Information on the implementation of the action plan (I quarter 2020)
|
№ |
The content of the question |
Execution |
|
1 |
Paving of local streets in village Besaryk (P. Miniyarov, V. Muratbaev) |
Developed design and estimate documentation for medium repair of roads in the village Besaryk on the street Managarova, Muratbaev total length of 3.61 km and presents budget request to regional management of passenger transport and motor roads totaling 103 474,0 thousand tenge. |
|
2 |
Repair of the office building of Kazpost JSC in Chagan village |
It is planned to carry out current repairs of the building of the branch of Kazpost JSC. |
|
3 |
Repair of local streets of the village Kalzhan Akhun (Kaiky Batyr, N. Sadirbaev) |
The Department of housing and communal services, passenger transport and highways developed design and estimate documentation for the average repair of Kaiky Batyr and N. Shiderbayev streets and submitted it to the regional budget; Recommended for funding to the district budget for the installation of a video surveillance system; Funds have been allocated from the district budget for lighting Beibitshilik street and public procurement is being carried out; Works on lighting N. Shiderbayev street will be carried out from the district budget. |
|
4 |
Major repairs of the outpatient clinic in the village of Kalzhan Akhun |
Current repairs are planned through the regional health Department in 2020. |
|
5 |
Repair of intra-village streets of the village of Seifullina and construction of a sidewalk on Sarke Batyr street for pedestrians |
Developed design and estimate documentation for medium repair of roads of the streets Ascoli, Andrei, Aulby, Murat, byte Batyr Than a total length of 5.94 km, for a total amount of 105 thousand tenge: 142.0 cm presents budget request to regional management of passenger transport and motor roads. 241.1 thousand tenge was allocated for the development of design and estimate documentation for the construction of the sidewalk on Sarke Batyr street. |
|
6 |
Major repairs of school No. 137 in Seifullina Village |
Funds were allocated from the district budget for the development of POI for major repairs. |
|
7 |
Construction of a new building of a medical dispensary in the village of tokmagambetova |
The cost 164,9 million dollars. Department of health West Kazakhstan region announces a competition for the project of public-private partnership for the construction of tenge outpatient clinics. |
|
8 |
Work on laying the stone on the street So children in the village of Terenozek |
This year, the design and estimate documentation for the asphalting of T. Kozybayev street will be developed, and a budget application for 2021 will be submitted. |
|
9 |
Lighting street Kyzyldyikan in the village of Terenozek |
In connection with the lighting of Kyzyldikhan street in the village, funds will be provided from the budget for the development of POI. |