to RP, RNTD 10/0.4 kV KPPB in the amount of 16 pieces for allocated funds, modernization of 35 kV overhead lines L-33.34 0.5 km, reconstruction of 10/0.4 kV overhead lines with a length of 128 ,4 km, reconstruction of cable lines 0.4 kV 5.6 km and purchase of vehicles, in particular 4 pieces “Vehicle with a metal platform for utilities”, “Mobile electrical laboratory vehicle”, “Specialized crane-manipulator vehicle”.
On the reconstruction project, a positive conclusion from the state expertise was received for the substation 220/110/35/10 kV 'Shieli' in the village 'Shieli' for 2024. KZT 1.5 billion was allocated from the National Fund. Public procurement tenders are being held with the aim of identifying the winner.
On the emergency shelters. At the moment, there are 55 multi-storey residential buildings, which are recognized as emergency by relevant experts, in the Kyzylorda region. Of these: In Kyzylorda city – 51, in the Syrdarya district – 3, in the Zhalagash district -1.
A total of 663 families are on the waiting list for housing, with the only housing units identified as emergency. Of these, 638 families in Kyzylorda, 18 families in Syrdarya district and 7 families in Zhalagash district.
In 2024, from the regional budget for the purchase of apartments 135 families, the only housing of which is recognized as emergency, provided for KZT 1.6 billion.
Capital repair of multi-apartment houses. To date, share of objects of the condominium, required the capital repair, decreased from 800 houses in 2011 to 550 (or 73% to 43.5%).
KZT 860.7 million was allocated from the republican budget for the repair of 17 multi-storey residential houses in the city of Kyzylorda, house 11, Kazaly, house 4, Zhanakorgan district, house 2.
From the republican budget in 2024, for capital repair of 36 multi-storey residential buildings KZT 2.111 billion was provided.
Payment for housing rented in a private housing stock.
In accordance with the instructions of the Head of State, work is being carried out to provide socially vulnerable segments of the population with affordable rental housing.
JSC “Zhilstroysberbank Otbasy” has been appointed as the financial operator for paying rent for housing to citizens.
Currently, contracts have been concluded with “Otbasy Bank” JSC and 784 citizens, and are paid monthly.
Housing waiting list.
The number of citizens, consisting on the account in the queue for housing is 35782.
Also:
- veterans of the Great Patriotic War - 2;
- orphans and children left without parental care - 2251;
- mothers of many children, large families awarded with the “Altyn alka”, “Kumis alka”, previously awarded the title “Heroine Mother”, as well as awarded the Order of “Maternal Glory” 1st and 2nd degree - 8407;
- socially vulnerable segments of the population - 13895;
- civil servants, employees of budgetary organizations, military personnel and persons holding public elective positions - 10503;
- citizens whose housing is recognized as unsafe in the manner established by the legislation of the Republic of Kazakhstan - 725.
Information on the work done for ІV quarter of 2023 for the Department of Energy, Housing and Communal Services of Kyzylorda region
Gas supply
In Kyzylorda region, 3 cities (Kyzylorda, Baikonur, Kazalinsk), 7 district centers and 19 settlements are connected to the natural gas.
In 2023, KZT 9.3 billion was allocated for the implementation of 26 gas supply projects. Of these: from the republican budget – KZT 8.1 billion, from the regional budget – KZT 1.1 billion.
By the end of 2023, 13 settlements had been linked to natural gas. The number of rural settlements that were gasified had gone up by 35. By the end of the year, the percentage of gasification had reached 75%.
In 2024, KZT 4.1 billion for 17 gas supply projects was provided from the republican budget.
Based on the 2024 results, there is a plan to raise the gasification level to 78%.
Water supply and sanitation
Of all 230 rural settlements on the territory of the region 198 or 98.1% of the general population are connected to the centralized water supply.
In total, in 2023, KZT 7.2 billion was allocated for 23 projects under the programs "Strong regions - driver of the country's development" and "Auyl el Besigi".
In 2023 the work was finished with a connection to the group water supply system of the settlement Koktem of Aral district, and the installation of a desalination plant in Kulandy settlement, settlements of Zhuantobe, Shieli district.
The construction of internal water supply networks of Kyzylkayyn and Kosuyenki settlements of Shieli district was completed.
By the end of the year, the provision of drinking water to the population of rural communities had increased to 98.4%.
Electric power
Kyzylorda region has more than 10 thousand kilometers of electrical networks and substations of various 1867. The level of their depreciation at the beginning of the year was 68%.
In 2023, KZT 3.7 billion was allocated for the implementation of 6 electricity supply projects. Of these: from the republican budget – KZT 2.1 billion, from the regional budget – KZT 1.6 billion.
Construction and installation works on the project «Modernization of the 10/0.4 kV power grid in the village of Zhanakorgan, Zhanakorgan district» are also continuing, construction of which began in 2022.
In 2023 KZT 1.2 billion was allocated from the republican budget, as the result of which 122.98 power grids or 33 KTPN were installed.
The completion date is 2024.
In addition, KZT 929.4 million has been allocated from the republican budget for power supply projects in the settlements of Chagan and Amangeldy of the Syrdarya district, reconstruction of the electric networks of the village of Shieli and the village of Aiteke bi of the Kazalinsky district, construction and installation works are underway.
Additionally, KZT 1.6 billion was allocated from the regional budget to increase the authorized capital of JSC “Kyzylorda Electricity Distribution Company”.With these funds, work was carried out on the transfer of 35 substations of 10/0.4 kV to Kyzylorda to the modular block type, major repair of 27 substations of 10/0.4 kV, replacement of 31.6 km of cable lines.
As a result of the work carried out at the end of the year, regulatory and technical loads in the power supply system decreased to 14.6%, the level of wear - to 66%.
Heat supply
The length of heat network in the region is 208 km, deterioration of networks is 47.5%.
In this year, KZT 8 billion was allocated for 8 projects from the republican budget, 8.7 km of heat networks were replaced.
As a result, the depreciation rate decreased by 2.9%
(from 47.5% to 44.6%).
Preparations for the upcoming heating season in the region are being conducted in accordance with the approved action plan.
Improvement
In 2023, KZT 6 200.0 million was allocated for 51 projects to improve cities and districts from the republican and regional budgets.
Including, KZT 1131.0 million was allocated for 33 projects to the street lighting (Kyzylorda, Kyzylzharma, Karaultobe, Kosshynyrau, Kyzyl ozek, Akzharma a/o streets, 5 in the city of Aralsk, Karmakshinsky district, 13 in the village of Zhosaly, DurOngar) 5 street in the village, lighting of 4 streets of the district center Zhanakorgan).
KZT1188.0 million was allocated for pedestrian paths for 10 projects (repair of 19 streets, courtyard roads of multi-storey residential buildings (17 courtyards), Karaultobe, Kosshynyrau, Kyzylozek, Kyzylzharma, Aksuat village, pedestrians on the street in the village of Aidarly Syrdarya district))
For improvement - KZT 3900 million for 8 projects. (Capital repair of the territory of the stadium of G. Muratbayev, S. Beibars street, left bank of Abylaykhan avenue, inner yard territories of multi-storey residential buildings of Kyzylorda, reconstruction of the alley «Rybakov» in the city of Aralsk, improvement of the territory of 6 multi-storey houses in the village of Aytek bi Kazalinsky district, improvement of the central square)
For the purchase of special equipment for the «Kyzylorda Water System» provided KZT 1 200.0 million, purchased 31 appliances.
Emergency houses
According to the expert's conclusion, 55 apartment buildings in the Kyzylorda region have been identified as an emergency. Of these, there are 51 houses in Kyzylorda, 3 houses in the Syrdarya district, and 1 house in the Zhalagash district.
In total, there are 634 families in the housing queue, whose only housing is recognized as emergency. Of these, 609 families are in Kyzylorda, 18 families in the Syrdarya district, 7 families in the Zhalagash district.
In 2022, the funds were allocated from the regional budget, 60 of them received apartments, in 2023 40 apartments.
In accordance with the Decree of the President of the Republic of Kazakhstan No. 976, the Roadmap for providing owners with housing until 2029 by demolishing apartment buildings recognized as emergency expert opinions in the region was approved by the akim of the region and sent to the ministry.
Major renovation of apartment buildings
Currently, the share of objects in the condominium that require major repairs has decreased from 800 houses in 2011 to 550. (or from 73% to 43.5%)
For 2023, KZT 862.4 million was allocated from the republican budget for the repair of 17 multi-apartment residential buildings. Kyzylorda, house 11, Kazalinsk, house 4, Zhanakorgan district, house 2.
KZT 2111 billion was allocated for major repairs of 36 multi-storey residential buildings from the republican budget for 2024.
Payment for housing rented in a private housing stock
In accordance with the instructions of the Head of State, work is being carried out to ensure affordable rental housing for socially vulnerable segments of the population.
JSC “Zhilstroysberbank” “Otbasy” has been appointed as the financial operator for paying rent for housing to citizens.
Currently, contracts have been concluded with “Otbasy Bank” JSC and 645 citizens are paid monthly.
Housing queue
The number of citizens registered in the housing waiting list is 36221.
Including:
- veterans of Great Patriotic War- 2;
- orphans and children left without parental care - 2289;
- mothers with many children, families with many children, awarded with pendants "Altyn Alka", "Kumis alka", previously awarded the title "Mother Heroine", as well as awarded with the orders of "Maternal Glory" of the 1st and 2nd degrees - 7948;
- socially vulnerable segments of the population - 13774;
- civil servants, employees of budgetary organizations, military personnel and persons holding state elected positions - 11518;
- citizens whose home is recognized as an emergency in accordance with the procedure established by the legislation of the Republic of Kazakhstan - 690.
Information on the work done for III quarter of 2023 for the Department of Energy, Housing and Communal Services of Kyzylorda region
Gas supply
At the end of 2022, the level of gasification in the region was 70%.
Of these: 4 cities (Kyzylorda, Baikonyr, Aral, Kazaly) - 100 % (with population), 22 rural settlements - 9.56 % (with number of settlements).
As of September 1, 2023, 3 settlements (Makhambetov-Nauryz, Birlik, Kyrash) are connected to natural gas, the number of gasified rural settlements increased by 25, the gasification level was 10.8%.
In 2023, KZT 8.3 billion (KZT 8,337,022.6 thousand) were allocated for the implementation of 26 gas supply projects. Including: from the republican budget – KZT 7.3 billion (KZT 7,270,622 thousand), from the regional budget – KZT 1.1 billion (KZT 1,066,400.6 thousand).
These funds will be used to continue 7 projects started in 2022 (Saksaulsk AGDS, Saksaulsk, Toretam, Akay, Makhambetov-Nauryz, Birlik-Kyrash, Shokai AGDS) and begin the construction of 19 new projects (Abai-Dosan, Kalzhan Akhun, Enbekshi, Zhideliaryk , Zhaiylma, Kuttykozha-Shalqiya, Tomenaryk, Kayden, Almaly, Aktogan, Bestam, Aksu, Shamenov, Abay, gas supply to Zhanakorgan settlement(expansion), Construction of external gas supply networks for a poultry farm for raising broilers in the Zhanakorgan district).
Also, KZT 7.3 billion will be allocated to clarify the republican budget for 2023 to finance the construction of 12 new projects. a budget request in the amount of KZT 2.1 billion was submitted and the construction of 3 ongoing projects was completed.
At the end of 2023, the gasification project for 12 settlements (Toretam, Akay, Makhambetov, Abay, Dosan, Kalzhan Akhun, Birlik, Kyrash, Zhaiylma, Kuttykozha, Shalkiya, Kayden) will be completed; about 40 thousand residents will benefit from natural gas.
In addition, KZT 17.2 billion will be allocated to form the republican budget for 2024-2026 to finance the construction of 21 projects, a budget request has been submitted.
At the end of 2023, the level of gasification in the region was increased to 75%.
Water supply and sanitation
Of all 230 rural settlements in the region, 198 or 98.1% of the population (434 thousand people out of 442.4 thousand people) are connected to a centralized drinking water system.
In the Address of the Head of State in 2021, on behalf of the Government, to provide 100% of the population with clean drinking water over the next five years, a comprehensive plan has been developed in our region and corresponding work is being carried out.
In total, in 2023, KZT 7.2 billion was allocated for 23 projects under the “Strong Regions - Driver of the Country’s Development” and “Aul el Cradle” programs.
Once the projects are fully completed, 163 km of drinking water networks will be modernized and the supply of drinking water to more than 100 thousand people will be improved.
In addition, KZT 38.5 million was allocated from the regional budget for the installation of a water intake in Kulandy settlement ( Aral district) and Zhuantobe settelement (Shieli district).
By the end of the year it is planned to increase the level of drinking water supply to the rural population to 98.3%.
Electric power
Today, the region has more than 10 thousand kilometers of electrical networks and about 2000 substations of various voltages. Their wear rate is 68%.
In 2023, KZT 3.7 billion was allocated for the implementation of 7 power supply projects. Of these, KZT 2.1 billion from the republican budget and KZT 1.6 billion from the regional budget.
These funds will be used to continue the implementation of 1 project started in 2022, and the construction of 4 new projects is underway.
In addition, 1.6 billion tenge was allocated from the regional budget to increase the authorized capital of JSC “KREC”.
These funds were used to replace 35 units of 10/0.4 kV substation in Kyzylorda with a block modular type, 27 units for major repairs of the 10/0.4 kV substation building, 31.6 km of cable networks.
To form the republican budget for 2024-2026, a budget request was submitted for the reconstruction of the 220/35/10 kV substation in the Shieli district amounting to KZT 4.5 billion by 2024.
Heat supply
Preparations for the upcoming heating season are carried out in accordance with the approved action plan.
The length of heating networks in the region is 208 km, the wear of networks is 47.5%.
This year, KZT 8 billion has been allocated from the republican budget for the modernization of 8.9 km of heating networks for 8 projects:
- 6 projects with a targeted transfer for KZT 7 billion;
- 2 projects through budget loans for KZT 922 million,
To date, of the planned 8.9 km of heating networks, 7.5 km or 84% have been replaced.
There are 1,067 social facilities in the region, including 532 educational facilities, 247 healthcare facilities, 288 cultural and sports facilities. Readiness for the heating season - 100%. The readiness of multi-storey residential buildings is 98% (out of 855 houses, 834 are ready).
Improvement
In 2023, KZT 8,766 million has been allocated from the republican and regional budgets for 62 projects for the improvement of cities and districts.
Including:
For street lighting for 34 projects amounting to KZT 1132.3 million (Kyzylorda, Kyzylzharma, Karauyltobe, Kosshynyrau, Kyzylozek, Akzharma s/o streets, 5 streets in Aral town, Karmakshy district, 13 streets in Zhosaly settlement, 5 street in Durongar settlement, 4 street lighting in Zhanakorgan district center),
For the pedestrian path – KZT 2081 million for 13 projects (Repair of the courtyard road of multi-storey residential buildings along 19 streets of the city of Kyzylorda (17 courtyards), placement of a pedestrian path on the street Karauyltobe, Kosshynyrau, Kyzylozek, Kyzylzharma, s/o Aksuat in the village of Aidarly, Syrdarya district)
For improvement – KZT 4810 million for 14 projects. (Improvement of the territory of the Aiteke bi stadium, Bukharbay batyr, Altynsarin, G. Muratbaev, S. Beibarys street, Abylaikhan Avenue, Boulevard of Flowers 12 hectares in the city of Kyzylorda, major repairs of courtyard areas of multi-storey residential buildings in Aralsk town, "Fishermen" alley reconstruction, improvement territory of 6 multi-storey buildings in Aiteke bi settlement, Kazaly district) for the purchase of special equipment of the State Enterprise “Kyzylorda Water System”.
Emergency houses
Currently, in Kyzylorda region there are 51 multi-apartment residential buildings that were recognized as unsafe based on the results of the examination. Of these, 47 houses are in Kyzylorda city, 3 houses in Syrdarya district, 1 in Zhalagash district.
In total, there are 627 families on the waiting list for housing, the only housing of which is recognized as unsafe. 482 of them are in Kyzylorda city, 18 families in Syrdarya district, 7 families in Zhalagash district.
In 2022, funds were allocated from the regional budget; for this category, 60 citizens standing in line for housing were provided with apartments, and in 2023 it is planned to provide 40 apartments.
In accordance with Decree of the President of the Republic of Kazakhstan No. 976, the Roadmap for providing owners with new housing until 2029 through the demolition of multi-apartment residential buildings recognized as unsafe in the region was approved by the regional akim and sent to the ministry.
On the implementation of housing reforms OSI/PT
In accordance with the instructions of the Head of State, 913 multi-apartment residential buildings in the region switched to a new form of management. 49 OSI (association of owners) and 864 PT (joint partnership) were created.
A roadmap for the transition of multi-apartment residential buildings with more than 30 apartments to OSI is fixed as a PT.
A roadmap for registering multi-apartment residential buildings as condominium properties has been approved. Upon registration of the condominium object with the justice authorities, out of 922 houses, 343 were registered.
Major renovation of multi-apartment residential buildings
Today, the proportion of condominium properties requiring major renovations has decreased from 800 homes in 2011 to 550 homes. (or a decrease from 73% to 45%).
In 2022, within the framework of the “Nurly Zher” program, KZT 616.7 million were allocated from the republican budget for major repairs of multi-apartment residential buildings in the region;
For 2023, KZT 862.4 million has been allocated from the republican budget for the repair of 18 multi-apartment residential buildings.
Payment for housing rented in a private housing stock
The work is being carried out in accordance with the instructions of the Head of State to provide socially vulnerable segments of the population with affordable rental housing.
JSC "Housing Construction Savings Bank "Family Bank" has been appointed as the financial operator for paying rent for housing to citizens.
Currently, 426 agreements have been concluded with JSC "Family Bank" , payments are made monthly.
Housing queue
The number of citizens registered in the queue for housing is 36,538.
Including:
- Veterans of the Great Patriotic War - 1;
- Children and children left without parental care - 2275;
- Mothers of many children, large families awarded by the collegiums “Altyn Alka”, “Kumis Alka”, or who previously received the title “Mother Heroine”, as well as awarded the Order of “Maternal Glory” 1st and 2nd degree - 7554;
- Socially weak groups of the population – 14403;
- Civil servants, employees of budgetary organizations, military personnel and persons holding public elective positions -;
- Citizens whose housing is recognized as unsafe in the manner established by the legislation of the Republic of Kazakhstan - 672.
Information on the work done for the 2nd quarter of 2023 on the department of energy and housing and communal services of Kyzylorda region
Gas supply
At the end of 2022, the level of gasification of the region amounted to 70%.
Of them: 4 cities (Kyzylorda, Baikonyr, Aral, Kazaly) - 100 percent (with population), 22 rural settlements - 9.56 percent (with the number of settlements).
As of June 1, 2023, 3 settlements (Mahambetov-Nauryz, Birlik, Kyrash) are connected to natural gas, the number of gasified rural settlements increased by 25, the level of gasification was 10.8%.
In 2023, KZT 8.3 billion (KZT 8,337,022.6 thousand) were allocated for the implementation of 26 gas supply projects. Including: from the republican budget – KZT 7.3 billion(KZT 7,270,622 thousand), from the regional budget – KZT 1.1 billion (KZT 1,066,400.6 thousand).
These funds will continue 7 projects started in 2022 (Saksaulsk AGRS, Saksaulsk, Toretam, Akai, Makhambetov-Nauryz, Birlik-Kyrash, Shokai AGDS) and construction of 19 new projects (Abai-Dosan, Kalzhan akhun, Enbekshi, Zhideliaryk , Zhayylma, Kuttykozha-Shalqiya, Tomenaryk, Keiden, Almaly, Aktogan, Bestam, Aksu, Shamenov, Abay, gas supply to Zhanakorgan village (expansion), Construction of external gas supply networks for a poultry farm for growing broilers in Zhanakorgan district).
Also, to clarify the republican budget for 2023, 7.3 billion will be allocated to finance the construction of 12 new projects submitted a budget request in the amount of KZT 2.1 billion and completed the construction of 3 ongoing projects.
At the end of 2023, the gasification project for 12 settlements (Toretam, Akai, Makhambetov, Abai, Dosan, Kalzhan akhun, Birlik, Kyrash, Zhaiylma, Kuttykozha, Shalkiya, Kayden) will be completed, about 40 thousand residents will benefit from natural gas.
In addition, KZT 10.8 billion will be allocated to form the republican budget for 2024-2026 to finance the construction of 19 projects. A budget application has been submitted.
At the end of 2023, the level of gasification of the region was brought to 75%.
Water supply and sanitation
In total, through the republican and regional budget for 2023, KZT 7.2 billion were allocated for 23 projects, including the Republic of Belarus – KZT 6.7 billion, regional budget-0.5 billion (Kyzylorda city - 7 projects, Aral district - 1 project, Baikonyr city - 1 project, Karmakshy district - 3 projects, Zhalagash district - 3 projects, Syrdarya district - 3 projects, Shieli district - 2 projects, Zhanakorgan district - 3 projects).
Currently, a public procurement competition for construction work is being held for new projects, contractors have been identified, and construction work has begun.
In accordance with the financing plan for transitional facilities, the relevant work will be completed and put into operation on time this year. As a result, it is planned to build 94.5 km of drinking water networks, modernize 68.5 km of water supply systems and 6 km of sewer systems and 12 km of sewage pumping stations, drilling 7 wells.
Heat supply
A regional headquarters has been set up to prepare and conduct the upcoming heating season, and an action plan has been approved. Preparatory work is being carried out in accordance with the approved schedules.
Together with the Ministry of Energy, a roadmap was developed for the readiness of the Kyzylorda Thermal Power Plant. In pursuance of the road map KZT 1.7 billion, of which 1.5 billion tenge. tenge from the regional budget, KZT 207 thousand is maintained at the expense of the enterprise's own funds.
At the expense of the regional budget, on the basis of a public procurement tender for the overhaul of a gas turbine unit of 2 units of the Kyzylorda Thermal Power Plant and Vodokanal KUV-30, contractors have been identified and work is underway. At the expense of the enterprise's own funds, it is planned to repair 9 steam boilers and 1 steam turbine and 18 autonomous boilers, 52% completed.
The depreciation rate of heat networks in the region is 47.5 percent. In order to reduce the level of depreciation in 2023, 14 projects for the reconstruction of 18 km of heating networks amounted to 14.5 billion tenge. on tenge was submitted to the Ministry of Industry and Infrastructure Development of the Republic of Kazakhstan. Of these, 8.2 billion tenge was allocated from the republican budget for 8 projects. tenge allocated (2 projects - budget crediting program, 6 projects - with targeted transfer). Currently, construction work is underway on 6 projects, 1 project is starting, 1 project has been suspended by a court ruling in connection with a complaint about the results of public procurement. As a result of the implementation of the projects, 8.9 km of heating networks will be modernized, the wear and tear of which will decrease by 44.6%.
In addition, technical studies of heating networks were carried out at the expense of the regional budget.
Within the framework of the program "Auyl el besigi" from the republican and regional budgets (378.5 million tenge. Funds have been allocated for the reconstruction of boiler houses of 10 social facilities and work is underway. In addition, by clarifying the regional budget, 1.0 million tenge has been allocated for the beginning of 10 projects. As a result, boiler houses of 12 educational facilities, 5 healthcare facilities, 3 sports facilities (Karmakshy - 6, Zhalagash - 2, Syrdarya-2, Shieli - 6, Zhanakorgan -1) will be modernized, of which 11 educational objects will be brought outside (Karmakshy - 4, Shieli -6, Zhanakorgan -1).
Landscaping
In 2023, 8,766 million tenge was allocated from the republican and regional budgets for the improvement of cities and districts for 62 projects.
Including:
for 34 street lighting projects in the amount of 1132.3 million tenge (streets of Kyzylorda, Kyzylzharma, Karauyltobe, Kosshynyrau, Kyzylozek, Akzharma, street 5 in the city of Aralsk, Karmakshy district, Zhosaly street 13, street 5 in the village of Durongar, street of the Zhanakorgan district center 4 lighting),
For pedestrian paths - 2081 million tons for 13 projects (Repair of the intra-yard road of multi-storey residential buildings along 19 streets of the city of Kyzylorda (17 courtyards), placement of a pedestrian path on Karauyltobe street, Kosshynyrau, Kyzylozek, Kyzylzharma, Aksuat village in the village of Aidarly, Syrdarya district )
For improvement - 4810 million tenge for 14 projects. (Improvement of the territory of the Aiteke Bi Stadium, Bukharbay Batyr, Altynsarin, G. Muratbaev, S. Beybarys Street, Abylaikhan Avenue, 12 ha Flower Boulevard in the city of Kyzylorda, overhaul of the courtyard areas of multi-storey residential buildings in the city of Aralsk, Rybakov Alley, reconstruction, improvement territory of 6 multi-storey buildings in the village of Aiteke bi, Kazaly district)
For the purchase of special equipment GKP "Kyzylorda water system" 742.8 million tenge
Emergency houses
As of 07/01/2023, there are 47 multi-apartment residential buildings in the Kyzylorda region, recognized as an emergency expert opinion. Of these, there are 43 houses in the city of Kyzylorda, 3 houses in the Syrdarya region, 3 houses in the Zhalagash region.
In total, there are 568 families in the queue for housing, the only living space of which was recognized as emergency. There are 543 families in the city of Kyzylorda, 18 families in the Syrdarya district, 7 families in the Zhalagash district.
In 2022, funds were allocated from the regional budget, apartments for this category were issued to 60 citizens on the waiting list for housing, and 40 in 2023.
In 2023, it is planned to demolish 2 houses in the city of Kyzylorda, this measure will be implemented after the relocation of residents to the purchased residential buildings.
On the implementation of housing reforms OSI/PT
In accordance with the instructions of the Head of State, 913 multi-apartment residential buildings (multi-apartment residential buildings) with a new form of management have been created in the region. (42 associations of owners (IIB) and 875 simple partnerships (PT).
A roadmap for the transition of multi-apartment residential buildings with more than 30 apartments to Gib was approved as a PT, work is underway.
A roadmap has been approved for registering multi-apartment residential buildings as condominium objects. 343 out of 922 houses were registered with the justice authorities for the registration of the condominium object.
Capital repairs of multi-apartment residential buildings
To date, the proportion of condominium properties requiring major repairs has decreased from 800 to 550 homes in 2011. (or decreased from 73% to 45%).
In 2022, within the framework of the Nurly Zher program, 616.7 million dollars were allocated from the republican budget for the overhaul of multi-apartment residential buildings in the region. Tenge was allocated, 15 multi-apartment residential buildings in the region were overhauled. There are 8 houses in the city of Kyzylorda, 5 houses in Zhalagash, 2 houses in Shieli district.
From the republican budget for 2023, 862.4 million tenge was allocated for the repair of 18 multi-apartment residential buildings. In the city of Kyzylorda there are 12 houses, Kazaly 4 houses, Zhanakorgan district 2 houses.
Payment for a dwelling rented in a private housing stock
Work is underway in accordance with the instruction of the Head of State to provide affordable rental housing for socially vulnerable segments of the population.
JSC Zhilstroysberbank Otbasy Bank has been appointed as the financial operator for the payment of rent to citizens.
At present, Otbasy Bank JSC and 207 citizens have concluded agreements and payments are being made monthly.
On the waiting list for housing
The number of citizens registered in the queue for housing is 36538.
Including:
- Veterans of the Great Patriotic War-1;
- Orphans and children left without parental care - 2262;
- Mothers with many children, families with many children awarded with pendants "Altyn alka", "Kumis alka" or those who received the title "Mother Heroine" earlier, as well as those awarded with the order "Maternal Glory" 1 and 2 degrees - 7038;
- Socially vulnerable segments of the population - 14426;
- Civil servants, employees of budgetary organizations, military personnel and persons holding public elected positions - 12199;
- Citizens whose only dwelling is recognized as emergency in the manner established by the legislation of the Republic of Kazakhstan-612.
Electric power industry
Today, the total length of the region's power supply systems is more than 10 thousand kilometers of power networks and 1867 units of substations of various tensions, the level of wear of which is 68%.
On the project for the reconstruction of the substation 220/110/35/10 kV "Shieli" in the village of Shieli, a positive conclusion of the state examination was received and a budget application for financing the project was sent to the Ministry of Energy of the Republic of Kazakhstan for 2023-2024.
"During the implementation of the project" Modernization of the 10 / 0.4 kV power grid system in the village of Zhanakorgan, Zhanakorgan district "1,175.7 million tenge was allocated from the republican budget, construction and installation work is underway.
In addition, design estimates are being developed from the regional budget for the project "Power supply of the left bank of the Syrdarya River, Kyzylorda (stage 2)" in the amount of 64.3 million tenge.
Information on the work done for 9 months of 2021 of the Department of Energy, Housing and Utilities of Kyzylorda region
Gasification
To date, the regional center and the city of Baikonyr, 5 regional centers (Aralsk, Aiteke bi, Terenozek, Shieli, Zhanakorgan) and 9 rural settlements are provided with natural gas. The share of natural gas supply is 65%.
Last year, we supplied gas to the Zhaksykylysh village in the Aral region, the villages of Gani Muratbaeva in the Kazaly region and Baysyn in the Shieli region, and at the beginning of this year gas was supplied to the Terenozek settlement.
This year it is planned to provide natural gas to more than 48 thousand residents of the region. For the implementation of these projects for 2021, 4.4 billion tenge was allocated. Of these: from the republican budget - 3.4 billion tenge, from the regional budget - 748.6 million tenge.
In July 2021, the villages of Zhosaly and Zhalagash, in August, the settlement of N. Bekezhanov, Shieli district, were connected to natural gas. By the end of the year, it is planned to supply gas to the city of Kazalinsk and the Kodamanov village of the Shieli region.
At the same time, this year we plan to start work on gas supply to the suburban settlements of Nauryz and Makhambet in the city of Kyzylorda. For the construction and installation work of this project, 500 million tenge have been allocated from the republican budget, work is underway on public procurement.
For the second clarification of the republican budget of 2021, a budget request was sent to the Ministry of Energy for the start of gasification projects in the village of Toretam and the village of Akay in the Karmakshy region.
The Department received a positive conclusion of the state expertise of gasification projects in the settlements of Birlik and Kyrash of the Zhanakorgan region this year
At the same time, projects for the installation of automatic gas distribution stations in the village of Saksaulsk and the village of Shokai, Shieli region are under consideration of the state expertise.
Also, projects are being developed for gas supply to the Abai village of the city of Kyzylorda, the Saksaulsk village of the Aral region, the Tomenaryk settlement of the Zhanakorgan region.
Water supply and sanitation
In 2021, 2.3 billion tenge (2,283,715 thousand tenge) were allocated for 8 water supply and sewerage projects, incl. from the Republic of Belarus - 2.2 billion teңge (2,155,111 thousand tenge), OB - 128 604 thousand tenge
For the estimated period of the financing plan 1,101,743 thousand tenge, 1 069 040.0 thousand tenge or 97 percent were mastered, of which in the Republic of Belarus out of 1,065 107.0 thousand tenge, 1,038 222.0 thousand tenge or 97, 5 percent, on OB out of 36 636 thousand tenge, 30 818 thousand tenge or 84 percent were spent.
As a result of the full implementation of the projects, 223 km of water supply and 11.4 km of sewerage networks will be built. 57 people will be temporarily employed. Water supply and sewerage services for more than 90 thousand consumers will be improved.
For reference: according to the Nurly Zher program
For the implementation of the project “Reconstruction of water supply and sewerage systems in the city of Baikonyr, Kyzylorda region. I - stage, I - stage. Water disposal "allocated 901.208 million tenge (RB - 808.53 million tenge, OB - 92.676 million tenge). Reconstruction of 11.4 km of sewerage networks is envisaged. For today, contract work is underway. The object will be commissioned in December 2021.
During the construction of the facility, 15 jobs will be temporarily created. During the implementation of the facility, the water disposal service for consumers in the city of Baikonur, numbering 16,061 people, will be improved.
For the implementation of 6 projects for the construction, reconstruction and expansion of water supply systems, 1,167.6 million tenge were allocated (RB - 1131.7 million tenge; OB - 35.9 million tenge), of which:
2 projects - for the construction of a water supply line to residential buildings in n. Zhankozha batyr and Maidakol of Kazaly district. Construction and installation works have been completed, 27.9 km of service lines have been built. Acceptance certificates have been received;
1 project - for the construction of water supply systems in the village of Toretam, Karmakshy region. For the reporting period, the construction of the facility is being fully completed;
3 projects - for the reconstruction and expansion of water supply systems in n. Tomenaryk, Sunakata, Ekpendy of Zhanakorgan region. Contract work is underway for today.
For the reporting period, according to the financing plan, 1,045,215.0 thousand tenge, 1,012,512.0 thousand tenge or 97 percent were disbursed, of which 981694.0 thousand tenge or 97 percent were disbursed in the Republic of Belarus out of 1,008,579.0 thousand tenge. 5 percent, on OB out of 36 636 thousand tenge, 30 818 thousand tenge or 84 percent were spent.
In general, a total length of 122.2 km of water supply networks was carried out on 6 projects.
42 temporary jobs will be created. As a result, 11 468 people will receive high-quality drinking water.
According to the special project "Auyl - el besigi", a project for the construction of a service line is being implemented in the village of Zhanakorgan since 2020. Last year, 93 km of service lines were built.
214 885.0 thousand tenge were allocated for the completion of the project in 2021. The project will build 101.3 km of service lines. The service for 31,530 consumers will be improved.
Housing and communal services
On September 1, 2020, the head of state issued an order to "introduce the institution of associations of property owners."
In accordance with the current legislation, apartment owners' cooperatives (KSK) carry out activities for the management of an apartment building only until July 1, 2022.
Currently, 1222 multi-storey residential buildings of the Kyzylorda region are served by 18 management bodies.
In order to implement the reform on "Implementation of the institution of property owners associations", the city and district akimats approved the Roadmap and Media Plan on February 17 this year.
Explanations on the creation of associations of apartment owners are given in the media (190 times) and in the social media. networks (220 times), brochures were also distributed to homeowners.
Currently, 9 associations of property owners and 327 simple partnerships have been created in the Kyzylorda region.
Heat supply
By the decision of the regional maslikhat No. 23 of April 14, 2021, 27 233.8 thousand tenge were allocated from the regional budget for the development of 5 design and estimate documentation with the receipt of an opinion on the reconstruction of heating networks of the city of Kyzylorda. To date, the project organization ProektService LLP is carrying out design work.
Electricity supply
At the beginning of the projects "Reconstruction of 35/10 kV SS" GMZ "," Komsomol "," Zalineinaya "," Promyshlennaya "in Kyzylorda" 1.4 billion rubles were allocated. tenge. Currently, construction and assembly work has begun.
At the same time, work is underway on "Development of design and estimate documentation for the project" Power supply to the left bank of the Syrdarya river in the city of Kyzylorda, stage 2 ".
Within the framework of the “Increase in the authorized capital of KREK JSC for the placement of 590 318 ordinary shares”, construction and installation work on the modernization of electric grids was completed. them. Bukharbai batyr, Zhalagash district.
In addition, within the framework of the “Increase in the authorized capital of KREK JSC for the placement of 80,000 ordinary shares”, construction and installation work was completed on the reconstruction of electrical networks in N of the item. Kaukei of Kazaly district.
As a result, consumers of settlements are provided with high-quality uninterrupted power supply.
Information on the work done for 6 months of 2021 of the Department of Energy, Housing and Utilities of Kyzylorda region
Gasification
To date, the regional center and Baikonyr town, 5 district centers (Aralsk, Aiteke bi, Terenozek, Shieli, Zhanakorgan) and 9 rural settlements are provided with natural gas. The share of natural gas supply is 65%.
Last year, we supplied gas to the Zhaksykylysh village in the Aral region, the villages of Gani Muratbaeva in Kazaly district and Baisyn in Shieli district, and at the beginning of this year gas was supplied to Terenozek settlement.
This year it is planned to provide natural gas to more than 48 thousand residents of the region. For the implementation of these projects for 2021, 4.4 billion tenge was allocated.
In July of this year, the villages of Zhosaly and Zhalagash will be supplied with gas. By the end of the year, it is planned to supply gas to the city of Kazalinsk and the villages of Bekezhanov and Kodamanov of Shieli district.
At the same time, this year we plan to start work on gas supply to the suburban settlements of Nauryz and Makhambet in Kyzylorda city.
Also, projects are being developed for gas supply to the Abai village of the city of Kyzylorda, the Saksaulsk village of Aral district, the settlements of Toretam and Akay of Karmakshy district, Birlik, Kyrash, Tomenaryk of Zhanakorgan district.
Water supply and sanitation
In 2021, KZT 2.4 billion (KZT 2,398,995 thousand) were allocated for 8 water supply and sewerage projects, incl. from the republican budget - KZT 2.2 billion (KZT 2 237 910 thousand), regional budget - KZT 161 095 thousand.
For the estimated period of the development plan, 209.4 million tenge from the Republic of Belarus has been fully disbursed. The work continues.
As a result, 223 km of water supply and 11.4 km of sewerage networks will be built. 57 people will be temporarily employed. Water supply and sewerage services for more than 90 thousand consumers will be improved.
For reference: according to the Nurly Zher program
For the implementation of the project “Reconstruction of water supply and sewerage systems in Baikonyr town, Kyzylorda region. I - stage, I - stage. Water disposal "allocated KZT 901.208 million (republican budget - KZT 808.53 million, regional budget - KZT 92.676 million). Reconstruction of 11.4 km of sewer networks is envisaged. As of today, the competitive procedures have been completed, the winner has been determined. The object will be commissioned in December 2021.
During the construction of the facility, 15 jobs will be temporarily created. During the implementation of the facility, the water disposal service for 16,061 consumers in the city of Baikonur will be improved.
For the implementation of 6 projects for the construction, reconstruction and expansion of water supply systems, KZT 1,184.8 million were allocated (republican budget - KZT 1148.9 million; regional budget - KZT 35.9 million), of which:
2 projects - for the construction of a water supply line to residential buildings in n. Zhankozha batyr and Maidakol of Kazaly district. Construction and installation works have been completed, 27.9 km of service lines have been built. Acceptance works are underway;
1 project - for the construction of water supply systems in the village of Toretam, Karmakshy region. For the reporting period, 8 km of networks were built;
3 projects - for the reconstruction and expansion of water supply systems in n. Tomenaryk, Sunakata, Ekpendy of Zhanakorgan district. Competitive procedures for government procurement are underway.
For the reporting period, according to the financing plan, 209.376 million tenge of funds from the republican budget or 100% were spent.
In the first half of the year, the total length of 35.9 km of water supply networks was completed.
In general, it is planned to commission 122.2 km of water supply networks, and 42 temporary jobs will be created. As a result, 11 468 people will receive high-quality drinking water.
According to the special project "Auyl - el besigi", a project for the construction of a service line is being implemented in Zhanakorgan village since 2020. Last year, 93 km of service lines were built.
For the completion of the project in 2021, KZT 312 987 thousand were allocated (republican budget - KZT 280 468 thousand; regional budget - KZT 32 519 thousand). The project will build 101.3 km of service lines. The service for 31,530 consumers will be improved.
Housing and communal services
On September 1, 2020, the head of state issued an order to "introduce the institution of associations of property owners."
In accordance with the current legislation, apartment owners' cooperatives carry out activities for the management of an apartment building only until July 1, 2022.
Currently, 1222 multi-story residential buildings of Kyzylorda region are served by 18 management bodies.
In order to implement the reform on "Implementation of the institution of property owners associations", the city and district akimats approved the Roadmap and Media Plan on February 17 this year.
Explanations on the creation of associations of apartment owners are given in the media (30 times) and in social media. networks (25 times), brochures were also distributed to homeowners.
Currently, in Kyzylorda region, 2 associations of property owners and 175 simple partnerships have been created.
Heat supply
By the decision of the regional maslikhat No. 23 of April 14, 2021, KZT 27 233.8 thousand were allocated from the regional budget for the development of 5 design and estimate documentation with the receipt of an opinion on the reconstruction of heating networks of Kyzylorda city. To date, public procurement procedures are underway.
Electricity supply
Public procurement procedures continue to determine the contractor for construction and installation works for the projects “Reconstruction of 35/10 kV SS“ GMZ ”,“ Komsomol ”,“ Zalineinaya ”,“ Promyshlennaya ”in Kyzylorda.
Based on the results of public procurement, the winner of the lot "Development of design and estimate documentation for the project" Power supply to the left bank of the Syrdarya river in the city of Kyzylorda, stage 2 "was determined. Currently, work has begun on the development of design and estimate documentation.
Funds allocated from the regional budget are used to conduct public procurement procedures to determine the design organizations for the development of design and estimate documentation for the project "Reconstruction of SS-220/110/35/10 kV" Shieli ".
Within the framework of the “Increase in the authorized capital of "KREK" JSC for the placement of 590 318 ordinary shares”, construction and installation work on the modernization of electric grids was completed. As a result, the consumers of the settlement are provided with a high-quality uninterrupted power supply.
Information on the work done for 12 months 2020 of the Department of Energy, Housing and Communal Services of Kyzylorda region
Gasification
In 2020, KZT 4.9 billion (KZT 4,911.8 million) were allocated for the implementation of 10 gas supply projects. Including the republican budget of KZT 3.5 billion (KZT 3 473.5 million), the regional budget - KZT 975.9 million, the "Employment Roadmap" - KZT 462.4 million. Of them:
- Within the framework of the "Employment Roadmap" program,
3 gas supply projects. Including the village of G.Muratbayev of the Kazaly district, Baysyn village of Shieli district, gas supply to the non-gasified streets of Aralsk town in Aral district.
- At the expense of the republican and regional budgets, the implementation of 3 projects was completed (Zhaksykylysh village of Aral district, Terenozek, Syrdarya district, non-gasified streets of Zhanakorgan village of Zhanakorgan district), 4 projects (Zhosaly village of Karmakshy district, Zhalagash of Zhalagash district, Kazaly town of Kazaly district, Bekezhanov village of Shieli district) rolling over to 2021.
As a result of the work carried out, 256.9 km of the gas pipeline were laid, more than 20 thousand residents of the region were able to use natural gas and the share of the gasified population increased to 65%.
For the development of 5 design and estimate documentation (installation of AGDS in the Saksaulsk settlement of the Aral region and the Shokai village of the Shieli region, the construction of intra-settlement gas supply networks for the settlements of Toretam, Akai in Karmakshy district and Birlik in Zhanakorgan district), KZT 91.8 million were allocated from the regional budget. As a result: gas supply projects for the settlements of Toretam, Akay and Birlik were sent for review by the state expertise, and the development of projects for the installation of automatic gas distribution stations in the settlements of Saksaulsk and Shokai are being transferred to 2021.
Water supply and sanitation
In 2020, for the restructuring and construction of water supply and sewerage systems under the state program "Nurly Zher", "Employment Roadmap", "Business Roadmap-2020", the special project "Auyl-El besigi" and only 4.6 billion were allocated from the regional budget. (republican budget - KZT 2.7 billion, regional budget - KZT 1.9 billion), 28 projects have been implemented, 2 projects are rolling over to 2021.
In 17 settlements of the region, 231 km of water supply and 8 km of sewerage networks, 23 sewage pumping stations were reconstructed and 6 water intake structures were built. Improved water supply for 151 thousand residents of the region.
KZT 3.3 billion has been allocated from the regional budget to subsidize water supply services in 178 rural settlements.
At the end of the year, 97.5% of the region's population is covered by a centralized water supply.
Heat supply
Within the framework of public-private partnership, by 2020, tender documentation has been developed for 7 projects and a tender has been held to determine a private partner. To date, the winner has signed an agreement on all 7 projects (13 social facilities). At present, construction and installation work has been completed on all projects and commissioned.
In addition, KZT 1.7 million were allocated from the regional budget for the development of design and estimate documentation with the receipt of the conclusion of the State Electoral Commission for the re-equipment of boiler houses of 2 social facilities in the field of sports and positive conclusions of the state examination was received.
In addition, within the framework of the "Employment Roadmap for 2020-2021" program for the allocated KZT 87,565.4 thousand, work has been completed to transfer boiler houses of 6 social facilities to gas heating.
As a result of the work carried out, boiler houses of 19 social facilities were transferred to gas heating, which in due time will give an opportunity to save public funds.
State utility company "Kyzylordateploelektrocenter" was put into operation in 1964 and is the only source of centralized heat supply in the regional center - Kyzylorda city.
Every year, during the heating season, in case of emergency situations, it is not possible to provide a reliable heat supply to residents of Kyzylorda city.
In this regard, in February 2019, at a meeting of the Security Council, this issue was raised, a decision was made to implement the project "Modernization and expansion of the Kyzylorda CHP in Kyzylorda." To date, a feasibility study has been developed for the project "Modernization and expansion of the Kyzylorda CHP in Kyzylorda city" and a state expert opinion has been received. At this time, work is underway to develop the design and estimate documentation.
In accordance with the "Comprehensive plan of socio-economic development of the Kyzylorda region for 2019-2022", it is planned to implement this project within three years.
This year, within the framework of the "Employment Roadmap for 2020-2021" and "Nurly Zher" program, an overhaul of 7.9 km of heating networks in the amount of KZT 4 billion was completed. Currently, the facilities have been commissioned.
For improvement
KZT 5,240,407.8 thousand have been allocated for the improvement, lighting and landscaping of regional centers and Kyzylorda city within the framework of the Employment Roadmap for 2020-2021 program.
Overhaul of apartment buildings
Currently, in Kyzylorda region, the number of apartment buildings requiring major repairs is 577 houses (47.2%).
In the current year, funds in the amount of KZT 2.079 billion were allocated from the republican budget for the overhaul of 34 apartment buildings (32 in Kyzylorda, 1 in Zhanakorgan district and 1 in Shieli district). All renovation work has now been completed.
Electricity supply
In 2020, for the development of power supply networks from the republican and regional budgets, KZT 3 billion 337 million were allocated (including from the Republic of Belarus - KZT 1 billion 300 million, from the regional budget - KZT 2 billion 37 million), these funds were completed and adopted in operation of 5 projects. Including:
Under the Regional Development Program - 1 project in Karmakshy district;
- "Reconstruction of SS-220/35/10 kV" Zhosaly "in Zhosaly village" (reconstruction of open switchgear with a voltage of 220/35 kV, construction of a general substation control center for a substation, replacement of a power transformer from 20,000 kVA to 25,000 kVA.);
Under the program "Employment Roadmap for 2020 -2021"
- “Expansion and reconstruction of substation 35/10 kV No. 22 of Toretam village "(reconstruction of a 35 kV open distribution device, construction of a general substation control center for a substation, replacement of a 6300 kVA transformer, project amount);
- "Expansion and reconstruction of 6-10 / 0.4 kV electrical networks in Toretam village and Akay rural district" (more than 96 km of 10 / 0.4 kV overhead lines were reconstructed, 33 sets of 10 / 0.4 kV KTPN-10 / 0.4 kV of various capacities were installed and 3031 units of metering devices).
These projects will help improve the reliability and energy efficiency of power supply to consumers, optimize power consumption modes and reduce losses through the use of modern equipment and new technologies, and prevent a shortage of electricity.
Under the "Business Roadmap 2025" program
- In Karmakshy district, in order to provide the external engineering infrastructure with networks for the construction of a poultry farm for the production of poultry meat with a capacity of 1500 tons per year in Aktobe settlement (power supply), a 14.1 km overhead line with a voltage of 10 kV was built and 1 unit of complete transformer substations of BKTP-1600 kVA type;
- In Kazali district, to provide the livestock farm of RZA JSC with a power supply, a 10 kV overhead line with a length of 10.3 km was built and a 1-unit two-transformer substation of the KTPN type 2x1600 kVA was installed.
Regional budget funds allocated to increase the authorized capital of KREK JSC
In 2019-2020, KZT 442.6 million were allocated from the regional budget in order to modernize the worn-out power supply systems of the settlements of Akkyr, Madeniet, Zhanadaria, Zhanatalap, Akkum and Bukharbai batyr of the Zhalagash district. Today, residents of the settlements of Akkyr, Madeniet and Zhanadaria are connected to the modernized power grids, construction and installation work continues in the remaining 3 settlements.
At the same time, 93.5 million tenge allocated from the regional budget were used to bring the illegally constructed electrical networks of six sections of the Sabalak dacha massif in Kyzylorda into compliance with the requirements of building codes (Shoemaker, financier, Monolith, Medic, Meliorator, Dorozhnik). As a result, 30 km of power lines with a voltage of 10/0, 4 kV were reconstructed, 6 units of complete transformer substations of various capacities were installed, as a result of these works, more than 540 consumers were provided with stable and high-quality electricity.
Utility tariffs
From September 1, 2020, due to the introduction of a temporary compensating tariff, an increase in the electricity tariff of GKP "KTETs", tariffs (including VAT) for 1m3 for services have been reduced
- water supply by 1.5% (from KZT 70.22 to 69.17), including for the population - from KZT 45.61 to 44.92;
- wastewater disposal by 2.8% (from KZT 77.80 to 75.64 ), for the population - from KZT 48.82 to 47.48.
Since September 11, 2020, due to the increase in tariffs at power generating stations (order of the Minister of Energy of the Republic of Kazakhstan No. 243 of June 14, 2020 "On approval of the maximum tariffs for supplied electricity"), tariffs for electricity supply services for the population have increased up to -4%, for legal persons 7.1%
Tariffs for heat and gas supply services remained unchanged.
On the work done for 9 months 2020 of the Department of Energy, Housing and Communal Services of Kyzylorda region
Gasification
Today, the share of the population with access to natural gas is 63%.
Since 2019, gas supply projects have been underway for 3 regional centers (Zhosaly, Zhalagash, Terenozek) and Zhaksykylysh village in Aral district. The total cost is 9 365.8 million tenge. Including the republican budget - 8 429.2 million tenge, the regional budget - 936.6 million tenge.
For 2020, 4,577.9 million tenge has been allocated for the implementation of these projects. Including: the republican budget - 3 753.6 million tenge, the regional budget - 824.3 million tenge. To date, 3 689.5 million tenge or 80.6% have been mastered.
In the first half of the year, a gas supply project for Zhaksykylysh village in Aral district was completed. More than 5 thousand residents of the village have the opportunity to use natural gas.
For the remaining 3 projects, construction and installation work is being carried out in accordance with the approved work schedules.
At the same time, 70.4 million tenge were allocated from the regional budget to complete the gas supply project for non-gasified streets of Zhanakorgan village. The object was put into operation.
91 million tenge was allocated from the regional budget for the development of gas supply projects for Toretam and Akay settlements in Karmakshy district. Today, the development of design estimates is underway.
Within the framework of the Employment Roadmap 2020, gas supply projects are being implemented in G. Muratbaev settlement in Kazaly district, Baisyn settlement in Shieli district and gas supply to non-gasified streets of Aralsk town. The total cost is 488.1 million tenge.
According to the program "Business Roadmap" from the regional budget for the project of gasification of the plant for the production of soda ash "AralSoda" LLP allocated 50 million tenge, work is underway.
Electricity supply
For the allocated in 2020 from the republican and regional budgets 1 640.4 million tenge (RB-965.6 million tenge, OB-164.1 million tenge), work continues on the reconstruction of the 220/35/10 kV substation “Zhosaly » in Zhosaly village, Karmakshy district, Kyzylorda region. (implementation period 2019-2020) As of October 01 of this year disbursed 919.6 million tenge (RB-848.3 million tenge, OB-71.4 million tenge). Upon completion of construction and installation work in December 2020, more than 18.9 thousand residents of Zhosaly settlement will be provided with an uninterrupted and high-quality power supply.
According to the program "Formation and increase of the authorized capital of legal entities" for the further development of electrical networks in Akkum village in Zhalagash district from the regional budget allocated 72.6 million tenge. Construction and installation work is currently underway.
Within the framework of the Employment Roadmap program for the project for the reconstruction of 6-10 / 0.4 kV electrical networks in the settlement Toretam and Akay, 35/10 kV substations in the settlement Toretam from the regional budget allocated 2,156.1 million tenge. To date, contracts have been concluded with contractors and construction and installation work has begun.
According to the program "Roadmap of business" from the Republic of Belarus under the project "Provision of external engineering infrastructure of the livestock farm of JSC" RZA "of Kazaly district of Kyzylorda region (power supply)" 228 398 thousand tenge were allocated from the republican budget. Currently, an agreement has been concluded with a contractor, construction and installation work has begun.
Within the framework of cooperation with the European Bank for Reconstruction and Development, a project with a total cost of 5.2 billion tenge is being implemented to modernize electrical networks in Kyzylorda and Shieli district. In accordance with the project, 70 substations and more than 300 km of electrical lines will be reconstructed. To date, 95% of the planned work has been completed. In connection with quarantine measures, the completion of the work is planned for the 4th quarter of 2020. As a result, consumers of the outskirts of Kyzylorda city and Shieli settlement will be supplied with an uninterrupted and high-quality power supply.
Water supply and sanitation
In 2020, 4.6 billion tenge was allocated for the reconstruction and construction of water supply and sewerage facilities in the region at the expense of all sources of financing for the implementation of 29 projects, of which RB - 2.7 billion tenge (2 655 364 thousand tenge), OB - 1.9 billion tenge (1 906 700 thousand tenge).
According to the financing plan of the reporting period, the development amounted to 2.5 billion tenge or 99 percent, including republican budget - 1.3 billion tenge (1,300,250.2 thousand tenge), regional budget - 1.2 billion tenge (1,245,609 thousand tenge). Incl. by programs:
Under the program "Development of Regions-2025"
For the implementation of 14 projects (of which 13 are rolling over from 2019 and 1 is new), 2.5 billion tenge (2 546 645 thousand tenge) were allocated, including, RB - 1.9 billion tenge (1 884 057 thousand tenge), co-financing from OB - 0.6 billion tenge (662 588 thousand tenge).
According to the financing plan for the reporting period, the disbursement of funds from the Republic of Belarus amounted to 1.1 billion tenge (1 052 715 thousand tenge) or 98%, from OB - 0.4 billion tenge (422 772 thousand tenge) or 99%.
According to the results of 9 months, 55.6 km of water supply networks were completed, the construction of 3 water intakes in the settlement was completed. Nauryz, Dosan, Talsuat of the city of Kyzylorda, there are acts of acceptance of objects for operation.
As a result of the full implementation of the projects, 200.9 km of water supply, 3.6 km of sewage networks, 23 sewage pumping stations, 7 units will be reconstructed/built. water intakes (Kyzylorda city - Nauryz - network, Belkul-2, Dosan, Karauyltobe, Talsuat, Karaozek EM - water intake, Taldyaral-set-kan-ya, 23 KNS, Zhalagash district - Daldabay, Zhanakonys, Shieli district -n - Tartogay, Shokai, Kazaly district - Tuktibaev, Aral district - Shomish).
According to the program "Auyl-el Besigi"
Implementation is underway for 2 projects (Bekarystan bi settlement, Kazaly district, Zhanakorgan settlement, Zhaakorgan district) in the amount of 702 252 thousand tenge, including republican budget - 648 079 thousand tenge, regional budget co-financing - 54 173 thousand tenge. According to the plan of the reporting period, the disbursement of funds from the Republic of Belarus amounted to 124.3 million tenge or 100 percent.
The projects will be implemented in 2020 with the commissioning of 214.1 km of service lines.
Under the Employment Roadmap program
At the expense of the regional budget, 12 projects are being implemented, including in Kazaly district (1), Syrdarya (1), Kyzylorda (10). in the amount of 876.6 million tenge (876 650 thousand tenge)
As of 01.10.2020. development amounted to 705.8 million tenge or 100 percent.
As a result, 28 km of water supply and 4.5 km of sewerage networks will be repaired, 214 jobs will be created.
Under the "Business Roadmap" program
The project "Provision of external engineering infrastructure for the construction of a poultry farm for the production of poultry meat with a capacity of 1,500 tons per year in Aktobe settlement , Karmakshy district", which is rolling since 2019, in 2020, 123,228.0 thousand tenge were allocated from the Republic of Belarus, which were fully utilized. For the complete completion of the facility, an additional 50,000 thousand tenge was allocated. As a result, 4.0 km of external water supply networks will be built.
Funds from the regional budget
For the continuation of work on the project "Additional exploration for the purpose of revaluation of the Talapa groundwater deposit in Kyzylorda region", which began in 2019, 31 796.0 thousand tenge were allocated in 2020, the development according to the financing plan is 100 percent. Completion - December 2020.
For the development of 4 design and estimate documentation (Baikogyr, Baykozha, MKOS Tasboget MKTS, SBO) - 197 143 thousand tenge, design work is underway.
For reference: the project for the water supply of the meat processing plant in the village of Talsuat, which began in 2019 (10.0 million tenge), was completed, 34 350.0 thousand tenge were allocated in 2020, the object was adopted by an act on 05/29/2020.
Subsidizing
3.3 billion tenge (3,273,927 thousand tenge) was allocated from the regional budget to subsidize local and group networks. Assimilation according to the financing plan of the reporting period is 100 percent. The number of RSs receiving subsidies is 178.
Heat supply
Within the framework of public-private partnership, by 2020, tender documentation has been developed for 7 projects and a tender has been held to determine a private partner. To date, the winner has signed an agreement on all 7 projects (13 social facilities). At present, construction and installation work has been completed on all projects and commissioned.
In addition, 1.7 million tenge were allocated from the regional budget for the development of design and estimate documentation with the receipt of the conclusion of the State Electoral Commission for the re-equipment of boiler houses of 2 social facilities in the field of sports. To date, positive conclusions of the state expertise have been received.
In addition, within the framework of the "Employment Roadmap for 2020-2021" program for the allocated 87,565.4 thousand tenge, work has been completed to transfer boiler houses of 6 social facilities to gas heating.
As a result of the work carried out, the boiler houses of 19 social facilities were transferred to gas heating, which in due time will make it possible to save public funds.
The state utility company "Kyzylordateploelektrocenter" was commissioned in 1964 and is the only source of centralized heat supply in the regional center - Kyzylorda city.
Every year, during the heating season, in case of emergency situations, it is not possible to provide reliable heat supply to residents of Kyzylorda city.
In this regard, in February 2019, at a meeting of the Security Council, this issue was raised, a decision was made to implement the project "Modernization and expansion of the Kyzylorda CHP in Kyzylorda." As of today, a feasibility study has been developed for the project "Modernization and expansion of the Kyzylorda CHP in Kyzylorda" and a state expert opinion has been received. At this time, work is underway to develop the design and estimate documentation.
In accordance with the "Comprehensive plan of socio-economic development of the Kyzylorda region for 2019-2022", it is planned to implement this project within three years.
This year, within the framework of the "Employment Roadmap for 2020-2021" and "Nurly Zher" program, an overhaul of 7.8 km of heating networks is being carried out in the amount of 4 billion tenge.
For improvement
5,240,407.8 thousand tenge were allocated for the improvement, lighting and landscaping of regional centers and the city of Kyzylorda within the framework of the Employment Roadmap for 2020-2021 program.
Overhaul of apartment buildings
Currently, in Kyzylorda region, the number of apartment buildings requiring major repairs is 611 houses (51.1%).
This year, for the overhaul of 34 apartment buildings (32 in Kyzylorda, 1 in Zhanakorgan district and 1 in Shieli district), funds in the amount of 2.079 billion tenge were allocated from the republican budget and the corresponding work is underway.
On the work done for I half of 2020 of the Department of Energy, Housing and Utilities of Kyzylorda region
Gasification
Today, the share of the population with access to natural gas is 63%.
Since 2019, gas supply projects have been underway for 3 regional centers (Zhosaly, Zhalagash, Terenozek) and Zhaksykylysh settlement in Aral district. The total cost is 9 365.8 million tenge. Including the Republican budget - 8 429.2 million tenge, the regional budget - 936.6 million tenge.
For 2020, 4,577.9 million tenge has been allocated for the implementation of these projects. Including the republican budget - 3 753.6 million tenge, the regional budget - 824.3 million tenge. To date, 2 511 million tenge or 54.8% have been mastered.
In the first half of the year, the project of gas supply to Zhaksykylysh settlement in Aral district was completed. More than 5 thousand residents of the village have the opportunity to use natural gas.
For the remaining 3 projects, construction and installation work is being carried out by the approved work schedules.
At the same time, 70.4 million tenge were allocated from the regional budget to complete the gas supply project for the non-gasified streets of Zhanakorgan settlement. The object was put into operation.
91 million tenge were allocated from the regional budget for the development of gas supply projects for the settlements of Toretam, Akay of Karmakshy district. Today, the development of design estimates is underway.
Within the framework of the "Employment Roadmap 2020", gas supply projects are being implemented in G. Muratbaev settlement in Kazaly district, Baisyn settlement in Shieli district and gas supply to non-gasified streets of Aralsk town. The total cost is 488.1 million tenge.
Electricity supply
For the allocated in 2020 from the republican and regional budgets 1 056.3 million tenge (RB-892.2 million tenge, OB- 164.1 million tenge), work continues on the reconstruction of the 220/35/10 kV substation " Zhosaly "in Zhosaly settlement, Karmakshy district, Kyzylorda region. On July 01 of this year 627.9 million tenge were mastered (RB-556.5 million tenge, OB-74.4 million tenge). Upon completion of construction and installation work in September 2020, more than 18.9 thousand residents of Zhosaly settlement will be provided with uninterrupted and high-quality power supply.
According to the program "Formation and increase of the authorized capital of legal entities" for the further development of electrical networks in Akkum settlement of Zhalagash district from the regional budget allocated 72.6 million tenge. Construction and installation work is currently underway.
Within the framework of the Employment Roadmap program for the project for the reconstruction of 6-10 / 0.4 kV electrical networks in the settlement Toretam and Akai, 35/10 kV substations in the settlement Toretas were allocated 2,156.1 million tenge from the regional budget. To date, contracts have been concluded with contractors and construction and installation work has begun.
For the implementation of projects for the reconstruction of electric power facilities for financing from OB, budget applications for the amount of 6,368.8 mln. tenge for the projects "Reconstruction of the substation 35 / 10kV" GMZ "; "Silicate"; "Komsomol"; "Zalineinaya" and "Promyshlennaya" in Kyzylorda city".
According to the program "Roadmap of business" from the Republic of Belarus under the project "Provision of external engineering infrastructure of the livestock farm of JSC" RZA "of the Kazaly district of Kyzylorda region (power supply)" 228 398 thousand tenge were allocated from the republican budget. Currently, an agreement has been concluded with a contractor, construction and installation work has begun.
Within the framework of cooperation with the European Bank for Reconstruction and Development, a project with a total cost of 5.2 billion tenge is being implemented to modernize electrical networks in Kyzylorda city and Shieli district. In accordance with the project, 70 substations and more than 300 km of electrical lines will be reconstructed. To date, 85% of the planned work has been completed. Due to quarantine measures, the completion of work is scheduled for the 3rd quarter of 2020. As a result, consumers on the outskirts of Kyzylorda city and Shieli settlement will be supplied with uninterrupted and high-quality power supply.
Water supply and sanitation
In 2020, 4.7 billion tenge was allocated from all budgetary sources for the implementation of 32 projects for the reconstruction/construction of water supply/sewerage facilities in the region, incl. RB - 2.7 billion teңge (2 655 364 thousand tenge), OB - 2.0 billion tenge (2,016 144 thousand tenge).
When re-allocated in tg. sequestered funds (Shomish - 100.0 million tenge; poultry farm - 50.0 million tons), 423.1 km of water supply and 13.3 km of sewage networks, 23 sewage pumping stations, 7 units will be built. water intakes explored and assessed 1 groundwater deposit, prepared 5 design estimates.
At the same time, 3.3 billion tenge (3,273,927 thousand tenge) are provided from OB for 2020, which are mastered monthly according to the financing plan for subsidizing local and group water supply systems.
For reference, in terms of programs:
Under the program "Development of Regions-2025" for the implementation of 13 projects (of which 12 are rolling over from 2019 and 1 is new), 2.4 billion tenge (2.409,024 thousand tenge) were allocated, including RB - 1, 9 billion tenge (1 884 057 thousand tenge), co-financing from OB - 0.5 billion tenge (524 967 my tenge).
For the full completion of these projects in 2020, it is necessary - RB-100.0 million tenge; OB - 116.579 million tenge
As a result, 177 km of water supply, 3.6 km of sewage networks, 23 sewage pumping stations, 7 units will be reconstructed/built. water intakes (Kyzylorda city - Nauryz - network, Belkul-2, Dosan, Karauyltobe, Talsuat, Karaozek E.M. - water intake, Taldyaral-set-kan-ya, 23 KNS, Zhalagash district - Daldabay, Zhanakonys, Shieli district -n - Tartogay, Shokay, Aral district - Shomish).
According to the special project "Auyl-el Besigi" for 2 projects (Kazalinsky district - Bekarystan bi, Kent Zhanakorgan) - 702 252 MYң tenge, including, RB - 648 079 thousand tenge; OB - 54,173 thousand tenge.
Currently, contractors have been identified, construction and installation work are underway. The projects will be implemented in 2020 with the commissioning of 214.1 km of service lines.
According to the Employment Roadmap program, 912 million tenge (911 983 thousand tenge) were allocated for 12 projects from OB, including in Kazaly district (1), Syrdarya (1), Kyzylorda (10).
Currently, contractors have been identified, construction and installation work are underway. As a result, 28 km of water supply and 4.5 km of sewerage networks will be repaired, 214 jobs will be opened.
Under the program "Business Roadmap 2020", the project "Providing networks of external engineering infrastructure for the construction of a poultry farm for the production of poultry meat with a capacity of 1500 tons per year in the settlement of Aktobe, Karmakshy district", which is rolling from 2019, in 2020, 123,228.0 thousand tenge and construction and installation work is underway.
To complete the object, 50,000 thousand tenge is required from the Republic of Belarus. As a result, 4.0 km of external water supply networks will be built.
Funds from the regional budget
- 31,796.0 thousand tenge were allocated in 2020 for the “Additional exploration for revaluation of the Talapa groundwater deposit in the Kyzylorda region”, which began in 2019, work is underway. Completion - November 2020.
- 222,764 thousand tenge was allocated for the reconstruction of sewage networks in Kyzylorda (DIA, Kamkor, Supermarket);
- for the development of 5 design and estimate documentation (Baykogyr, RZA, Baykozha, MKOS Tasboget MKTS, SBO) - 267,907 thousand tenge, design work is underway.
Subsidizing
3.3 billion tenge (3,273,927 thousand tenge) were allocated from OB to subsidize local and group networks. The number of RSs receiving subsidies is 184.
Heat supply
Within the framework of public-private partnership, by 2020, tender documentation has been developed for 7 projects and a tender has been held to determine a private partner. To date, the winner has signed an agreement on all 7 projects (13 social facilities). Currently, construction and installation work is underway on all projects.
Also, 1.7 million tenge were allocated from the regional budget for the development of design and estimate documentation with the receipt of the conclusion of the State Economic Commission for the re-equipment of boiler houses of 2 social facilities in the field of sports. As of today, the conclusions of the state examination have been received for 1 project, for the remaining 1 projects, work is underway to obtain an expert opinion.
Also, within the framework of the Employment Roadmap for 2020-2021 program, work is underway to replace steam boilers in 6 social facilities with gas heating, in the amount of 87,565.4 thousand tenge.
As a result of the work carried out, the boiler houses of 19 social facilities will be transferred to gas heating, which will make it possible to save public funds and reduce a one-time burden on the budget.
The state utility company "Kyzylordateploelektrocenter" was commissioned in 1964 and is the only source of centralized heat supply in the regional center - the city of Kyzylorda.
Every year, during the heating season, in case of emergencies, it is not possible to provide reliable heat supply to residents of the city of Kyzylorda.
In this regard, in February 2019, at a meeting of the Security Council, this issue was raised, a decision was made to implement the project "Modernization and expansion of the Kyzylorda CHP in Kyzylorda."
By the "Comprehensive plan of socio-economic development of the Kyzylorda region for 2019-2022", it is planned to implement this project within three years.
This year, within the framework of the "Employment Roadmap for 2020-2021" and "Nurly Zher" programs, a major overhaul of 7.3 km of heating networks is being carried out for 3.9 billion tenge.
On improvement
5,240,407.8 thousand tenge has been allocated for the improvement, lighting, and landscaping of regional centers and the city of Kyzylorda within the framework of the Employment Roadmap for 2020-2021 program.
Overhaul of apartment buildings
At present, in the Kyzylorda region, the number of apartment buildings requiring capital repairs is 611 houses.
In 2019, the repair work of 10 apartment buildings was completed (Kyzylorda - 2 houses, Aralsky district - 5 houses, Karmakshy district - 2 houses, Zhalagash district - 1 house).
As a result, the share of condominium objects requiring major repairs from the total number of multi-apartment residential buildings decreased from 52.8 percent to 51.1 percent.
This year, for the overhaul of 34 apartment buildings (32 in Kyzylorda, 1 in Zhanakorgan district, and 1 in Shieli district), funds for 2.079 billion tenge were allocated from the republican budget and the corresponding work is underway.
On the work done for 12 months of 2019
by the Department of energy, housing and communal services of Kyzylorda region
On gasification
For 2019, KZT 4 349 556 thousand were allocated from the republican budget. Including: KZT 1 174.6 million for the completion of 2 projects ("Construction of gas distribution networks of the left bank of the Syrdaria river in Kyzylorda city" and "Construction of a gas pipeline branch from the main the Beineu-Shymkent gas pipeline with the installation of an AGRS in Terenuzyak village "), KZT 3174.9 million launched a gasification project for 4 settlements (Zhosaly, Zhalagash, Terenozek, Zhaksykylysh).
In addition, 208.8 million was allocated from the regional budget for co-financing. tenge. The following work was carried out on the projects:
1. Under the project "Construction of gas distribution networks on the left bank of the Syrdarya river in Kyzylorda city" (stage 1 - a high-pressure supply gas pipeline 1.2 MPa from AGRS-1 with installation of GRGP-2) "construction and installation works are fully completed. The facility was commissioned in August 2019.
2. The construction work was completed under the project "Construction of a gas pipeline branch from the Beineu-Shymkent gas pipeline with the installation of an AGRS in Terenuzyak village. The object was adopted by state acceptance certificate on September 25, 2019.
3. Work has begun on the gasification of 4 settlements (Zhosaly, Zhalagash, Terenozek, Zhaksykylysh), currently 50-55% of construction and installation works have been completed. Currently, 184.2 km of gas pipelines have been welded and 6 units installed. Hydraulic fracturing, 3 units ShRP. Construction of projects will be completed in 2020.
4. In 2019, KZT 139.9 million were allocated from the regional budget for the project "Supply of a gas pipeline to residential buildings in AIteke bi of Kazaly district". According to the project, construction and installation works were carried out, 7.8 km of gas pipelines were built, 2 units were installed. ShRPV now the facility is fully completed and put into operation.
5. Under the project "Construction of intra-quarter gas distribution networks in Zhanakorgan village, Zhanakorgan district," KZT 88.2 million were allocated from the regional budget, 9.7 km of gas pipelines were completed, 1 unit was installed.
KZT 6. 13.9 million were allocated from the regional budget for the development of design and estimate documentation and the receipt of a state expert review of the project “Gas Supply to Kazaly town in Kazaly district”, and a positive state expert opinion has been received on this project.
On power supply
In 2019, the first phase of the construction of electric networks of the left-bank part of the Syrdarya river in Kyzylorda city was completed, and a substation with a capacity of 32 MVA was put into operation. Residents of the left bank, household and social facilities are equipped with uninterrupted electric energy.
For the KZT 510.6 million allocated from the republican budget, reconstruction of the Zhosaly 220/35/10 kV substation of Kyzylorda region has begun. Upon completion of construction and installation work in 2020, more than 34 thousand residents of KentZhosaly will be uninterruptedly supplied with high-quality electric energy.
A positive conclusion was received from the state examination of projects for the reconstruction of the substation SS 35/10 kV "GMZ", "Silikatnaya", "Komsomol", "Zalineinaya", "Promyshlennaya" in Kyzylorda city.
Within the framework of the state program “Business Road Map 2020” under the project “Power Supply for the Farm of the Bekarys and K Production Cooperative in Zhanakorgan district of Kyzylorda region”, 15 km of electric lines were built, 8 units were installed transformer substations.
At the same time, within the framework of this program, construction and installation works are underway to supply electricity to the greenhouse complex with an area of 2.157 hectares in Makhambet rural district. A block-modular transformer substation with a capacity of 2x1600 kVA was installed and 5.4 km of electric networks were built.
In the framework of cooperation with the European Bank for Reconstruction and Development, a project is being implemented with a total value of KZT 5.2 billion for the modernization of electric networks in Kyzylorda city and Shieli district.
In accordance with the project, 52 substations and more than 300 km of electric lines will be reconstructed. To date, 80% of the planned work has been completed. Completion date is the 2nd quarter of 2020. As a result, consumers on the outskirts of Shieli will be provided with uninterrupted and high-quality power supply.
Two solar power plants with a total capacity of 80 MW were commissioned in Zhalagash and Shieli districts of the region, built at the expense of investors. Opened 70 new jobs. The project has a positive impact in the implementation of the Concept of the Republic of Kazakhstan on the transition to a "green economy".
On heat supply
In 2019, as part of a public-private partnership, the boiler rooms of 4 social facilities of the Aral Sea and 9 facilities of Shieli districts were switched to gas heating, and today maintenance work is underway. As a result, when converting 13 social facilities to gas heating, the amount of funds allocated for fuel will decrease by 3-4 times.
At the same time, on 7 PPP projects on the conversion of 13 social facilities to boiler houses gas, tender documentation was developed, and a private partner was determined. Construction and installation work will be carried out in 2020.
In addition, KZT 29.1 million were allocated from the regional budget for the development of design and estimate documentation with the conclusion of the GoE for the conversion of boiler houses to 6 social facilities in the field of sports. To date, the conclusions of the state examination have been received for 4 projects, and work is underway on the remaining 2 projects to obtain the expert opinion. In the coming year, as part of a public-private partnership, 6 social facilities in the field of sports will be converted to gas heating.
As a result of the work, boiler rooms of 13 social facilities will be converted to gas heating, will make it possible to save state funds and reduce a one-time burden on the budget.
On the reconstruction of the Belkul boiler house of the public utility company KTETs in Kyzylorda city, construction and installation work has been completed and commissioned. As a result, 1335 residents and 3 social facilities are provided with uninterrupted and high-quality heat supply.
The state utility company “Kyzylordateploelectrocenter” was commissioned in 1964 and is the only source of district heating for the regional center - Kyzylorda city.
Every year during the heating season during emergency situations, it is not possible to provide reliable heat supply to the residents of Kyzylorda city.
In this regard, in February 2019, at a meeting of the Security Council, this issue was raised, a decision was made on the implementation of the project “Modernization and expansion of the Kyzylorda CHPP in Kyzylorda”.
In accordance with the "Comprehensive Plan for the Social and Economic Development of Kyzylorda region for 2019-2022," it is planned to implement this project within three years.
On beautification
To the amount of 145 million tenge allocated from the regional budget, the corresponding works on improvement, lighting and greening of Kyzylorda city were carried out.
Overhaul of apartment buildings
Currently, in Kyzylorda region, the number of apartment buildings requiring major repairs is 610 houses.
In 2019, repairs were completed on 10 multi-apartment residential buildings (Kyzylorda - 3 houses, Aral region - 4 houses, Karmakshy district - 2 houses, Zhalagash district - 1 house).
As a result, the share of condominium facilities requiring major repairs of the total number of multi-apartment residential buildings decreased from 52.8 percent to 50.5 percent.
Water supply and sanitation
In 2019, within the framework of the Nurly Zhol and Development of Regions programs and funds from OB for the implementation of 34 projects and the development of 4 design and estimate documentation, KZT 8.8 billion (KZT 8 802 789 thousand) was allotted. Including 8.2 billion tenge from Belarus (KZT 8,206,062 thousand), regional budget -KZT 597 million(KZT 596,727 thousand).
About KZT 8.8 billion (KZT 8,775,747 thousand) or 99.7% was mastered.
In 2019, work was completed on 19 projects (the cities of Kyzylorda - Brkazan, Dosan, Karauyltobe, Nauryz, Sabalak, the greenhouse complex, Torangylsai, Korkyt ata, Esenov str., Aral district - Saksaulsk, AralSoda, Kazalinsky - Tuktibaev, Karmakin - Karmakin, Karmakin - Karimyak, Karmakin - Tuktibaev, Karmak Zhalagashsky - Zhanadaria, Akkyr, Makpalkol, Shieli - May 1, Botabay, Kent Zhanakorgan). Reconstructed 524 km of water supply and 2.5 km of sewer networks. The remaining 15 projects are rolling over to 2020.
In the context of programs.
On the Nurly Zhol program
The project launched in 2017 for the reconstruction and expansion of the water supply system in Kent Zhanakorgan was adopted by an act in September 2019. Total allocated KZT 3.9 billion (KZT 3 939 941 thousand). 189.1 km of water supply networks were built.
On the program "Regional Development"
For the implementation of 24 projects allocated KZT 6.8 billion (republican budget- KZT6 575 657 thousand; regional budget- KZT 229 332 thousand).
In 2019, 12 projects were completed.
(Kyzylorda - Birkazan, Dosan, Karauyltobe, Nauryz, Sabalak, Korkyt ata street, Yesenov, Aral region - Saksaulsk, Kazalinsky - Tuktibaev, Zhalagashsky - Zhanadaria, Akkyr, Makpalkol).
289.6 km of water supply and 2.5 sewer networks were reconstructed. The remaining 12 projects are rolling over to 2020.
(Kyzylorda - Nauryz network, Belkol - 2, Dosan, Karauyltobe, Talsuat, Karaozek - water intakes, Taldyaral, 23 KNS, Zhalagash district - Daldabay, Zhanakonys, Shieliysky - Tartogai, Shokai).
With funds from the regional budget
In 2019, KZT 367 million (KZT 367,394 thousand) was allocated for the implementation of 9 projects and the development of 4 design and estimate documentation, including for water supply:
May 1 settlement, Botabay of Shieli district KZT 143 million (KZT 143,029 thousand), fully mastered, 25.3 km of networks built;
Akai settlement of Karmakshy district 57 million tenge (56 825 thousand tenge), fully mastered, built 16.4 km of networks;
KZT 56 million (KZT 55,742 thousand) have been fully utilized for additional exploration with revaluation of groundwater reserves of the Torangylsai field. Received protocol.
for tying the exploratory well No. 6733 for water supply to the greenhouse complex KZT 27 million (KZT 26,690 thousand), fully mastered, 1 well drilled;
AralSoda plant with a capacity of 300 thousand tons and KZT 28 million (28,109 million tons) were fully utilized for water supply, 3.9 km of networks were built;
poultry farms with a capacity of 1.5 thousand tons of poultry meat in Aktobe village of Karmakshy district KZT 25 million (KZT 25,000 thousand) has been fully mastered, the project is moving on to 2020;
meat processing plant in Talsuat settlement of Kyzylorda city KZT 10 million (KZT 10,000 thousand) has been fully utilized, the facility is moving on to 2020;
revaluation of underground water reserves of the Torangylsai field KZT 10 million (KZT 10,000 thousand) has been fully utilized, the project is moving on to 2020;
development of design and estimate documentation for electric and gas supply of SBO in Titov settlement with a capacity of 70.0 thousand mz / day KZT 1 million (KZT 1000 thousand) has been fully mastered, the project is going on in 2020;
the development of design and estimate documentation for the construction of a pressure head sewage in 2 strands from MKOM “Tasboget” to the SBO in the village of Titov KZT 5 million (KZT 5,000 thousand) has been fully mastered, the project is moving on to 2020;
the development of design and estimate documentation for the reconstruction of the Baykhozhinsky GV in Kazaly district of 5 million (KZT 5,000 thousand) has not been mastered, the object is moving to 2020. (Reason: later determination of the contractor, the amount remains in the budget of the Kazaly district);
the development of design and estimate documentation for the reconstruction of water supply and wastewater systems KZT 1 million (KZT 1,000 thousand) has not been mastered, the object is rolling over to 2020. (Reason: the winner of public procurement has not been determined, the amount remains in the budget of the UEHKH);
Subsidies
A total of KZT 3.2 billion (KZT 3,214,339 thousand) was allocated for subsidizing group and local water supply systems, including KZT 3.1 billion (KZT 3,138,376 thousand) from the region, and RB - KZT 75 million (KZT 75 963 thousand). Funds are fully utilized. The number of SORs receiving a subsidy is 184.