Completed works on gasification of settlements in the district for the III quarter of 2026
On gasification:
For the gasification of the settlement of Akzharma, the project cost is 1.8 billion tenge. For 2025–2026, 1.8 billion tenge was allocated from the republican budget, and these funds have been fully utilized. This facility was put into operation in August of the current year. From the republican budget, 400.0 million tenge was allocated for the project “Construction of laid gas pipelines and intra‑block gas pipelines in the settlement of Shirkeyli, Syrdarya District, Kyzylorda Region,” with a project cost of 1.3 billion tenge for 2026. In particular, 320.0 million tenge was allocated from the republican budget for 2026 for the project “Construction of laid gas pipelines and intra‑block gas pipelines in the settlement of Kogalykol, Syrdarya District, Kyzylorda Region,” with a cost of 1.1 billion tenge. Contracting organizations have been identified based on the results of public procurement, and work is currently underway to conclude the contracts.
Completed works on gasification of settlements in the district for the II quarter of 2026
On gasification:
The cost of the project for the gasification of the village of Akzharma is 1.8 billion tenge. In 2025, 840.7 million tenge was allocated from the republican budget, and high-pressure gas pipelines with a length of 17.5 km were completed. To complete the project in 2026, the necessary funds have been allocated, and as of today, the contractor company "Aliya Service" has completed low-pressure gas pipelines within the village with a length of 25.1 km, and construction and installation work is currently underway.
Completed works on gasification of settlements in the district for the I quarter of 2026
Gasification Within the framework of the project "Construction of a supply pipeline and intra-quarter gas distribution networks in the village of Akzharma, Syrdariya district, Kyzylorda region" (contract value: 1 billion 875.7 million tenge), funds were allocated from the republican and regional budgets for 2025–2026. Currently, the contractor, "Aliya Service" LLP, is carrying out gas pipeline installation. The facility is scheduled to be commissioned in the summer of this year.
Completed works on gasification of settlements in the district for the IV quarter of 2025
On gasification: The cost of the project is 1.1 billion tenge from the Republican budget for 2025, 199.9 million tenge from the regional budget for the complete completion of construction and installation works of the gasification facility of the Chagan settlement, the cost of which is 2.6 billion tenge. The facility was commissioned in November 2025. The contractor is NPP and Limited LLP. The cost of the project – 840.7 million tenge was allocated from the Republican budget for 2025 to start the construction of the akzharma village gasification project in the amount of 1.8 billion tenge. Additionally, for 2026, the Republican and regional budgets allocated the necessary funds for the complete completion of the project.In 2025, the indicator of gas supply by the number of settlements in the district was 42%.
Completed works on gasification of settlements in the district for the III quarter of 2025
On gasification: For the complete completion of construction and installation works of the gasification facility of the settlement of Shagan, the cost of the project is 2.6 billion tenge, 1.1 billion tenge was allocated from the republican budget for 2025. Tenge. As of today, construction and installation work is being carried out by a contracting agency.
Completed works on gasification of settlements in the district for the II quarter of 2025
On gasification: For the completion of construction and installation works of the gasification facility of the settlement of N. Ilyasova, the cost of the project is 661.4 million tenge, 39.3 million tenge was allocated from the local budget for 2025. To date, construction and installation works of this facility are fully completed and the facility is put into operation.
For the complete completion of construction and installation works of the gasification facility of the settlement of Shagan, the cost of the project is 2.6 billion tenge, 1.1 billion tenge was allocated from the republican budget for 2025. Tenge. To date, the contractor has completed 35 km of medium and low-pressure gas pipelines.
This year, 200.0 million tenge has been allocated from the national budget for the construction of a gas pipeline and intra-neighborhood gas distribution networks in the village of Akzharma, Syrdarya District, Kyzylorda Region. The project is estimated to cost 1.8 billion tenge. Currently, work is underway to organize competitive bidding through the web portal of public procurement.
Completed works on gasification of settlements in the district for the I quarter of 2025
For gasification:
39.3 million tenge was allocated from the local budget for 2025 for the complete completion of the construction and installation works of the gasification facility of the settlement of N. Ilyasov, the cost of the project is 661.4 million tenge. To date, in order to continue the construction and installation works of this facility, the contractor is working on the construction of gas pipelines. 1.1 billion tenge was allocated from the Republican budget for the full completion of the construction and installation works of the gasification facility of the settlement of Chagan, the cost of the project is 2.6 billion tenge, and to date, in order to continue the construction and installation works of this facility, the contractor has established 16.0 km of medium and low pressure gas pipelines were carried out through it. The project cost is теңг 200.0 million from the Republican budget for 2025 for the start of construction "construction of a supply gas pipeline and intra-block gas distribution networks in Akzharma village of Syrdarya District of Kyzylorda region" worth 1.8 billion tenge. tenge was allocated, and an application with relevant documents was sent to the Kyzylorda Regional Department of public procurement for the organization of the competition through the web portal of Public Procurement.
Completed works on gasification of settlements in the district for the IV quarter of 2024
On gasification:According to the gasification project of the settlements of A. Tokmaganbetov, S. Seifullin, the project cost is 962.3 million tenge, the contract value is 913.1 million tenge. In 2023, 40.0 million tenge was allocated from the regional budget for these works, and in 2024, 150.0 million tenge was allocated from the republican budget and 723.1 million tenge was withdrawn from the regional budget. The allocated funds have been fully utilized. These facilities were accepted and put into operation by the act of state acceptance in November 2024. The works were performed by the contractor AES and Limited LLP. In 2024, 595.3 million tenge were allocated from the regional budget for the start of construction work on the gasification project of the settlement of N.Ilyasov, the project cost is 661.4 million tenge. These funds have been fully disbursed, and the project is transitional for 2025. The contractor is Trans Asia Construction LLP. For 2024, the project "Gasification of the settlement of Shagan" was allocated from the republican budget.
Completed works on gasification of settlements in the district for the III quarter of 2024
On gasification: 4 projects (transitioning) are underway for gasification in the district, of which 2 projects have been completed by 98%, the remaining 2 projects are currently undergoing construction and installation work through contractors. Namely: The cost of the project is 514.8 million tenge for the gasification of the settlement of A.Tokmaganbetov, 20.0 million tenge was allocated from the regional budget for 2023, 100.0 million tenge from the republican budget for 2024. 28.8 million tenge has been allocated from the regional budget, a total of 22.8 km of gas pipelines have been carried out, construction work is scheduled to be completed in October and put into operation in accordance with the plan. For reference: the cost of the contract is 488.5 million tenge, on June 19, 2024, the regular session of the regional maslikhat allocated 339.7 million tenge for the full completion of the project. According to the plan, 305.7 million tenge was allocated and disbursed for the months of June and July, the remaining 10% - 34.0 million tenge, disbursement is planned for the month of October.
1) For the gasification of the settlement of S. Seifullina: the cost of the project is 447.5 million tenge, 20.0 million tenge was allocated from the regional budget for 2023 and 50.0 million tenge was allocated from the republican budget for 2024, 22.2 million tenge from the regional budget. A total of 25.8 km of gas pipelines will be laid, construction work is scheduled to be completed in October and put into operation in accordance with the plan. For reference: the cost of the contract is 424.6 million tenge, on June 19, 2024, the regular session of the regional maslikhat allocated 332.2 million tenge for the full completion of the project. According to the plan, 298.9 million tenge was disbursed in June and July, the remaining 10 percent was 33.3 million tenge. The development is planned for October. 2) 595.3 million tenge has been allocated from the regional budget for the gasification project of the settlement of N.Ilyasov, worth 661.4 million tenge, and construction and installation works are currently being carried out by contractors. The project is transitional for 2025. For reference: in 2023, 10 million tenge was allocated for the gasification of the settlement of N.Ilyasov. 595.3 million tenge has been allocated from the regional budget for 2024, to date, the contractor Trans Asia Construction LLP has laid 15 km of gas pipelines, construction and installation works are underway. 3) 100.0 million tenge has been allocated from the republican budget for 2024 for the start of construction work on the gasification project of the settlement of Chagan, worth 2.6 billion tenge, 1.0 billion tenge has been allocated from the regional budget, to date, construction and installation work is underway by the contractor AES and Limited LLP. The project is transitional for 2025.
Completed works on gasification of settlements in the district for the II quarter of 2024
On gasification, 4 projects are being carried out in the district, of which 2 projects are completed by 90%, the remaining 1 project is being signed by additional contracts with contractors, and public procurement is being carried out for 1 project. In particular,
For reference: the cost of the contract is 488.5 million.Tenge, the remaining funds for the complete completion of the project – 339.7 million tenge, execution – 95%.
2.the project cost is 50.0 million tenge from the Republican budget in 2024 for gasification of the settlement of S. Seifullin in the amount of 447.5 million tenge. KZT 22.2 million from the regional budget.tenge has been allocated, a total of 25.8 km of gas pipelines have been laid, and work is underway to release a gas pipeline for residential buildings (exit).
For reference: the cost of the contract is 424.6 million.Tenge, the remaining funds for the complete completion of the project – 332.2 million tenge, execution-95%
For reference: in 2023, 10.0 thousand tenge was allocated for gasification of the settlement of N. Ilyasov, as a result of public procurement, the contractor was identified "Trans Asia construction" LLP.The cost of the contract is 602.1 million.tenge
Completed works on gasification of settlements in the district for the I quarter of 2024
On gas supply: For the project "Construction of intra-block gas distribution networks and traction gas pipeline of the settlement of S.Seifullina of the Syrdarya district of the Kyzylorda region" worth 447.4 million tenge was allocated, of which: 20.0 million tenge from the regional budget for 2023, 50.0 million tenge was allocated from the republican budget for 2024, 22.4 million tenge was allocated from the regional budget. The total length of the gas pipelines in the project is 25.8 km, gas control cabinet points (GRSHP) are provided in the amount of 5 pieces.To date, -23.7 km of the gas pipeline has been laid through the Contracting Institution of AES and Limited LLP and relevant work is underway. For the full completion of this project, 332.2 million tenge has been allocated from the republican budget for financing through the Department of Energy and Housing and Communal Services of the Kyzylorda region, an application has been submitted to the Ministry of Energy of the Republic of Kazakhstan for 2024. Funding is expected.
The cost of the project is 514.8 million tenge. 20.0 million tenge was allocated from the regional budget for 2023, 100.0 million tenge was allocated from the republican budget, 28.8 million tenge was allocated from the regional budget for 2024 for the project "Construction of intra-block gas distribution networks and suppliers to the settlement of A. Tokmaganbetov of the Syrdarya district of the Kyzylorda region".
The total length of the gas pipelines in the project is 22.8 km, gas control cabinet points (GRSHP) are provided in the amount of 4 pieces. The contractor has laid 21.2 km of gas pipeline through AES and Limited LLP, and currently work is underway to lay a gas pipeline under highways inside the settlement (HDD) by horizontal drilling. 339.7 million rubles have been allocated from the republican budget for the full completion of this project. tenge for financing through the Department of Energy and Housing and Communal Services of the Kyzylorda region, an application has been submitted to the Ministry of Energy of the Republic of Kazakhstan for 2024.Funding is expected.
The cost of the project is 2.6 billion tenge for the project "Construction of intra-block gas distribution networks and a traction gas pipeline in the settlement of Shagan in the Syrdarya district of the Kyzylorda region", 100.0 million tenge has been allocated from the republican budget for 2024, currently work is underway on public procurement in order to identify contractors.
In order to fully implement this project, an application was submitted to the regional Department of Energy and Housing and Communal Services for 2024-2025.Funding is expected.
Completed works on gasification of settlements in the district for the IV quarter of 2023
To date, 1894 individual residential buildings of 2514 houses, 276 apartments of 40 multi-storey residential buildings and 19 social facilities and 18 institutions, 85 business entities are connected to gas, 116 individual residential buildings of 220 houses, 1 institution, 1 social facility are connected to gas in the village of Kalzhan Akhun.
The total cost of the project" construction of a supply gas pipeline and intra - block gas distribution networks in the settlement of Kalzhan Akhun, Syrdarya district, Kyzylorda region "within the framework of the program" auyl - El besigi " is 330,586.0 thousand tenge.For 2023, 297,968.0 thousand tenge was allocated from the Republican budget, 31,228. 3 thousand tenge from the regional budget, gasification work was completed and the settlement was completely gasified. The total cost of the project for the construction of intra - block gas distribution networks and a gas pipeline in the settlement of S. Seifullin, Syrdarya district, is 447,486.4 thousand tenge, 20.0 million tenge was allocated from the regional budget for 2023. The total length of gas pipelines in the project is 25.8 km, 5 units of gas control cabinet points (GRPSH) are provided. The total length of the gas pipeline was 11.0 km through the contractor "nuclear power plant and Limited" LLP and the corresponding works were carried out. The duration of construction is 12 months. Construction work is transitional to 2024. The total cost of the project for the construction of supply and intra – quarter gas distribution networks in the settlement of A. Tokmaganbetov, Syrdarya district-514,800.9 thousand tenge, 20.0 million tenge was allocated from the regional budget for 2023. The total length of gas pipelines in the project is 22.8 km, 4 units of gas control cabinet points (GRPSH) are provided. The total length of the gas pipeline was 6.0 km through the contractor "nuclear power plant and Limited" LLP and the corresponding works were carried out. The duration of construction is 5 months. Construction work in transition to 2024
Completed works on gasification of settlements in the district for the III quarter of 2023
To date, 1,863 individual residential buildings out of 2,503 houses, 257 apartments out of 40 multi-storey residential buildings and 18 social facilities and 17 institutions, 85 business entities have been connected to gas in Terenozek.
According to the results of public procurement for the construction of a supplier gas pipeline and intra-block gas distribution networks in the settlement of Kalzhan Akhun within the framework of the "Auyl-El Besigi " program for 2023, 312,283.4 thousand. the contract was concluded in tenge. (The cost of the project is 330 586.0 thousand tenge). The total length of gas pipelines in the settlement of Kalzhan Akhun is 19.7 km, intra-village-12.8 km. For 6.8 km of a high-pressure gas pipeline with a length of 6.9 km out of 142 pieces of gas pipeline (outlet) for all residential buildings of the settlement, the gas pipeline is carried out by a contracting institution (Remstroy LLP). The total duration of construction is 7 months (November 18, 2023).To date, in order to pass the gas pipeline, work is being carried out by the method of underground horizontal drilling (HDD). - The total cost of the gas supply project for the settlement of S. Seifullina is 447,486.4 thousand tenge, the total cost of the gas supply project for the settlement of A. Tokmaganbetov is 514,800,9 thousand tenge at the beginning of gas supply for the settlement of S. Seifullina for 2023 is 20.0 million tenge.tenge and the beginning of gas supply to the settlement of A. Tokmaganbetov-20.0 million. TENGE dollars have been allocated from the regional budget, as a result of public procurement, the Contracting Institution of "AES and Limited" LLP has been identified, preparations for construction work are underway today.
Completed works on gasification of settlements in the district for the II quarter of 2023
For gas supply: to date, 1810 individual residential houses out of 2503 houses, 263 apartments out of 40 multi-storey residential buildings and 18 social facilities and 17 institutions, 85 business entities have been connected to gas in Terenozek.
According to the results of public procurement of the project "construction of a supplier gas pipeline and intra-block gas distribution networks in the settlement of Kalzhan Akhun of the Syrdarya district of the Kyzylorda region" for a total amount of 330,586.0 thousand tenge, an agreement for 2023 in the amount of 312,283.4 thousand tenge was concluded within the framework of the Auyl el-Besigi program.
At the same time, 90% of this project was allocated from the republican budget for 2023 in the amount of 297,968.0 thousand tenge, of which 16,912.9 thousand tenge was saved, which under the contract amounted to 281,055.1 thousand tenge.
In this regard, at the expense of public procurement, an additional contract was concluded for 10 percent of project funds in the amount of 31,228.3 thousand tenge, in connection with which an application was submitted to the regional Department of Energy and Housing and Communal Services for financing from the regional budget in the amount of 31,228.3 thousand tenge for 2023.
To date, 12.8 km of gas pipelines have been carried out from intra-village gasification works with a total length of 19.7 km of gas pipelines, a total of 132 pieces of gas pipelines (outlets) for residential buildings in the amount of 142 pieces have been placed. To date, the gas pipeline has been carried out on 3.2 km of a high-pressure gas pipeline with a length of 6.9 km. The above-mentioned works are carried out by the contractor Remstroy LLP.
In addition, the total cost of the gas supply project for the settlement of S. Seifullina of the Syrdarya district is 447,486.4 thousand tenge, the total cost of the gas supply project for the settlement of A. Tokmaganbetov is 514,800,9 thousand tenge, at the beginning of gas supply for the settlement of S. Seifullina for 2023 - 20.0 million tenge. tenge and A. At the beginning of gas supply to the settlement of tokmaganbetov-20.0 million tenge were allocated from the regional budget, as a result of public procurement, the Contractor Institution "AES and Limited" LLP was determined. Currently, work is underway on public procurement to determine technical supervision.
For the gasification of social facilities: the total cost of the reconstruction project of the boiler house of the rehabilitation department of the central hospital of the Syrdarya district is $66.7 million.the total cost of the project for the conversion of steam boilers of the kindergarten building "Botagoz" with gas fuel is 29.7 million tenge, as a result of public procurement, Gazstroy Company LLP was determined. Currently, work is underway on public procurement to determine technical supervision.
Completed works on gasification of settlements in the district for the I quarter of 2023
in the village of Terenozek, 1,790 individual residential buildings out of 2,500, 245 apartments of 47 multi-storey residential buildings (477 apartments in total) are connected to gas. To date, 63 houses without gas are socially vulnerable. On September 28, 2022, a plan for gasification of settlements in the Syrdarya district for 2023-2027 was developed and approved.
To date, 297.5 million tenge has been allocated from the Republican budget for the gasification project of the settlement of Kalzhan Akhun, public procurement has been carried out, and the winning institution has been identified.
A project for gasification of the settlement of Chagan has been developed and has been subjected to state expertise. (№ 19-0070/23 dated 17.02.2023)
At the same time,the project of gasification of the settlements N. Ilyasov, Shkhaili, Akzharma, Besaryk is being developed at the expense of sponsorship.
In order to gasify rural settlements in 2023, 298.0 million tenge was allocated from the Republican budget for the gasification project of the settlement of Kalzhan Akhun, and work is underway by the contractor "Remstroy" LLP. Gas supply to the village of S. Seifullin for gasification of other settlements-the cost of the project is 447.4 million tenge, gasification of the settlement of A. Tokmaganbetov-the cost of the project is 514.8 million tenge.tenge, gas supply to the settlement of Chagan-the cost of the project is 2.6 billion rubles. in total, 3.6 billion tenge was allocated for financing from the Republican budget. applications for tenge were submitted to the relevant departments, and these applications were submitted to the Ministry of energy of the Republic of Kazakhstan through the Department.
Completed works on gasification of settlements in the district for the IV quarter of 2022
Within the framework of the program "Gasification: Employment Roadmap", within the framework of the project "Construction of internal gas distribution (white dots) Terenozek networks" funds in the amount of 143.8 million tenge were allocated from the republican budget for 2021-2022. Within the framework of the project (335 points) and 207 units of gas control cabinets, the contractor AES and Limited LLP installed 9,762 km of gas pipelines and performed the corresponding work.
In order to gasify rural settlements, the cost of the gasification project of the village of Kalzhan Akhun is 330.5 million tenge, the cost of the gasification project of the village of S. Seifullin is 447.4 million tenge, the cost of the gasification project of the village of A. Tokmaganbetov is 514.8 million tenge.
The design and estimate documentation for the gasification of the village of Shagan has been developed, which is currently under state examination.
Gasification of 5 social facilities: re-equipment of the heating boiler room of the secondary school building No. 210 S. Terengozek for gas fuel, conversion of the steam boiler room of the kindergarten building "Aigoylek" to gas fuel", conversion of the steam boiler room of the kindergarten building No. 2 "Baldauren" to gas fuel", "Reconstruction of the boiler room building of the district hospital "Syrdarya district hospital" at the address: ul. Toktibayeva, 13, Terengozek village, Syrdarya district, Kyzylorda region, 137.5 million tenge was allocated for the implementation of the works "Gas supply of the boiler building of the polyclinic for 250 beds of the Syrdarya district hospital of the SHZK KMK at the address: Kyzylorda region, Syrdarya district, Muratbayev Street, 110, the specified social facilities were gasified.
Completed works on gasification of settlements in the district for the IIІ quarter of 2022
in the village of Terenozek, 1,492 individual residential buildings out of 2,162 houses, 191 apartments out of 47 multi-storey residential buildings, 13 social facilities, 54 business facilities and 21 institutions are connected to gas. Within the framework of the project " construction of intra-block gas distribution networks (white spots) in the village of Terenozek within the framework of the Employment Roadmap program, 143.8 million tenge was allocated from the republican budget for 2021-2022. Within the framework of the project (334 points) and 207 pieces of gas control cabinets, works on laying 9.762 km of gas pipelines were installed by the contractor organization AES and Limited LLP. To date, gasification works are underway, the completion date will be completed on April 22, 2022. In order to gasify rural settlements, funds have been allocated from the local budget for the development of design estimates in the villages of Kalzhan Akhun, S. Seifullin, A. Tokmaganbetov, Chagan, and a project has been developed. To date, these projects are state expertise
Completed works on gasification of settlements in the district for the II quarter of 2022
in the village of Terenozek, 1,492 individual residential buildings out of 2,162 houses, 191 apartments out of 47 multi-storey residential buildings, 13 social facilities, 54 business facilities and 21 institutions are connected to gas. Within the framework of the project " construction of intra-block gas distribution networks (white spots) in the village of Terenozek within the framework of the Employment Roadmap program, 143.8 million tenge was allocated from the republican budget for 2021-2022. Within the framework of the project (334 points) and 207 pieces of gas control cabinets, works on laying 9.762 km of gas pipelines were installed by the contractor organization AES and Limited LLP. To date, gasification works are underway, the completion date will be completed on April 22, 2022. In order to gasify rural settlements, funds have been allocated from the local budget for the development of design estimates in the villages of Kalzhan Akhun, S. Seifullin, A. Tokmaganbetov, Chagan, and a project has been developed. To date, these projects are state expertise
Completed works on gasification of settlements in the district for the I quarter of 2022
in the village of Terenozek, 1,492 individual residential buildings out of 2,162 houses, 191 apartments out of 47 multi-storey residential buildings, 13 social facilities, 54 business facilities and 21 institutions are connected to gas. Within the framework of the project " construction of intra-block gas distribution networks (white spots) in the village of Terenozek within the framework of the Employment Roadmap program, 143.8 million tenge was allocated from the republican budget for 2021-2022. Within the framework of the project (334 points) and 207 pieces of gas control cabinets, works on laying 9.762 km of gas pipelines were installed by the contractor organization AES and Limited LLP. To date, gasification works are underway, the completion date will be completed on April 22, 2022. In order to gasify rural settlements, funds have been allocated from the local budget for the development of design estimates in the villages of Kalzhan Akhun, S. Seifullin, A. Tokmaganbetov, Chagan, and a project has been developed. To date, these projects are state expertise
Completed works on gasification of settlements in the district for the IV quarter of 2021
In order to gasify boiler houses of social facilities and institutions with natural gas, 69.7 million tenge was allocated and gasified from the district budget for 13 facilities. 1,600 individual residential buildings and 32 multi-storey residential buildings are connected to blue fuel. 40 business facilities and 26 institutions and enterprises are connected to gas. In order to gasify newly built residential buildings (334 points) in the village of Terenozek, a project worth 143.8 million tenge for 2021-2022 is being implemented. In order to gasify rural settlements, 29.7 million tenge was allocated from the budget for the development of design and estimate documentation for the gasification of the villages of Kalzhan Akhun, S. Seifullin, A. Tokmaganbetov, Chagan. Currently, the PSD has been submitted for environmental expertise and a conclusion has been received on the settlement of Kalzhan Akhun. Ecological expertise of the projects of the settlements of S. Seifullin and A. Tokmaganbetov is being conducted.
Completed works on gasification of localities in the district for the II quarter of 2021
143,864.0 thousand tenge was allocated from the republican budget for 2021-2022 for the project "Construction of intra-district gas distribution networks (white spots) of the village of Terenozek to the Syrdarya districts of the Kyzylorda region" within the framework of the "Employment Roadmap". To date, an open tender has been announced to determine a contractor for procurement through the public procurement Department, which is engaged in the organization of procurement. After the results of the competition are determined, gas construction works will be carried out. In addition, 29.7 million tenge was allocated from the local budget for the development of design and estimate documentation for the construction of intra-block gas pipelines and gas pipelines to the settlements of Syrdarya district, A. Tokmaganbetov, S. Seifullin, Kalzhan Akhun, Chagan, currently undergoing state expertise. After receiving an expert opinion on the construction of supply gas pipelines and intra-block gas pipeline networks to the above-mentioned settlements, an application will be submitted to the regional Department of Energy and Housing and Communal Services for financing from the republican budget.
To date, 13 budget and business facilities are used, 1,042 residential buildings out of 2,162, 13 out of 36 multi-storey residential buildings. In order to deliver high-quality and safe gas to the population through the Municipal state Enterprise on the right of economic management "Kyzylorda gas taratu Zhuyesi", 109 emergency crews work 24 hours and instruct on the safe operation of gas to consumers connected to gas, wide propaganda is carried out to prevent unauthorized connection of gas equipment.
Completed works on gasification of localities in the district for the II quarter of 2021
"Construction of gas pipelines and intra-block gas pipelines to settlements: A. Tokmaganbetov, Kalzhan Akhun, S. Seifullin, Chagan of the Syrdarya district" 29,767 thousand tenge has been allocated from the local budget, to date, PSD2 is being developed by the contractor organization. In order to bring the gas pipeline to the newly built residential buildings (334 points, including the zone of new settlement), separated from the gasification project of the village of Terenozek, a project worth 143,864.0 thousand tenge was developed and a budget application was sent to the regional department of energy and Housing and communal services.
To date, 14 social facilities have been adapted for gas and 484 residential buildings use blue fuel. In order to deliver high-quality and safe gas to the population through the establishment of the KGP "Kyzylorda Gas Distribution System", 109 emergency crews work 24 hours and are instructed on the safe operation of gas to consumers connected to gas, wide propaganda is carried out to prevent unauthorized connection of gas equipment.
Completed works on gasification of localities in the district for the I quarter of 2021
"Construction of gas pipelines and intra-block gas pipelines to the settlements: A. Tokmaganbetov, Kalzhan Akhun, S. Seifullin, Chagan of the Syrdarya district" 29,767 thousand tenge was allocated from the local budget, and work is currently underway on public procurement. In order to bring the gas pipeline to the newly built residential buildings (334 points, including the zone of new settlement), separated from the gasification project of the village of Terenozek, a project worth 143,864. 0 thousand tenge was developed and a budget application was sent to the regional Department of Energy and Housing and Communal Services.
To date, 13 facilities have been adapted for gas, of which 8 social facilities and 305 residential buildings use blue fuel. In order to deliver high-quality and safe gas to the population through the establishment of the KGP "Kyzylorda Gas Distribution System", 109 emergency crews work 24 hours and are instructed on the safe operation of gas to consumers connected to gas, wide propaganda is carried out to prevent unauthorized connection of gas equipment.
Completed works on gasification of settlements in the district for the IV quarter of 2020
The construction of intra-block gas pipeline networks in the village of Terenozek was carried out in 2019-2020 through Aliya-Service LLP. Currently, the customer is receiving from the regional Department of Energy and housing and Communal Services.
In the project "construction of gas pipelines and intra-quarter gas pipelines" in the village of Terenozek, 7390,0 thousand tenge was allocated from the district budget, design and estimate documentation was developed and submitted for state expertise through the project enterprise "Azimut"LLP.
Relevant work performed on projects of gas steam boiler air (22 746,0 thousand tenge), and gas steam boiler room of the school of the Lyceum №35 (22 746,0 thousand tenge).
The project of gasification steam boiler rooms of apartment houses on street N. Ergeshbaev allocated 7 991,0 thousand tenge for the project of gasification steam boiler multystoried house No. 95V G. muratbayev str allocated 9 022,0 thousand tenge.
Completed works on gasification of localities in the district for the THIRD quarter of 2020
Construction of gas pipelines and intra-block gas pipelines in the village of Terenozek is planned for 2019-2020.
The total cost of the project is $ 2.4 billion. the project in tenge is financed from the national and regional budgets.
The project client is the Department of energy and housing and communal services of the Kyzylorda region. And the contractor is Aliya Service LLP.
To date, the planned 6 gas control points have been installed, 100% underground gas pipelines have been installed for 96.7 km, and 2162 gas control cabinets have been installed for each residential building.
The project will be put into operation at the end of 2020.
Completed works on gasification of localities in the district for the First quarter of 2020
The total cost of the project is $ 2.4 billion. currently, the construction and installation works are being carried out by the contractor "Aliya-Service" LLP. In 2019, work was carried out to gasify the boiler rooms of 9 objects located in the village of Terenozek, and by 2020 it is planned to gasify the boiler rooms of 11 objects.