Reference for the first quarter of 2025
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for ІI quarter of 2024
On the execution of construction projects in the 2nd quarter, which are planned to be implemented in 2024 by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district
About the objects under construction
In 2024, 13 facilities are being built at the expense of budgetary funds.
Of these: - 3 construction sites are transitional from 2023, 10 new facilities.
Transitional objects:
1. "Construction of internal gas pipelines in the village of Abai, Kazalinsky district"
To date, 14.6 km of gas pipelines have been built (3.3 km of medium pressure, 11.3 km of low pressure), and 90% of construction work has been completed. The contract value of the contractor Remstroy LLP is 343,094 million tenge. The necessary funds amount to 276.577 million tenge. Currently, gas from the Syrdarya River is extracted by horizontal drilling. Currently, work is continuing on laying carpet and installing gas signs (identification marks).
2. "Construction of a village club for 100 people in the village of Kaukey, Kazalinsky district"
The contract value is USD 335.752 million. Tenge. 325.752 million people have been allocated from the regional budget to continue construction in 2023. 265,001 million tenge was allocated and used. The remaining funds in the amount of KZT 70.752 million have been allocated for the current year and an agreement has been signed. The contractor, SCS Engineering LLP, is working behind schedule. To date, the installation of stage equipment and ventilation equipment continues.
3. Construction of a 300-seat school in the village of Zhankozha Batyr, Kazalinsky district, as part of the pilot national project "Comfortable School"
The cost of the project amounted to 3,100.0 (together with the project) 1,072.0 million tenge in 2024. Currently, the brickwork has been completed and the roof has been covered. Roofing works are starting.At the same time, internal plastering works (levkas), work on the heating and sewerage system were carried out. The contractor is Asar LLP.
New facilities:
1. "Construction of the sports complex of the Bekristan dance village of the Kazalinsky district"
The contract value is 398.494 million tenge. 50.0 million tenge has been allocated from the republican budget for 2024. The necessary funds amount to 348.494 million tenge. Construction work has begun, excavation work has been completed, and foundation work is underway. The contractor is Zhylu XXI LLP, the author's supervisor is Project Service LLP, the technical supervision is Aimereke LLP.
2. "Construction of a sports complex from Pobeda Park in the Aiteke dance village of the Kazalinsky district"
The contract value is 628.743 million tenge, 50.0 million tenge has been allocated from the republican budget for 2024. The necessary funds amount to 578.743 million tenge.
Currently, bids are scored for the land plot. Construction work has begun, earthworks have been completed, and preparations are underway to lay the foundation. Contractor – Bolashak LLP, author's supervision – SuKurysProekt LLP, technical supervision – Aktaustoroexpert LLP.
3. "Construction of a sports complex in the village of Kozhabaki, Kazalinsky district"
The contract value is 537.783 million tenge, 50.0 million tenge has been allocated from the republican budget for 2024. The necessary funds amount to 478.149 million tenge.
Currently, bids are scored for the land plot. Construction work has begun and the land is being leveled. Foundation blocks are delivered to the facility. Contractor – Namys-Kurylis LLP, author's supervision – DAB LLP, technical supervision – Aktaustroyexpert LLP.
4. "Construction of a rural club with 100 seats according to a standard project of the village of Maidakol in the Kazalinsky district"
The cost of the contract is 399.133 million tenge, 50.0 million tenge has been allocated from the republican budget for 2024. The necessary funds amount to 349.133 million tenge.
Currently, bids are scored for the land plot. Construction work has begun. Earthworks have been completed and the foundation is being laid. Contractor – Namys-Kurylis LLP, author's supervision – Sartobe LLP, technical supervision – Grand Urban LLP.
5. Execution of works (pumping station and distribution pipeline) under the project of JSC "RZA" "Creation of 184.29 hectares of irrigated land plots (for sowing crops) in the Kazalinsky district of the Kyzylorda region"
The contract value is KZT 211,841 million. On April 19 of this year, a budget application was submitted to the regional department of Natural Resources and Environmental Management, 21 billion 184 million tenge was allocated from the regional budget. Currently, an additional contract has been signed and construction work is continuing.
6. "Landscaping of the territory of the monument to Zhankozhe Nurmukhammeduly in the village of Ayteke bi, Kyzylorda region, Kazalinsky district" The contract value is 160,971 million tenge. 105.0 million tenge has been allocated from the district budget for 2024.
Construction work has now begun. The foundation is being installed. The contractor is Namys–Kurylis LLP, the author's supervision is Meken and K LLP, the technical supervision is Archidesignstroy Engineering LLP.
7. "Construction of internal gas pipelines in the village of Aktan Batyr, Kazalinsky district, Kyzylorda region" The contract value is 353.663 million tenge. 325.929 million tenge has been allocated from the regional budget for 2024. The necessary funds amount to 27.734 million tenge.
Currently, preparations are underway for the start of construction work. Contractor – Orda-Kurylys Construction Company LLP, author's supervision – DOOM-Project LLP, technical supervision – Novat Stroy LLP.
8. "Construction of an administrative building in the village of Ayteke bi, Kazalinsky district, Kyzylorda region"
The contract value is 1,735,509 million tenge. 50 thousand tenge has been allocated from the district budget for 2024. The necessary funds amount to 1,735,459 million tenge. Currently, preparations are underway for the start of construction work. Contractor – Asar LLP, author's supervision – Remporoekt LLP, technical supervision – Prospector-NS LLP.
9. "Purchase of rental housing for socially vulnerable segments of the population (21 housing units)"
In 2024, 266,973 million tenge was allocated from the republican fund for the purchase of 21 residential facilities (the cost of one apartment is 12,713 million tenge), in addition, the regional department of construction, architecture and urban planning department for the purchase of 129 residential units. At the moment, 1,569.0 million tenge has been allocated for 102 apartments. 123 apartments for a total amount of 1,835,984 million tenge.
Currently, construction work has begun on all residential buildings.
10. "Construction of a forest nursery with an area of 33.5 hectares, including an irrigation project on the territory of the Kazalynsky MM for the protection of forests and wildlife of the Kyzylorda region"
Customer: Committee of Forestry and Wildlife of the Ministry of Ecology and Natural Resources of the Republic of Kazakhstan.
The cost of the project is 518,558 million tenge. The contractor is Enbek LLP.
The project provides for the construction of a water pipeline to a sowing field with an area of 27 hectares, the installation of 1 water tank with a volume of 500 m3, fencing of the territory of 35 hectares, drilling a well with a depth of 250 m, a modular kitchen, a recreation room, a warehouse, a bathroom, a refrigerator and a roof (canopy) with special equipment.
Currently, the construction work has been completed and preparations are underway for the reception.
About the public procurement competition
Currently, the department carries out 8 public procurement:
Of these, 2 are construction works, 6 are projects for the development of design and estimate documentation.
About construction works:
1. On April 16 of this year, a state competition was announced for the performance of construction and installation works "to provide engineering infrastructure (road construction) of residential buildings being built in the newly opened quarter of the village of Muratbayev in the Kazalinsky district" by means of a rating-point system competition.
1.0 thousand tenge has been allocated from the district budget for 2024. The announced budget is 218.250 million tenge.
Kazaly-Zholshi LLP was recognized as the winner of the public procurement competition.
2. "Aktan Batyr, Zhankozha Batyr, Bekayan bi Maidakol, U. On June 28 of this year, a state tender was announced for construction and installation work on the project "Construction of a gas pipeline to the settlements of Tuktibayev" through a tender according to the rating system.
(Acceptance of documents will begin on July 5, 2024 and will end on July 22, 2024)
A total of 1,562,453 million tenge has been allocated for 2024. (RB – 200.0 million tenge, OB – 1,362,453). At the June session, 1,235,202 million tenge was allocated from the regional budget. The announced budget is KZT 3,293.147 million.
On the development of design and estimate documentation:
3. The project "Construction of residential buildings in the newly opened quarter of the village of Aiteke bi of the Kazalinsky district of the Kyzylorda region with engineering infrastructure (drinking water, gas and electricity supply)" was transferred to the state in February 29 of this year, a competition for the development of estimated documentation was announced according to the rating-point system.
500 thousand tenge has been allocated from the district budget for 2024. The announced budget is 5,161 million tenge.
(The winner of the public procurement competition is Zhania Kurilia Group LLP)
4. On February 26 of this year, a state competition was announced for the construction of engineering infrastructure (road construction) for residential buildings to be built in the newly opened quarter of the village of Aiteke in the Kazalinsky district of the Kyzylorda region - the development of estimated documentation through a rating-point system competition.
500 thousand tenge has been allocated from the district budget for 2024. The announced budget is 1,587 million tenge.
(The winner of the public procurement competition is PSK Qabylet LLP)
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for І quarter of 2024
In total, 13 facilities are planned to be built in the Kazalinsky district in 2024. For the implementation of these projects in 2024, 225.384 million tenge was allocated from the National Fund, 2970.5 million tenge from the republican budget, 1915.5 million tenge from the regional budget, a total of 5,111.3 million tenge.
Of these:- 3 objects are under construction in transition from 2023, 10 objects are a new project.
To say more, we can say:
Within the framework of the Aul-El Besigi project, 200.0 million tenge was allocated from the republican budget for 4 facilities under the program for the development of social and engineering infrastructure in rural settlements.
1. "Construction of a sports complex from the village of Kozhabaki in the Arandinsky rural district of the Kazalinsky district of the Kyzylorda region."
The project is worth 566.355 million tenge. 50.0 million tenge has been allocated for 2024 (a public procurement competition is taking place, the results are being summed up).
2. "Kyzylorda region Kazalinsky district, Aiteke bi kenty "Zhenis" park construction of a sports complex".
The project cost 649.8 million tenge. 50.0 million tenge was allocated for 2024 (a public procurement competition is being held, the results are being summed up).
3. "Construction of a sports complex from the village of Bekristan bi Kazalinsky district of Kyzylorda region".
The cost of the project is 429.496 million tenge. 50.0 million tenge has been allocated for 2024 (contractor LLC Zhelo-XXI, work has begun).
4. "Construction of a rural club with 100 seats of a typical project from the village of Maidakol in the Kazalinsky district of the Kyzylorda region"
The cost of the project is 419.347 million tenge. 50.0 million tenge has been allocated for 2024 (a public procurement competition is being held, the results are being summarized).
According to the program for the development of the gas transportation system, 225.384 million tenge was allocated from the National Fund, and 127.251 million tenge from the regional budget.
5. "Construction of a gas pipeline to be laid to the settlements of Aktan Batyr, Jankhoja batyr, Bekarystan bi Maidakol, U. Tuktibayeva " of the Kazalinsky district
The project cost 3,863,855 million tenge for 2024, a total of 327.251 million tenge (200.0 million tenge was allocated from the national fund, 127.251 million tenge was allocated from the regional budget). (a public procurement competition is taking place, the deadline for accepting applications is April 16 of this year).
As part of the national entrepreneurship development project for 2021-2025, 116.626 million tenge was allocated from the republican budget for 1 facility under the industrial infrastructure development program.
6. "RZA" AK-nyn Kyzylorda oblysy, Kazaly audanyda 184.29 ha (dakhyldardy ysu usin) suarmaly zher uchaskesin kuru"zhobasy boyynsha sorgy stations men taratu kuby"
Project cost - 224.056 million tenge. For 2024, 116.626 million tenge was allocated from the republican budget (contractor LLC "Zhelo-XXII", works started).
Transitional facilities from 2023
7. "Construction of intra-block gas networks in the settlement of Abai Kazalinsky district"
The cost of the project is 357.735 million tenge. The contract value is 343,093 million tenge. By the beginning of construction in 2023, 5.0 million tenge was allocated from the AB, 36.153 million tenge from the OB, a total of 41.153 million tenge, which were fully utilized. The necessary financing in the amount of 301,941 thousand tenge. For 2024, 25.384 million tenge has been allocated from the national fund. The contractor is Remstroy LLC. (the necessary funds are 276,557 million tenge, to date, 3 km of medium-pressure gas pipeline, 8.9 km of low pressure, only 11.9 km of gas pipeline have been completed, 80% of the works of the facility have been completed)
8. construction of a rural club " for 100 seats from the village of Kaukey " in the Kazalinsky district.
The cost of the contract is 335.752 million tenge. In 2022-2023, 335.752 million tenge was allocated from the regional budget for construction, construction and installation work is underway. Mastered finances-265,001 thousand tenge. The remaining funds are 70,752 million tenge. Contractor "SCS Engineering" LLC.
To date, the construction of the exterior gates of the building has been completed for pouring the foundation of a modular steam boiler, interior finishing works have been carried out, work on the internal heating system, overlapping the roof of the stage, casting the building's facade, pouring the column crossbars of the stairs KR-1, KR-2, gluing tiles. The object is under consideration in court due to the expiration of its completion date.
The rest of the work: Interior finishing, asphalting of external roads, installation of equipment, work on external landscaping, construction of an external toilet.
9. "Kyzylorda region Construction of an administrative building in the village of Ayteke bi Kazalinsky district"
Due to the change in the land plot and the price, the project was adjusted.
The cost of the project is 341.404 million tenge. The financing required to finance the construction is 339.967 million tenge.
5.0 million tenge has been allocated from the regional budget for 2023, 1.4 million tenge has been disbursed. A public procurement competition was held, the contractor of which was LLC SK and Montazh-Stroy. No.84 Contracts were concluded with the contractor institution on October 06, 2023. The duration of construction is 5.5 months.
10. 266.984 million tenge was allocated from the republican budget for the simple purchase of housing for low-income families with many children (21 residents are simple). (land plots have been allocated, stakes have been knocked out, work will begin this week).
In addition, a budget application has been submitted to the regional construction department for the purchase of 101 additional apartments.
A total of 122 apartments, that is, 61 houses, for each of which plots of 600 square meters are ready, are put up for auction.
5 Projects will be implemented by the Customer by the regional Department of Construction, Architecture and Urban Planning.
If we talk more, we can say:
11. Construction of the Ruhaniyat center in the village of Ayteke bi of the Kazalinsky district. The cost of the project is 1822.964 million tenge. 1791.614 million tenge has been allocated from the regional budget for 2024. The contractor is Omirzak LLC (the contract with the contractor was concluded on March 07 of this year for financing 1718,053 tenge). A public procurement competition is being held for the technical supervisory authority, and the results are being summarized.
12. Construction of a 300-seat school from the village of Jankhoja Batyr, Kazalinsky district, as part of the pilot national project "Jile school".
The cost of the project is 3100.0 million tenge per project. Contractor "Asar" LLC. 1658.0 million tenge has been allocated for 2024 (to date, the cornerstone has been filled in, the first floor has been braided and the second floor has been braided).
13. "Construction of a school for 600 places" within the framework of the pilot national project "Juile school" from Aiteke bi rudy Kazalinsky district.
729.0 thousand tenge has been allocated for 2024. On Zhankhodzhi Nurmukhamedovich Street, plot No. 568, 4.5 hectares were transferred.
In addition, public services are provided with the department.
In accordance with the Order of the Minister of National Economy of the Republic of Kazakhstan dated November 30, 2015 No. 750 on approval of the Rules for the organization of construction and passage of licensing procedures in the field of construction 2 provide public services.
Through the electronic licensing portal: 435 applications were received in January-March 2024. Namely:
During the development of projects - "Construction and reconstruction (redevelopment, re-equipment) for the provision of raw materials in January - March 2024, 224 applications for public service were received."
- "Nobai Project Soviet" The Civil Service in January-March 2024 received 211 applications, of which 210 were satisfied, 1 received a reasoned refusal;
In accordance with the order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated March 30, 2020 No.According to the state service for issuing a certificate to determine the address of real estate objects in the territory of the Republic of Kazakhstan in January-March 2023, " 82 applications were submitted through the e–government portal, 87 applications were submitted through HKKO and the State Corporation, a total of 169 applications. No motivated refusals.
According to the order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated April 29, 2021 No. 202 on transfer activities on handles for performing a complex of works on subsequent disposal (demolition of buildings and structures) of objects, currently maintenance is not carried out due to non-compliance with standards.
In addition, according to 29 applications for determining, increasing, and understating the size of a land plot in Aitek-Biysk, Kazalinsky and 19 rural districts, drawings were studied, measured, developed and submitted to the district land commission for consideration with a visit to the beginning of each land plot.
In total, 705 applications for public services were completed on time in January-March 2024. The business processes of providing public services were carried out in accordance with the Rules without violating deadlines, and no complaints were received about the quality of public services.
In accordance with the requirements of current legislation, the acts of acceptance of all facilities into operation are subject to accounting in part
Housing
With the results of the 12 months of 2023, 287 residential buildings with a total volume of 54,647.0 square meters were put into operation.
With the results of 3 months this year, there were 11,994.0 square meters
62 residential buildings have been put into operation. It is performed by 103.0% more than in the corresponding period of 2023.
It is planned that 289 residential buildings with a total volume of 55,00.0 square meters will be commissioned by the end of the year.
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for ІV quarter of 2023
In total, the construction of 12 facilities in kazalinsky district is planned for 2023. For the implementation of these projects,6.6 billion rubles were allocated from the Republican, regional and district budgets for 2023. the tenge was allocated.
Of these: - 7 new projects, with the construction of 5 objects in transition from 2022.
- The District Department of construction, architecture and urban planning is implementing 7 projects, of which 3 objects will be completed in 2022, and 4 objects will be newly launched.
- The Regional Department of construction, architecture and urban planning is implementing 5 projects, of which 2 are transitional from 2022, and 3 are newly launched construction projects. Let's talk in more detail:
Transitional objects from 2022:-
The customer implemented the construction of 3 projects in the District Department of construction, architecture and urban planning.
1.form" equipping residential buildings with low-pressure gas networks and 0.4 KV power lines that are stuck in the infrastructure construction project on a plot of 210 hectares in the village of Aiteke bi".
the contract cost 168.941 million tenge. 168.941 million in 2022-2023. the tenge was allocated and fully disbursed. Contractor "Remstroy" LLP. The facility was put into operation on July 27, 2023.
(According to the project, 137 residential buildings (2,552 km) are provided with 0.4 KV power lines, about 460 residential buildings are provided with low-pressure gas lines. The total length of Gas Networks is 9.7 km, GRPSH-1 PC.).
2.construction of a" rural club for 100 seats in the village of Kuukey, Kazalinsky district".
the contract cost 335.752 million. tenge. In 2022-2023, 335.752 million from the regional budget for construction. tenge has been allocated, construction and installation works are underway. Disbursed funds-265,001 thousand tenge. The remaining funds are 70.752 million. tenge. Contractor" SCS Engineering " LLP.
The contractor is late in fulfilling the approved work schedule. In this regard, a lawsuit is being filed against the contractor for the payment of a permanent fine and recognition as unscrupulous, and the Specialized Interdistrict Economic Court of Kyzylorda region is considering a lawsuit.
To date, the foundation of the modular steam boiler has been completed, the construction of the outer gate of the building has been completed, internal finishing works are being carried out, the internal heating system is being carried out, the stage roof is being covered, the building is being poured, the column crossbars of the stairs kr-1, kr-2 are being poured, the tile is being glued.
Other works: interior finishing works, asphalting of external roads, installation of equipment, external improvement works, construction of an external toilet.
the contract cost млн 157.620 million. tenge. 149.860 million in 2021-2022. 7.76 million tenge will be allocated and disbursed by 2023.tenge is considered. Contractor "RB Stroy" LLP.
A court decision was made to oblige the contractor to complete the construction.
Newly launched facilities in 2023:
The construction of 3 projects was carried out through the customer's District Department of construction, architecture and urban planning.
4.construction" provision of engineering infrastructure (supply of drinking water, gas and electricity) for residential buildings to be built in a new quarter of the village of G. Muratbayev, Kazalinsky district"
the contract cost 471.539 million. tenge. 420.116 million from RB for 2023. KZT 51.423 million from the central bank. tenge was allocated and the amount of the contract was fully disbursed. Contractor "Universal Stroy Service" LLP.
The facility was commissioned on December 27, 2023.
Drinking water network-15.3 km, gas network-7.0 km, GRPSH-1 PC, electric network-8.7 km, transformer installation-3 pcs. 270 land plots will be covered by engineering networks.
the contract cost 104.167 million tenge. 98.910 million from RB for 2023. KZT 11.286 million from the central bank. tenge was allocated and the cost of the contract was fully disbursed. Contractor "update" LLP.
The facility was put into operation on July 27, 2023.
The project provides for the maintenance of service water networks for 230 houses.
6.construction" maintenance of intra-block gas networks in the Abay settlement of Kazalinsky district".
The project cost млн 357.735 million.tenge. The contract cost 343.093 million tenge. 5.0 million from AB to start construction. KZT 36.153 million from the central bank. tenge, total 41.153 million. the tenge was allocated and fully disbursed. The required amount is 301,941 thousand tenge. Contractor "Remstroy" LLP.
The facility is transitioning to 2024.
To date, 3 km of medium-pressure and 8.8 km of low-pressure gas pipelines have been laid.
Covered facilities: population-1269 people, 193-housing, 8-social facilities. The total length of gas pipelines is 15,090 km, GRPSH – 2 PCs.
The cost of the project is 193481.0 thousand tenge. The amount required to finance the construction is 178825.0 thousand tenge.5.0 million from the regional budget for 2023.TG was divided. A public procurement competition was held, the contractor of which was identified as "SK and "Montazh-Stroy" LLP. Contract No. 84 was signed with the contractor on October 06, 2023. The duration of construction is 5.5 months. The facility is transitioning to 2024. 8.in addition, a total of 577.2 million tenge (52 residential premises) was allocated from the National Fund and the district budget for the purchase of rental housing for socially vulnerable segments of the population. The allocated funds purchased 52 apartments for socially vulnerable segments of the population. 5 projects were implemented by the customer of the Regional Department of construction, architecture and urban planning, of which 2 objects will be completed in 2022, and 3 objects will be newly launched.
Let's talk in more detail:
the project cost 1009.5 million.tenge. The contract amount is 847.282 million.tenge. For construction within the framework of the" employment roadmap " program for 2021, RB received млн 471.779 million. the tenge was allocated. 411.974 million for 2022. the tenge was allocated. 44.187 million for 2023. tenge is considered. Contractor "SSS Engineering" LLP. The construction was commissioned in December 2023.
the project cost млн 948.245 million. tenge. The contract cost 826.196 million. tenge. Contractor "Kazkurylys Service" LLP. Construction of the facility began in 2018. 784.896 million for construction in 2018-2021. if the tenge is allocated and disbursed, the central bank will receive 41.3 million tenge by 2023.tenge is considered.
The rest of the work: installation of DES and installation of stage equipment.
10.in the field of healthcare, 3 projects were implemented through the Regional Department of construction, architecture and urban planning.
1.construction of an outpatient clinic in Bozkol village with a cost of млн 377.951 million.TG; general contractor "Bolashak" LLP. the facility was put into operation on December 8, 2023.
2.construction of an outpatient clinic in the village of Kaukei with a cost of млн 383.136 million.TG; general contractor Aman kurylys LLP. the facility was put into operation on December 13, 2023.
3.construction of an outpatient clinic in Abay village with a cost of млн 389.615 million.TG. The general contractor is Aman kurylys LLP. the facility was put into operation on December 13, 2023.
In addition, the department provides 6 types of public services.
In accordance with the order of the minister of national economy of the Republic of Kazakhstan dated November 30, 2015 No. 750 on approval of the rules for organizing construction and passing licensing procedures in the field of construction, 2 public services are provided.
Through the electronic licensing portal: in 2023, 1645 applications were received. In particular:
- In 2023, 844 applications were satisfied for the state service" provision of primary materials in the development of construction and reconstruction (redevelopment, re-equipment) projects".
- In 2023, 801 applications were received and satisfied for the state service" coordination of draft projects".
In accordance with the order of the minister of Industry and infrastructure development of the Republic of Kazakhstan dated March 30, 2020 No. 168 "on the state service for issuing certificates for determining the address of real estate objects in the territory of the Republic of Kazakhstan in 2023, 82 applications were received through the e – government portal, 78 applications through the state corporation "PSC yis", a total of 160 applications were received. There are no reasoned refusals.
According to the order of the minister of Industry and infrastructure development of the Republic of Kazakhstan dated April 29, 2021 No. 202, the provision of services for the provision of a set of works on the subsequent disposal of objects (demolition of buildings and structures) is currently not carried out due to the non-compliance of service work with the standard.
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for ІІІ quarter of 2023
Architectural and urban planning supervision is understood as measures aimed at regulating the processes of transfer and use of land plots, construction and reconstruction. The main task of architectural and urban planning supervision is to ensure compliance with the rules and requirements established by legislation and regulations in the field of architecture and urban planning, as well as to preserve the architectural appearance and character of the territory.
The Department of Construction, Architecture and Urban Planning of the Kazaly District conducts monitoring in accordance with paragraph 14 of Article 26 of the Law of the Republic of Kazakhstan dated July 16, 2001 "On Architecture, Urban Planning and Construction Activities".
For the current year, 11.0 billion tenge was allocated from the republican, regional and district budgets for the construction of 61 facilities.
Including:
1 project through the Committee on Water Resources (Baikozhinsky main water pipeline, funds 678.295 million tenge);
6 projects are being implemented by the Regional Department of Construction, Architecture and Urban Planning. (2 facilities are transitional from 2022, the construction of 4 facilities is being built again, the funds are 2308.2 million tenge).
1 facility is being implemented through the regional health department (funds 150.8 million tenge), 1 facility through the Department of Education (funds 208.305 million tenge).
2 facilities are being implemented by order of the regional Department of Passenger Transport and Highways. (3615.7 million tenge).
6 projects are being implemented by the district department of construction, architecture and urban planning (3 facilities are transitional since 2022, 3 facilities were launched this year, 1281.4 million tenge of funds) and 16 facilities are being implemented by order of the Department of Housing and Communal Services, Passenger Transport and Highways (with a total cost of 2894.8 million tenge).
In addition, 28 facilities are under construction by the akimats of the village of Aiteke bi, the city of Kazalinsk and rural districts, including landscaping, construction of sidewalks, major repairs, repair of sports grounds.
Facilities that are built at the expense of the budget are under the constant control of the customer, a technical observer.
In addition, according to the protocol order of the deputy akim of the region S. Kozhaniyazov, construction sites are controlled by the regional control department. In July-September, the department's specialists visited the construction sites of the district 3 times and issued certificates for each facility.
In order to control the construction at the expense of private funds, it was noted that 70 business facilities are being built and installed in the village of Aiteke bi and the city of Kazalinsk, of which 19 objects are land plots for entrepreneurial activities, 51 for individual housing construction.
To date, permits have been issued for 10 facilities and construction is being carried out in accordance with the requirements of the law.
Since the beginning of the year, 24 construction facilities (social and entrepreneurial facilities) have been commissioned, 22 construction facilities have been adapted for entrepreneurial activities.
For 8 months of 2023, 1.370 billion tenge was invested in the district for construction at the expense of private funds. investments (for 8 months of 2022 amounted to 1.340 billion tenge).
In accordance with Article 33 of the Law, the Regional Control Department (hereinafter referred to as the Department) has the right to check the compliance of construction objects, used building materials, products with the requirements of state standards.
The results of monitoring are regularly sent to the department: in 2022, 15 facilities were sent, of which 3 facilities were fined, the remaining 12 facilities were submitted. In 2023, 10 business facilities and 19 gas stations were opened.
Private housing construction facilities are not subject to inspection in accordance with the Law on Architecture and Construction, and business facilities are subject to explanatory work on the legalization of documents, and notification letters have been issued for 51 objects.
In accordance with Article 710 of the Code of Administrative Offences, violations of the legislation on land use in accordance with its intended purpose are considered by the Department of Land Management of the Kyzylorda region. Since the beginning of the year, the Department of Agriculture and Land Relations of the district has sent 34 persons to the land inspectorate for this violation, 14 of them instructed to draw up their documents in accordance with the law. Information is collected and studied.
In order to identify persons who violated the architectural appearance and principles of improvement of the settlement, 46 persons who violated the rules of improvement were identified.
In accordance with Article 505 of the Code of Administrative Offences, administrative measures were taken by the akimat of the village of Aiteke bi 16 (7 fines – 241,500 tenge; 9 warnings), 30 people from the city of Kazalinsk (8 fines – 272,000 tenge; 22 warnings).
In 2018-2021, on the basis of the master plan, 831 hectares (6 zones) of infrastructure were provided between the village of Aiteke bi and the city of Kazalinsk, 1800 plots were transferred for the construction of individual housing.
In the course of the inventory with the Department of Agriculture and Land Relations of the Kazalinsky District, 48 land plots were returned due to the lack of development by the owners in accordance with the established procedure, currently work is underway on the transfer of returned land plots (by the end of the year, the transfer of 19 plots is possible).
In order to transfer land plots to the next citizens, a project was developed to provide engineering infrastructure networks of 600 hectares of the southwestern outskirts of the village of Aiteke bi (water supply, electricity supply, road construction) worth 8.9 billion tenge (water supply 2.7 billion tenge, electricity supply 1.3 billion tenge, road construction 4.8 billion tenge).
The project provides for 237.3 km of drinking water, 119.8 km of power lines, 86.5 km of cattle and stone roads (HPPs).
If this territory is covered by infrastructure, then land plots will appear here for the construction of 3,770 individual houses, a school, a kindergarten, a sports ground, and a park.
To finance the project, budget applications were submitted to the Committee for Construction, Housing and Utilities of the Ministry of Industry and Infrastructure Development.
In addition, in order to open new quarters for housing construction, 10.0 million tenge was allocated from the district budget for the development of a detailed planning project for 140 hectares from the territory of the 5th quarter of the village of Aiteke bi. Public procurement procedures are currently underway (opening on 26.09.2023, 1 person excluded).
In addition, for the design development of a detailed planning project for 76 hectares on the territory of the 2nd quarter of the village of Aiteke bi, budget applications were submitted for financing from the regional budget in the amount of 21.0 million tenge.
As you know, from 2008 to 2010, master plans and development schemes for 24 settlements of the district were developed and approved. At present, due to the approach to the calculation period of rural development schemes, there is a need to make adjustments to the schemes.
In this regard, in accordance with the "Roadmap for the development (adjustment) of master plans, schemes for the development and construction of settlements in the Kyzylorda region until 2025", budget applications were submitted for financing the project from the regional budget in the amount of 35.8 million tenge to amend the master plans of the villages of Tasaryk (6.1 million tenge), Kaukei (10.5 million tenge), Urkendeu (5.2 million tenge), G. Muratbayev (7.1 million tenge), K. Primov (6.9 million tenge).
Since September of this year, specialists of the Kyzylorda branch of the RSE "Republican State Center for Urban Planning and Cadastre" have begun an inventory of underground and surface engineering networks in built-up areas of 1381 hectares of the village of Aiteke bi, 252 hectares of Kazalinsk.
For this work, 82.1 million tenge was allocated from the regional budget. Tg. (55.4 million tenge Aiteke bi, 26.7 million tenge Kazalinsk).
To date, aerial photography has been carried out by specialists of the Public Administration enterprise. Now an inventory of engineering networks on the territory of the settlement will be carried out. Completion of the work is scheduled for December 15, 2023.
According to the results of 12 months of 2022, 280 residential buildings with a total area of 54,072.0 square meters were commissioned.
According to the results of 8 months of this year, 136 residential buildings with a total area of 27,314 square meters were commissioned, which is 120.0% more than in the corresponding period of 2022. (investment reports on housing construction have been submitted for 3.2 billion tenge).
By the end of the year, 306 residential buildings with a total area of 58,674.0 square meters were commissioned, 6.9 billion tenge was commissioned. It is planned to submit investment reports (5.5 billion tenge in 2022).
In total, since the beginning of the year, 4 public services will be provided in the department, 1154 applications have been received through the electronic licensing portal:
Purchase of primary materials for the development of construction projects – 565 applications, of which 557 were satisfied, 8 were rejected for valid reasons;
589 applications were submitted for approval of the conceptual design, of which 559 were satisfied, 30 were rejected;
156 applications were received through the PSC, 207 applications through the e-government portal, a total of 363 applications.
In addition, 215 applications for the determination, increase, reduction of the size of land plots in the village of Aiteke bi, the city of Kazalinsk and 19 rural districts, 60 applications for changing the purpose were studied, measured, drawn up and submitted to the district land commission.
In accordance with Article 48 of the Land Code of the Republic of Kazakhstan (acquisition of rights to state land plots at auctions), 105 land plots with a total area of 70.0 thousand square meters have been prepared and submitted to the Department of Land Relations since the beginning of the year for the transfer of land plots for entrepreneurial purposes through auctions. 48 land plots were sold through the auction, 24.3 million tenge was transferred to the local budget.
In general, since the beginning of the year, 1517 applications of the population for public services have been fulfilled during this period.
Supervisory work on the architectural and urban development of the district will be continued together with the competent authorities.
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for ІІ quarter of 2023
2 facilities planned for 2023 will be transitional by 2022, and 4 facilities will be new this year. For the implementation of projects for 2023, 721.687 million tenge has been allocated from the republican and regional budgets. Exactly:
1. for 2023, from the regional budget -$9.0 million for the continuation of construction works of the object "equipping residential buildings stuck in the infrastructure construction project on a land plot of 210 hectares in the village of Aiteke bi of the Kazalinsky district with low-pressure gas networks and a 0.4 kV power grid". tenge has been allocated, construction and installation works have been completed, and preparations are underway to put the facility into operation. The general contractor is Remstroy LLP. The project provides for the provision of electricity to 137 residential buildings, low-pressure gas networks to about 450 residential buildings. The total length of gas networks is 9.7 km, GRPSH-1 pc. The construction of the facility is scheduled to be completed and commissioned in July.
2. for the continuation of the construction of the facility"construction of a rural club for 100 seats in the village of Kakukey, Kazalinsky district", $ 325,752 million was allocated from the regional budget. tenge was allocated, construction and installation works are underway. The general contractor is SSENgineering LLP. The village club building consists of 1 floor. The building area is 32m x 19M. the total area of the building is 586.35 m2. There are: an auditorium, a hall, a bathroom, a vestibule, artistic rooms, a stage entrance room, a library, a vent chamber, a heating point, a stage, a pantry, a dressing room, a security room, a director's room and 2 specialist rooms. On the territory of the village club there is a septic tank, a KTPN, a modular heat boiler, garbage containers, Parking. Provision of the building with tables, cabinets, computers, televisions, sofas and other furniture is provided. To date, the foundation of the facility is completely flooded, work is underway on laying bricks on the walls of the building, covering the roof.
3.259.060 million tenge was allocated from the republican budget for the construction of "provision of engineering infrastructure (drinking, gas and electricity supply) of residential buildings under construction in the newly opened quarter from the village of Muratbayev, Kazalinsky district", 51.423 million tenge was allocated from the regional budget, construction and installation works are underway. Contractor institution "Universal Stroy Service" LLP. A drinking water network-15.3 km, a gas network-7.0 km, a GRPSH-1 piece, an electric grid-8.7 km, a transformer installation-3 pieces will be installed at the facility. Engineering networks will cover 270 land plots
4.98.910 million tenge was allocated from the republican budget for the construction of "carrying out service networks of drinking water to residential buildings on a land plot of 180 hectares in the village of Ayteke bi of the Kazalinsky district", 11.286 million tenge was allocated from the regional budget, construction and installation works are underway. The contracting organization of "zhangyru" LLP. The construction of the facility is scheduled to be completed and commissioned at the end of July.
5. "implementation of intra-block gas networks in the settlement of Abai Kazalinsky district". The project cost is 357.735 million tenge. 5.0 million tenge has been allocated from the district budget for the start of construction, 36,153 regional funds have been allocated, construction and installation works are underway. Contractor institution "Remstroy" LLP.
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for І quarter of 2023
2 facilities planned for 2023 will be transitional by 2022, and 4 facilities will be new this year. For the implementation of projects for 2023, 721.687 million tenge has been allocated from the republican and regional budgets. Exactly:
1. For 2023, from the regional budget -9.0 million tenge. for the continuation of construction works of the object"equipping residential buildings stuck in the infrastructure construction project on a land plot of 210 hectares in the village of Aiteke bi of the Kazalinsky district with low-pressure gas networks and a 0.4 kV power grid". tenge has been allocated, construction and installation works are underway. The general contractor is Remstroy LLP. The project provides for the provision of electricity to 137 residential buildings, low-pressure gas networks to about 450 residential buildings. The total length of gas networks is 9.7 km, GRPSH-1 pc. The construction of the facility is scheduled to be completed and commissioned at the end of April.
2. For the continuation of the construction of the object "construction of a rural club for 100 seats in the village of Kaukey of the Kazalinsky district", 325,752 million tenge was allocated from the regional budget, tenge was allocated, construction and installation work is underway. The general contractor is SSENgineering LLP. The village club building consists of 1 floor. The building area is 32m x 19M. the total area of the building is 586.35 m2. There are: an auditorium, a hall, a bathroom, a vestibule, artistic rooms, a stage entrance room, a library, a vent chamber, a heating point, a stage, a pantry, a dressing room, a security room, a director's room and 2 specialist rooms. On the territory of the village club there is a septic tank, a KTPN, a modular heat boiler, garbage containers, Parking. It is planned to provide the building with tables, cabinets, computers, televisions, sofas and other furniture. To date, the foundation of the facility is completely filled in, work is underway on laying bricks on the walls of the building.
3. Within the framework of the Nurly Zher program, 200.0 million tenge was allocated from the republican budget for the construction of "provision of engineering infrastructure (drinking, gas and electricity supply) of residential buildings under construction in the newly opened quarter of S. G. Muratbayev of the Kazalinsky district", 51.423 million tenge from the regional budget according to the results of the public procurement tender, the Contracting institution LLP "Universal Stroy Service" was determined as the winner.
4.98.910 million tenge was allocated from the republican budget for the construction of "carrying out service networks of drinking water to residential buildings on a land plot of 180 hectares in the village of Ayteke bi of the Kazalinsky district" within the framework of the Nurly Zher program, 11.286 million tenge was allocated from the regional budget, according to the results of the public procurement competition, the Contractor "Zhangyru" LLP was determined the winner. Construction work began on March 30.
5. 25.315 million tenge has been allocated from the regional budget for the construction of "electricity supply of new residential areas of the village of U. Tuktibayev of the Kazalinsky district" within the framework of the Nurly Zher program. Due to the redirection of allocated funds from the regional budget by sequestration to another project, the public procurement competition has been suspended to date.
6. "Implementation of intra-block gas networks in the settlement of Abai Kazalinsky district". The project cost is 357.735 million tenge. 5.0 million tenge was allocated from the district budget for the start of construction. According to the results of the public procurement tender, the Contractor institution Remstroy LLP was determined the winner.
In addition, the department provides 4 types of public services.
In accordance with the Order of the Minister of National Economy of the Republic of Kazakhstan dated November 30, 2015 No. 750 "on approval of the Rules for the organization of development and passage of licensing procedures in the field of construction", provides 2 public services.
Through the electronic licensing portal: 239 applications were received in January-March 2023. Exactly:
-126 applications were received for the state service "provision of raw materials for the development of construction and reconstruction projects (redevelopment, re-equipment) " in January-March 2023. Of these, 124 applications were satisfied, and a reasoned refusal was submitted for 2 applications.
- 123 applications were received for the state service "approval of the draft project" in January-March 2023, 115 of them were satisfied, 8 motivated refusals;
In accordance with the order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated March 30, 2020 No. 168 on the state service "issuance of a certificate for determining the address of real estate objects in the territory of the Republic of Kazakhstan" for January-March 2023, 82 appeals were received through the e–government portal, 78 appeals were received through the State Corporation's "AIS PSC", in total 160 requests were received. There are no motivated refusals.
In accordance with the order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated April 29, 2021 No. 202, for the transfer service for the complex of works on the subsequent disposal of facilities (demolition of buildings and structures), services are currently not provided due to non-compliance with the standards.
In general, 2,238 appeals were executed for public services in 2022, and 409 appeals were executed in January-March 2023 within the established deadlines. Business processes of rendering public services were conducted in accordance with the rules without violating deadlines, there were no complaints about the quality of public services.
In accordance with the requirements of the current legislation, the acceptance certificates of all objects in operation are subject to accounting in the department.
According to the results of the 12 months of 2022, 285 residential buildings with a total area of 54072.0 sq. m were put into operation.
According to the results of 3 months of this year, 62 residential buildings with an area of 11658.0 sq. m. were put into operation. Compared to the corresponding period of 2022, 102.0% more were executed.
By the end of the year, it is planned to put into operation 287 residential buildings with a total area of 54520.0 sq. m.
Certificate of the work done by the Department of Construction, Architecture and Urban Planning of the Kazalinsky district for 2022
Construction of 17 facilities was carried out in the Kazalinsky district in 2022. Of these, 7 projects are transitioning from 2021, 10 objects are newly started in 2022. 2 451.013 million tenge has been allocated for the implementation of projects for 2022.
Namely:
Gasification of settlements
1. "Construction of gas supply to the city of Kazaly, Kazalinsky district".
The project cost is 1026.9 million tenge. The amount of the contract amounted to 883.241 million tenge. For 2020, 203.679 million tenge, for 2021 683.242 million tenge, (NC-547.982 million tenge, OB-135.260 million tenge), 19.391 million tenge were allocated for 2022 and the facility was commissioned in April 2022. The general contractor is MBK Kurylys LLP.
2. "Construction of intra-block gas networks in the settlement of Basykara, Kazalinsky district".
The project cost is 283,196 million tenge. The amount of the contract is 244.218 million tenge. For 2022, 256.034 million tenge was allocated (NF-140.0 million tenge, RB-91.612 million tenge, OB - 24.422 million tenge). The facility was commissioned in December 2022. Contractor of Remstroy LLP.
3. "Construction of intra-block gas networks in the settlement of K. Pyrimov of the Kazalinsky district"
The project cost is 172,759 million tenge. The amount of the contract is 157.555 million tenge. For 2022, 149.423 million tenge (NF-130.0 million tenge, RB-19.423 million tenge, OB-15.756 million tenge). The facility was commissioned in December 2022. Contractor of Remstroy LLP.
4. "Construction of intra-block gas networks in the settlement of Zhalantos batyr of the Kazalinsky district".
The project cost is 469.245 million tenge. The amount of the contract is 436,860 million tenge. For 2022, 414.311 million tenge (NF-300.0 million tenge, RB-114.311 million tenge, OB-43.696 million tenge). The facility was commissioned in December 2022. Contractor of Remstroy LLP.
Sports facilities
5. The object "Construction of a sports complex in the village of K. Primov of the Kumzhiyek aul district of the Kazalinsky district" started in 2021.
The project cost is 352.457 million tenge. The amount of the contract amounted to 313.184 million tenge. In 2021, the National Fund received 194,200 million dollars. In 2022, 124,585 million tenge was disbursed.tenge (NF-70,0 million tenge, RB-22,666 million tenge, Central Bank-31,919 million tengetg) allocated and fully mastered. Contractor "RAGS+GS" LLP. The facility was commissioned on July 28, 2022.
6. "Construction of a sports complex of the Angara type in the village of U. Tuktibayev, Alginsky rural district of Kazalinsky district".
In 2022, according to the program "Auyl el besigi", 242.574 million tenge was allocated from the republican budget, 25.577 million tenge from the regional budget. The project cost is 281, 293 million tenge. The cost of the contract is 255.776 million tenge. Contractor of SMP-Kyzylorda LLP. The facility was commissioned in December 2022.
7. "Construction of a sports ground in the Dostyk microdistrict of Kenta Aiteke bi Kazalinsky district". The project cost is 26.775 million tenge. The amount of the contract amounted to 23.975 million tenge. For 2021, 13.976 million tenge was allocated from the district budget. For 2022, 9.9 million tenge was allocated and disbursed from the district budget. The facility was commissioned in April 2022.
8. "Construction of a mini-football field on U. Tuktibayev Street in the city of Kazaly, Kazalinsky district".
The project cost is 30.213 million tenge. The amount of the contract amounted to 28.671 million tenge. 28.671 million tenge has been allocated from the district budget for construction, the amount of the contract has been fully disbursed. The facility was commissioned in June 2022.
Sports grounds built by rural districts.
9. Installation of a sports playground in the settlement of Shaken.
The project cost is 8.6 million tenge. The amount of the contract is 7.2 million tenge. 7.2 million tenge has been allocated from the district budget for construction, the amount of the contract has been fully mastered. Contractor of Engineer Stroy Group LLP. The facility was commissioned in June 2022.
10. Installation of a sports playground in the settlement of Baykozha.
The project cost is 8.6 million tenge. The amount of the contract is 5.3 million tenge. 5.3 million tenge has been allocated from the district budget for construction, the amount of the contract has been fully mastered.The contractor is Namys Kurylys LLP. The facility was commissioned in May 2022.
Cultural objects.
11."Construction of a village club for 100 seats in the village of Kaukey Kazalinsky district.
10.0 million tenge was allocated and disbursed from the regional budget for the start of construction. The project cost is 372.184 million tenge. The cost of the contract is 335,753 million tenge. The general contractor is SS Engineering LLP. The object is transitioning to 2023.
For reference: to date, the foundation of the facility has been laid, work has been done on laying wall bricks
Networks of engineering and communication infrastructure.
12. Provision of infrastructure for new quarters of the Aimash microdistrict of the Aiteke bi settlement of the Kazalinsky district (road construction).
The project cost is 179.487 million tenge. The amount of the contract is 157,602 thousand tenge. 161.537 million tenge was allocated for construction in 2021 (NC - 161.537 million tenge, OB-15.762 million tenge). Contractor of RB Stroy LLP. For 2022, 52.603 million tenge has been allocated and 44.8 million tenge has been disbursed. The object is transitioning to 2023.
For reference: the construction of a gravel road with a total length of 5.4 km (19 streets) is planned for the object. To date, sandy, clay soil has been laid on 19 streets, and work on laying GPS has been carried out on 10 streets.
13. "Provision of low-pressure gas networks and an electric network of 0.4 kV for residential buildings not included in the project "Construction of infrastructure on a land plot of 210 hectares in Kent Aitek bi Kazalinsky district".
The project cost is 179.691 million tenge. 156.780 million tenge has been allocated from the republican budget for construction under the Nurly Zher program for 2022, 16.894 million tenge from the regional budget, construction and installation works are underway. The object is transitioning to 2023. The general contractor is Remstroy LLP.
For reference: to date, the construction of 0.4 kV overhead line networks has been fully carried out and launched. Low-pressure gas networks are being conducted, service pipelines for residential buildings are being produced.
Objects carried out by the customer by the Regional Department of Construction, Architecture and Urban Planning:
14. "Construction of a school building for 250 places in the village of Ayteke bi of Kazalinsky district of Kyzylorda region".
The cost of the project is 1009.5 million tenge. The contract amount amounted to 847.282 million tenge. 471.779 million tenge has been allocated to finance construction from the republican budget within the framework of the "Employment Roadmap" for 2021. For 2022, 411.974 million tenge, construction and installation works are underway. The general contractor is SS Engineering LLP. The object is transitioning to 2023.
15. "Construction of a 600-seat house of culture in the village of Aiteke bi of the Kazalinsky district".
The project cost is 948,245 million tenge. The amount of the contract amounted to 826.196 million tenge. The contractor is Kazstroy Service LLP. Construction of the facility began in 2018. 784.896 million tenge was allocated for construction in 2019-2021 and fully mastered, 41.3 million tenge was allocated for 2022. Other works: installation of DES and installation of stage equipment.
16. "Construction of a kindergarten for 140 places in Kazaly, Kazalinsky district".
The cost of the project is 712,042 thousand tenge. The general contractor of "SMP Kyzylorda" LLP. The amount of the contract amounted to 680.713 million tenge. For 2022, 680.713 million tenge has been allocated from the regional budget and fully utilized. The facility was commissioned on November 22, 2022.
17. "Construction of a polyclinic for 250 visits per shift in the village of Ayteke bi Kazalinsky district".
The project cost is 2774.1 million tenge. The amount of the contract is 2450.1 million tenge. The general contractor is SCS Engineering LLP. Construction of the facility began in 2020. 2326.6 million tenge has been allocated for construction in 2020-2021, and the amount of the contract has been fully mastered. Construction and installation works of the facility were completed and put into operation on April 08, 2022.
In addition, section 4 provides for public services. Since the beginning of the year, taking into account the acceptance certificates of 285 residential buildings and 35 construction projects, State Services have provided 857 draft projects, 921 architectural and planning tasks and 691 address certificates.
Information on the completion of construction works for ІIІ quarter of 2022 by the Department of Construction, аrchitecture and Urban Planning of the Kazalinsky district
17 facilities are under construction in the Kazalinsky district in 2022. Of these, 7 projects are transitioning from 2021, 10 objects are newly started in 2022.
2 324.678 million tenge has been allocated for the implementation of projects for 2022.
Exactly:
According to the state program of regional development for 2020-2025.
1. Construction of gas supply in Kazaly, Kazalinsky district.
The project cost is 1026.9 million tenge. The amount of the contract amounted to 883.241 million tenge. 203.679 million tenge was allocated for 2020, 683.242 million tenge for 2021, (NF-547.982 million tenge, OB - 135.260 million tenge), 19.391 million tenge was allocated for 2022. The allocated amount of the contract is fully mastered.
The general contractor is MBK Kurylys LLP. The facility was commissioned in April 2022.
Within the framework of the program "Auyl-el besigi"
2."Construction of intra-block gas networks to the settlement of Basykara, Kazalinsky district, Kyzylorda region"
The project cost is 283.196 million tenge. The amount of the contract is 244.218 million tenge. For 2022, 231.612 million tenge was allocated (at the expense of the National Fund 140.0 million tenge, 91.612 million tenge was allocated from the republican budget), of which 145.0 million tenge was disbursed. The remaining amount is 86.6 million tenge. The general contractor of Remstroy LLP, the necessary co-financing amounted to 24.422 million tenge. The facility is scheduled to be commissioned by October 2022.
3."Construction of intra-block gas networks to the locality of K. Primova of Kazalinsky district of Kyzylorda region"
The project cost is 172,759 million tenge. The amount of the contract is 157.555 million tenge. 149.423 million tenge has been allocated for 2022 (at the expense of the National Fund 130.0 million tenge, 19.423 million tenge has been allocated from the republican budget), 125.0 million tenge of which has been disbursed. The remaining amount is 24.4 million tenge. The general contractor of Remstroy LLP. the necessary co-financing is 15,756 million tenge. The facility is scheduled to be commissioned by September 2022.
4. "Construction of intra-block gas networks to the settlement of Zhalantos batyr of Kazalinsky district of Kyzylorda region"
The project cost is 469.245 million tenge. The amount of the contract is 436,860 million tenge. 414.311 million tenge was allocated for 2022 (300.0 million tenge was allocated from the National Fund, 114.311 million tenge was allocated from the republican budget), of which 274.0 million tenge was disbursed. The remaining amount is 24.4 million tenge. The general contractor of Remstroy LLP. the necessary co-financing amounts to 43.696 million tenge. The facility is scheduled to be commissioned by September 2022.
Sports facilities.
5. "Construction of a sports complex in the village of K. Primova of the Kumzhiyeksky rural district of the Kazalinsky district of the Kyzylorda region" started in 2021. The project cost is 352.457 million tenge. The amount of the contract is 313,183.9 thousand tenge. In 2021, 194,200 million tenge was disbursed from the National Fund, 124,585 million tenge was allocated for 2022.tenge (NC-70,0 million tenge, RB-22,666 million tenge, OB-31,919 million tenge), 119,585 million tenge has been disbursed. The general contractor is RAGS+GS LLP.
To date, the construction and installation works of the facility have been completed and put into operation on July 28 of this year.
6. "Construction of a sports complex of the Angara type in the village of U. Tuktibayev of the Alginsky aul district of the Kazalinsky district of the Kyzylorda region"
In 2022, according to the program "Auyl el besigi", 242.574 million tenge was allocated for the construction of a sports complex in the village of U. Tuktibayev of the Alga aul district of the Kazalinsky district. The project cost is 281, 293 million tenge. The cost of the contract is 255.776 million tenge. The necessary co-financing funds amounted to 25.577 million tenge. To date, a contractor has been identified and construction has begun. General contractor of SMP-Kyzylorda LLP. The commissioning of the facility is planned before the end of the year
At the expense of the district budget.
7. "Construction of a sports ground in the village of Ayteke bi, the Dostyk microdistrict of the Kazalinsky district.
The project cost is 26.775 million tenge. The amount of the contract amounted to 23.975 million tenge. For 2021, 13.976 million tenge has been allocated from the district budget. 9.999 million tenge has been allocated and disbursed for 2022. The general contractor is Bolashak LLP. The facility was commissioned in April 2022.
8. Construction of a mini-football field on U. Tuktibayev Street in Kazaly, Kazalinsky district.
The project cost is 30.213 million tenge. The amount of the contract is 28.671 million tenge. 28.671 million tenge has been allocated from the district budget to finance the construction, the amount of the contract has been fully disbursed. The general contractor is SCS Engineering LLP.
The facility was commissioned in June 2022.
Construction of sports grounds from rural districts.
9. Work on the construction of a sports playground in the settlement of Shaken.
The project cost is 8.6 million tenge. The amount of the contract amounted to 7.2 million tenge. 7.2 million tenge has been allocated from the district budget to finance the construction, the amount of the contract has been fully disbursed. The general contractor is Engineer Stroy Group LLP.
The facility was commissioned in June 2022.
10. Work on the construction of a sports playground in the settlement of Baykozha.
The project cost is 8.6 million tenge. The amount of the contract amounted to 5.3 million tenge. 5.3 million tenge has been allocated from the district budget to finance the construction, the amount of the contract has been fully disbursed. The general contractor is Namys Kurylys LLP.
The facility was commissioned in May 2022.
11. Construction of a village club for 100 seats in the village of Kaukey, Kazalinsky district.
For the start of construction, 10.0 million tenge was allocated from the regional budget and fully mastered.
The project cost is 372.184 million tenge. The cost of the contract is 335,753 million tenge. The required funds amount to 325,753 million tenge.
To date, the foundation has been laid at the facility, and work is underway to braid wall bricks. The general contractor of SS Engineering LLP is an object transitioning to 2023.
12. Construction of new quarters of the Aimash microdistrict (road construction) of the Aiteke bi settlement of the Kazalinsky district of the Kyzylorda region. The project cost is 179.487 million tenge. The amount of the contract is 157.602 million tenge. 161.537 million tenge was allocated to finance construction for 2021 (NC - 161.537 million tenge), of which 105.0 million tenge was disbursed. The general contractor is RB Stroy LLP.
52.603 million tenge has been allocated for 2022, of which 36.8 million tenge has been disbursed. The remaining amount is 15.8 million tenge. The completion of the facility is planned in September 2022.
13. "Provision of low-pressure gas networks and 0.4 kV electric grid for residential buildings not included in the project "Construction of infrastructure on a 210-hectare land plot in Kent Aitek bi Kazalinsky district of Kyzylorda region"
The project cost is 179.691 million tenge.
156.780 million tenge has been allocated from the republican budget for 2022 to finance this project. The general contractor is Remstroy LLP, the contract amount is 168.942 million tenge. The object is transitioning to 2023.
Objects under construction by the customer from the regional department of construction, architecture and Urban Planning:
14. Construction of a school building for 250 places in the village of Aiteke bi of the Kazalinsky district of the Kyzylorda region. The project cost is 1009.5 million tenge. The contract amount amounted to 847.282 million tenge.
471.779 million tenge has been allocated to finance construction from the republican budget within the framework of the Employment Roadmap for 2021. 411.974 million tenge has been allocated for 2022, construction and installation works are underway. The general contractor is SS Engineering LLP. It is planned to put the facility into operation in November of this year.
15. Construction of a house of culture for 600 people in the village of Aiteke bi Kazalinsky district. The cost of the project is 948,245 million tenge. The amount of the contract amounted to 826.196 million tenge. The general contractor is Kazstroy Service LLP. Construction of the facility began in 2018. 784.896 million tenge was allocated and disbursed to finance construction in 2019-2021, 41.3 million tenge was allocated for 2022. The rest of the work is the installation of DES and the installation of stage equipment.
16. construction of a kindergarten for 140 places in Kazaly, Kazalinsky district, Kyzylorda region" The cost of the project is 712,042 thousand tenge. The amount of the contract amounted to 680.713 million tenge. For 2022, 418,934 million tenge has been allocated from the regional budget, construction and installation works are underway. The remaining funds amounted to 261.8 million tenge. The general contractor of "SMP Kyzylorda" LLP. The object is transitioning to 2023.
17. construction of "polyclinic for 250 visits per shift in the village of Ayteke bi Kazalinsky district". The project cost is 2774.1 million tenge. The amount of the contract amounted to 2450.1 million tenge. The general contractor is SCS Engineering LLP. construction of the facility started in 2020. 2326.6 million tenge were allocated and disbursed to finance construction in 2020-2021. 123.5 million tenge has been allocated for 2022.tenge. To date, the construction and installation works of the facility have been completed and put into operation on April 08, 2022.
In addition, the department provides 4 public services in total. A total of 1,254 applications have been received through the Electronic Licensing portal since the beginning of the year.
Exactly:
- Initial materials for the development of construction projects receipt (APZ) - 633 applications, 629 of them were satisfied, 4 were refused for reasons;
- For approval of the draft design-621 applications, of which 569 were satisfied, 52 motivated refusals;
- Issuance of address register certificates-595 applications (through the PSC), through the e-government portal-221, a total of 816 applications were received. In addition, in the village of Aiteke bi, the city of Kazaly and 19 rural districts, 600 applications for determining, increasing, decreasing the area of a land plot, 65 applications for changing the intended purpose with a visit to each land plot were studied, measured, schemes were developed and submitted to the district land commission for consideration.
Information on the completion of construction works for ІІ quarter of 2022 by the Department of Construction, аrchitecture and Urban Planning of the Kazalinsky district
In 2022, 18 facilities are under construction in the district. Of these, 9 projects are transitioning from 2021, 9 objects are newly started in 2022. 2031.5 million tenge was allocated for the implementation of these projects (NC-640.0 million tenge, RB-647.366 million tenge, OB-693.002 million tenge, AB-51.180 million tenge). To date, construction and installation work has continued at 16 facilities, a public procurement competition is being held for 2 facilities..
In particular:
the State Program of Regional Development for 2020-2025 (1 project).
1. Construction of gas supply in Kazaly, Kazalinsky district.
The project cost is 1026.9 million tenge. The amount of the contract amounted to 883.241 million tenge. 203.679 million tenge for 2020, 683.242 million tenge for 2021 (NF-547.982 million tenge, OB - 135.260 million tenge) 635.172 million tenge was disbursed, 19.391 million tenge was allocated and disbursed for 2022. The general contractor is MBK Kurylys LLP. the facility was commissioned in April 2022. 58,914 km of gas networks have been laid along the facility.
2. "Construction of intra-block gas networks to the settlement of Basykara, Kazalinsky district, Kyzylorda region".
The project cost is 283,196 million tenge. The duration of construction works is 6 months. Within the framework of the "Auyl el Besigi" program, 231.612 million tenge was allocated for 2022 (at the expense of the National Fund 140.0 million tenge, 91.612 million tenge was allocated from the republican budget), of which 135.0 million tenge was disbursed. The general contractor is Remstroy LLP. The amount of the contract is 244.218 million tenge. The facility is scheduled to be commissioned by October 2022.
The project provides for gas pipelines of high pressure – 4496 m, medium pressure-1750 m, low pressure-13469 m, total 19715 m. To date, 80 percent of the construction has been completed.
3."Construction of intra-block gas networks to the settlement of K.Primov of the Kazalinsky district of the Kyzylorda region" The project cost is 172,759 million tenge. The amount of the contract is 157.555 million tenge. The duration of construction works is 4 months. Within the framework of the "Auyl el Besigi" program, 149.423 million tenge was allocated for 2022 (at the expense of the National Fund 130.0 million tenge, 19.423 million tenge from the republican budget), 125.0 million tenge was disbursed. The general contractor is Remstroy LLP. The facility is scheduled to be commissioned in August 2022.
The project provides for 3 cabinet gas control points, medium pressure gas pipelines -1693 m, low pressure-12183 m, total 13,876 m. The project provides for the supply of natural gas to 235 residential buildings, 6 social facilities. To date, 80 percent of the construction has been completed.
4."Construction of intra-block gas networks to the settlement of Zhalantos batyr of the Kazalinsky district of the Kyzylorda region" The project cost is 469.245 million tenge. The amount of the contract is 436,860 million tenge. The duration of construction works is 5 months.
Within the framework of the "Auyl el Besigi" program, 114.311 million tenge was allocated for 2022 (at the expense of the National Fund 300.0 million tenge, from the republican budget 114.311 million tenge), of which 156.0 million tenge was disbursed. The general contractor is Remstroy LLP. The facility is scheduled to be commissioned by September 2022. To date, 60 percent of the construction has been completed.
Sports facilities
5.Within the framework of the "Auyl el besigi" program, construction of a sports complex in the village of K. was started in 2021. Primova of the Kumzhiyeksky rural okrug of the Kazalinsky district of the Kyzylorda region. The project cost is 352.457 million tenge. The amount of the contract is 313,183.9 thousand tenge. In 2021, 194,200 million tenge was allocated from the National Fund, 124,585 million tenge for 2022. (NC-70,0 million tenge, RB-22,666 million tenge, Central Bank-31,919 million tenge) total disbursed 302,303 million tenge. The duration of construction is 7 months. General contractor of "AKHAT+GS" LLP. The facility was commissioned in June 2022.
6. Construction of a sports ground in the village of Ayteke bi, the Dostyk microdistrict of the Kazalinsky district at the expense of the district budget. The project cost is 26.775 million tenge. The amount of the contract amounted to 23.975 million tenge. 13.976 million tenge has been allocated from the district budget for 2021, 9.914 million tenge has been fully disbursed from the district budget for 2022. The general contractor is Bolashak LLP. The facility was commissioned in April 2022.
7. Construction of a mini-football field on U. Tuktibayev Street in Kazaly, Kazalinsky district. The project cost is 30.213 million tenge. The amount of the contract is 28.671 million tenge. 28.671 million tenge was allocated from the district budget to finance the construction and fully mastered. The general contractor is SCS Engineering LLP. The facility was commissioned in June 2022.
8. Work on the construction of a sports playground in the settlement of Shaken. The project cost is 8.6 million tenge. The amount of the contract amounted to 7.2 million tenge. 7.2 million tenge was allocated from the district budget to finance the construction and fully mastered. The general contractor is Engineer Stroy Group LLP.
9. Work on the construction of a sports playground in the settlement of Baykozha.
The project cost is 8.6 million tenge. The amount of the contract amounted to 5.3 million tenge. 5.3 million tenge was allocated from the district budget to finance the construction and fully mastered. The general contractor is Namys Kurylys LLP. The facility was commissioned in May 2022.
10. Construction of a hangar-type sports complex in the village of U. Tuktibayev of the Alginsky aul district of the Kazalinsky district of the Kyzylorda region"
In 2022, according to the program " Auyl el besigi", 242.574 million tenge was allocated for the construction of a sports complex in the village of U. Tuktibayev of the Alginsky rural district of the Kazalinsky district. To date, a public procurement competition is being held. The project cost is 281, 293 million tenge.
11. Construction of a village club for 100 seats in the village of Kaukey, Kazalinsky district.
At the beginning of construction, 10.0 million tenge was allocated from the regional budget and fully mastered.
The project cost is 372.184 million tenge. The contract value is 335,753 million tenge. To date, the foundation has been laid at the facility, work is underway on laying wall bricks. The object is transitioning to 2023.
12. Construction of new quarters of the Aimakash microdistrict (road construction) of the Aiteke bi settlement of the Kazalinsky district of the Kyzylorda region. The project cost is 179.487 million tenge. The amount of the contract is 157601.9 thousand tenge. 161.537 million tenge was allocated to finance construction for 2021 (NC - 161.537 million tenge), of which 105.0 million tenge was disbursed.
52.603 million tenge has been allocated for 2022, of which 10.0 million tenge has been disbursed.
The general contractor is RB Stroy LLP. The completion of the facility is planned in July 2022. According to the project, it is planned to build a gravel road with a total length of 5.4 km (19 streets).
13. According to the object "Supply of low-pressure gas networks and 0.4 kV electric network of residential buildings not included in the infrastructure construction project on a 210-hectare plot of land in the village of Aiteke bi of Kazalinsky district of Kyzylorda region"
The project cost is 179.691 million tenge. 156.780 million tenge has been allocated from the republican budget for 2022 to finance this project. To date, there is a public procurement competition for construction.
Structures under construction by the customer from the regional Department of Construction, Architecture and Urban Planning:
1) construction of a school building for 250 places in the village of Ayteke bi Kazalinsky district of Kyzylorda region. Transitioning from 2021. 411.974 million tenge has been allocated for 2022, construction and installation works are underway.
2) construction of a house of culture for 600 people in the village of Aiteke bi of the Kazalinsky district. Transitioning from 2021. About 41.311 million tenge has been allocated for the completion of construction by 2022.
3) construction of a "polyclinic for 250 visits per shift in the village of Ayteke bi Kazalinsky district". Rolling over from 2021. About-123,504 million tenge has been allocated for the completion of construction by 2022. The facility has been put into operation.
4) " construction of a medical center in the village of Zhuban of Sarykolsky rural district of Kazalinsky district of Kyzylorda region " was commissioned on March 11, 2022.
5) construction of a kindergarten for 140 places in Kazaly, Kazalinsky district, Kyzylorda region"
The cost of the project is 712,042 thousand tenge. Financing of construction-676.595 million tenge. The Central Bank allocated 236.935 million tenge for 2022, construction and installation works are underway.
In addition, the department provides 4 public services. In total, since the beginning of the year, in the district, taking into account the acceptance certificates of 319 residential buildings and 12 construction projects, state services have been provided for the issuance of 426 draft projects, 488 architectural and planning tasks and 338 address certificates.
Information on the completion of construction works for first quarter of 2022 by the Department of Construction,
Architecture and Urban Planning of the Kazalinsky district
Certificate on construction works of the Kazalinsky district Department of Construction, Architecture and Urban Planning for 2022
In 2022, 15 facilities are under construction. Of these, 8 facilities are transitioning from 2021, 7 facilities are newly started in 2022.
In particular:
According to the state program of regional development for 2020-2025
1) construction of gas supply in Kazaly, Kazalinsky district, starting in 2020.
Guide:
58,914 km of gas networks have been laid along the facility. PGB-1 pc., GRPSH-9 pcs. According to the project, 1,565 residential buildings, 28 institutions-enterprises and 51 business objects will be covered by blue fuel. The general contractor is MBK Kurylys LLP. To date, preparatory work is underway for the commissioning of the facility.
Within the framework of the program "Auyl-el besigi"
2) construction of new quarters of the Aimash microdistrict of the Aiteke bi settlement of the Kazalinsky district with the provision of engineering infrastructure (road construction). Transitional from 2021.
Guide:
The construction of a gravel road with a total length of 5.9 km (20 streets) is planned for the object. To date, sand and clay soil have been laid on 19 streets, and work on laying GPS has been carried out on 4 streets. The general contractor is RB Stroy LLP.
3) construction of a sports complex in the village of K. Primova of Kumzhiyeksky rural okrug of Kazalinsky district. Transitional from 2021. The facility is scheduled to be commissioned in June 2022.
Guide:
The foundation of the building is filled in, the walls of the administrative building are lined with brick, the roof is blocked, windows and doors are installed, a KTPN installation is installed, drinking water pipes are supplied, outdoor landscaping is carried out. The general contractor is RAGS+GS LLP.
Within the framework of the sports facilities development program
4) dismantling works were carried out on the construction of a sports ground in the village of Ayteke bi, the Dostyk microdistrict of the Kazalinsky district, leveling of land, laying of gravel mixture. Mesh metal grilles are installed. The object is transitioning from 2021. Delivery is planned in April 2022.
Structures under construction by the customer from the regional Department of Construction, Architecture and Urban Planning:
5) construction of a school building for 250 places in the village of Ayteke bi Kazalinsky district from 2021.
Reference book:
Starting from September 2021, work is underway on the installation of roofing on blocks A,B, C, braiding of wall bricks on block G. The cost of the project is 982.471 million tenge. The duration of construction is 12 months. Funds have been allocated and disbursed for the start of construction within the framework of the Employment Roadmap program. The general contractor is SCS Engineering LLP.
6) construction of a 600-seat house of culture in the village of Ayteke bi Kazalinsky district from 2021.
Reference:
Construction and installation work began in July 2018. To date, construction and installation work has been completed. The rest of the work is the installation of stage equipment and a diesel power plant.
7) the construction of a "polyclinic for 250 visits per shift in the village of Aiteke bi Kazalinsky district" continues. Transitional from 2021.
Reference:
The facility was launched in January 2020, it is planned to be put into operation in April. The general contractor is SS Engineering LLP.
8) the construction of a medical post in the settlement of Zhuban Sarykolsky rural district of Kazalinsky district was put into operation on March 11, 2022.
Objects whose construction has begun this year.
1. "construction of intra-block gas networks to the settlement of Basykara, Kazalinsky district, Kyzylorda region"
The project cost is 283,197 million tenge. The duration of construction works is 6 months. Funds have been allocated for 2022 within the framework of the Auyl el Besigi program, construction and installation work at the facility began on April 04. Contractor of Remstroy LLP.
Guide:
The project provides for 2 cabinet gas distribution points, an underground polyethylene gas pipeline of high pressure-4495 m, medium pressure-1465 m, low pressure-6995 m, aboveground steel gas pipelines of high pressure-1.5 m, medium pressure-285 m, low pressure-6475 m. In addition, the project provides for the supply of natural gas to 247 residential buildings, 10 social, cultural, healthcare facilities, etc.
2."construction of intra-block gas networks to the locality of K. Primova of Kazalinsky district of Kyzylorda region"
The project cost is 172,759 million tenge. The duration of construction works is 4 months. Funds have been allocated for 2022 within the framework of the Auyl el Besigi program, construction and installation work at the facility began on April 04. Contractor of Remstroy LLP.
Guide:
The project provides for 3 cabinet gas distribution points, an underground polyethylene gas pipeline of medium pressure -1683 m, low pressure-10234 m, aboveground steel gas pipelines of low pressure-1949 m. In addition, the project provides for the supply of natural gas to 235 residential buildings, 6 social facilities.
3. "construction of intra-block gas networks to the settlement of Zhalantos batyr of the Kazalinsky district of the Kyzylorda region"
The cost of the project is 469.245 million tenge. The duration of construction works is 5 months. For 2022, funds have been allocated within the framework of the "Auyl el besigi" program. Contractor of Remstroy LLP.
Guide:
The project provides for 6 cabinet gas distribution points, the total length of the gas pipeline is 24958.4 m, high pressure -11019.7 m, medium pressure-2573.8 m, low pressure-11364.9 m. In addition, 261 residential buildings and 10 social facilities have been provided with natural gas.
4. funds have been allocated for the start of construction of a rural club for 100 seats in the village of Kaukey of the Kazalinsky district. The project cost is 372.184 million tenge. The general contractor is SS Engineering LLP.
Reference:
The building area is 32m x19m, the total area of the building is 586.35 m2. The village club building consists of 1 floor. On the territory of the village club there is a cesspool, a 10/0.4 kV KTPN, a shade shed, a modular boiler room, a dumpster, a 4-hole toilet, Parking. The building provides furniture: a table, a wardrobe, a computer, a TV, a sofa, etc.
5. Funds have been allocated for the start of construction of a mini-football field on U. Tuktibayev Street in Kazaly, Kazalinsky district. The cost of the project is 30,213 million tenge. The general contractor is SS Engineering LLP.
For reference: the project provides for the fencing of a special playground with a metal mesh adapted for playing volleyball, basketball and mini-football.
6."construction of a kindergarten for 140 places in Kazaly, Kazalinsky district, Kyzylorda region"
The customer is the Kyzylorda Regional Department of Construction, Architecture and Urban Planning. The project cost is 712.042 million tenge. Contractor LLP "SMP Kyzylorda".
Reference:
Land area 0.75 ha. The project provides for the placement on the territory of the kindergarten-the main building, a heating boiler, a KTPN-160 kVA, a 220 kW DES, a garbage chute and a special playground for 8 groups. There is a kindergarten with 140 seats in total. Of these: up to 2 years-2 groups of 10 children, 2-3 years-2 groups of 20 children, 3-7 years-4 groups of 20 children.
7."construction of a kindergarten for 90 places in the village of Bozkol, Kazalinsky district, Kyzylorda region"
The customer is the Kyzylorda Regional Department of Construction, Architecture and Urban Planning. The cost of the project is 387.011 million tenge. Funds have been allocated for 2022, a public procurement competition is being held.
Reference:
Land area 0.481 ha. On the territory of the kindergarten there is a main building, a boiler room, a KTPN-160 kVA, a 220 kW DES, a garbage chute and a special playground. There is a kindergarten for 90 places in total. Of these: 2 groups of 15 children, 3 groups of 20 children.
The Department has developed design and estimate documentation for 12 projects that were submitted for construction financing.
In particular:
1. construction of a sports complex of the Angara type in the village of U. Tuktibayev of the Alginsky rural district of the Kazalinsky district;
2. construction of a 160-seat sports complex in the village of Ayteke bi Kazalinsky district;
3, construction of a biothermal pit in the village of Zhankent Orkendinsky rural okrug of Kazalinsky district;
4, construction of a cattle burial ground (biothermal pit) of a typical project in Maydakolsky rural okrug of Kazalinsky district;
5. construction of a cattle burial ground (biothermal pit) of a typical project in the rural district of Mailybas of the Kazalinsky district;
6. construction of an administrative building in the village of Ayteke bi Kazalinsky district;
7, construction of the fence of the Karibaibulak border outpost of the Kazalinsky district with a technical protection device;
8. construction of fencing of the territory of the border outpost "Zhankozha Batyr", located in the settlement of Shengeldy of the Kyzylkum rural district of the Kazalinsky district with a technical protection device;
9, construction of a gas pipeline to the land plot allocated for the production zone of the village of Aiteke bi Kazalinsky district;
10. construction of equipment for residential buildings backward from the developed project with low-pressure gas networks and an electric network of 0.4 kV on a land plot of 210 hectares in the village of Aiteke bi of the Kazalinsky district;
11. construction of a 1-storey 2-apartment rental residential building 10 in Kazaly;
12. construction of a 1-storey 2-apartment rental residential building 10 in the village of Ayteke bi.
In addition, $24.173 million has been allocated from the district budget for the development of design estimates for 11 projects for 2022.the money has been allocated and is being developed in tenge.
In particular:
Support to the development and receipt of an expert opinion on the project of providing engineering infrastructure (water supply, electricity, road construction) of residential buildings under construction on a land plot of 600 hectares in the village of Aiteke bi Kazalinsky district;
Support to the development and receipt of an expert opinion of the project "provision of engineering infrastructure (water supply, electricity, road construction) of residential buildings in the newly opened quarter in the village of Muratbaeva Kazalinsky district";
Development and examination of the project for the construction of a sports complex in Kazaly, Kazalinsky district;
Information on the completion of construction works for 12 months of 2021 by the Department of Construction,
Architecture and Urban Planning of the Kazalinsky district
In 2021, the Kazalinsky District Department of Construction, Architecture and Urban Planning plans to build 13 facilities. Of these, 5 objects are transitioning, 8 are new construction. 4025.4 million tenge was allocated for these purposes, V.T.h from the Republic of Belarus-3447.0 million tenge, OB-578.325 million tenge. To date, 5 facilities have been commissioned. In particular:
"Supply of service water supply lines to residential buildings in the village of Zhankozha batyr, Arykbalyk aul district, Kazalinsky district" -10000.0 thousand tenge was allocated from the district budget in 2020 and fully mastered in the same year. In 2021, only 116359.0 thousand tenge was allocated for the completion of construction. t.h. from the republican budget 104723.0 thousand tenge, from the regional budget 11636.0 thousand tenge. The total estimated cost is 121211.0 thousand tenge. Gen.The contractor is Altyn Aidarly LLP. The facility was commissioned on June 26, 2021. Water supply lines for 250 residential buildings and socio-cultural objects have been carried out.
"Supply of service water supply lines to residential buildings in the village of Maydakol, Akzhoninsky aul district of Kazalinsky district" -10000.0 thousand tenge was allocated from the district budget in 2020 and fully mastered. In 2021, only 83064.0 thousand tenge was allocated for the completion of construction. t.h. from the republican budget 74749.0 thousand tenge, from the regional budget 8305.0 thousand tenge. The total estimated cost is 87385.0 thousand tenge. Gen.The contractor is Altyn Aidarly LLP. The facility was commissioned on June 26, 2021. Water supply lines have been installed for 204 residential buildings and socio-cultural objects.
"Construction of the power supply line of a single-storey 4-apartment 10-rental residential buildings in Kent Aitek bi Kazalinsky district" allocated in 2021 a total of 17395.0 thousand tenge.t.h from the republican budget 15565.0 thousand tenge, from the regional budget 1739.0 thousand tenge. Gen.The contractor is Energomera LLP. The facility was commissioned on April 12, 2021. According to the project, 1.8 km of overhead overhead line-0.4 kv was carried out and electric meters were installed for 40 houses.
For the "Construction of the outdoor gas pipeline network of a single-storey 4-apartment 10-rental residential buildings in Kent Aitek bi Kazalinsky district", a total of 12706.7 thousand tenge was allocated in 2021 from the republican budget of 11436.0 thousand tenge, from the regional budget of 1276.7 thousand tenge. Gen.The contractor is NPP and Limited LLP. The facility was commissioned on May 11, 2021. 937 m of low-pressure gas pipeline lines were carried out on the object and gas pipeline lines were brought to 40 houses.
And also for the object "Construction of water supply and sewerage lines of a single-storey 4-apartment 10-rental residential buildings in Kent Aitek bi Kazalinsky district", a total of 35378.0 thousand tenge was allocated in 2021. t.h. from the republican budget 31840.0 thousand tenge, from the regional budget 3538.0 thousand tenge. Gen.The contractor is Altyn Aidarly LLP. The facility was commissioned on May 27, 2021. 581 m of water supply and 600 m of sewer lines were carried out on the object and connected to 40 houses.
A total of 67293.4 thousand tenge was allocated for the construction of the "General layout and landscaping of the territory of a single-storey 4-apartment 10-rental residential buildings in Kent Aitek bi Kazalinsky district" in 2021. Of these, 67293.4 thousand tenge has been mastered. Gen.The contractor is SCS Engineering LLP. The facility is scheduled to be commissioned in October 2021. At the moment, the asphalting of pedestrian roads has been completed and work is underway to fence the territory.
For the construction of "Gas supply ofKazalinsk, Kazalinsky district, Kyzylorda region" 203679.0 thousand tenge was allocated and disbursed in 2020. In 2021, only 683242.0 thousand tenge was allocated for these purposes, including 547982.0 thousand tenge from the Republic of Belarus, 135260.0 thousand tenge from the Republic of Belarus. Of these, 586212.0 thousand tenge has been disbursed. The facility is scheduled to be commissioned by the end of 2021. Gen.The contractor is MBK Kurylys LLP.
To date, 45.5 km of low-pressure gas pipeline, 10 km of high- and medium-pressure underground gas pipeline have been carried out, 4 sets of gas-regulating equipment have been installed, and construction and installation work is underway to install the PGB.
According to the state program "Auyl-El besigi" for 2021, 161537.0 thousand tenge was allocated from the Republic of Belarus for the construction of "Providing engineering infrastructure for new quarters of the m/r Aimakash Kenta Aiteke bi Kazalinsky district (road construction)". Of these, 91650,0 thousand tenge were disbursed in 9 months. Gene.The contractor is RB Stroy LLP. The commissioning of the facility is scheduled for December of this year.
The project provides for the construction of a gravel road with a total length of 5.9 km (20 streets). Currently, 5.4 km of the road base has been laid, as well as GPS for 4 streets.
And also according to the state program "Auyl-El besigi" for 2021, 194200.0 thousand tenge was allocated from the National Fund of the Republic of Kazakhstan for the "Construction of a sports complex in the village of K.Primov of the Kumzhiyek aul district of the Kazalinsky district". The total estimated cost is 352456.763 thousand tenge. The general contractor is "aKhat+GS" LLP. Currently, 48550,0 thousand tenge has been disbursed from the allocated funds. These funds are used for excavation and filling of strip foundations.
According to the state program "Nurly Zher", 294000,0 thousand tenge was allocated for the purchase of housing for the poor and large families from the Republic of Belarus, 94050,0 thousand tenge was allocated for co-financing. The purchase of housing is planned in October, December 2021 according to the financing plan.
In addition, on the part of the customer, the Kyzylorda Regional Department of Construction, Architecture and Urban Planning is building 4 objects, of which 2 are transitioning, 2 are new construction. In particular:
465800.0 thousand tenge was allocated for the construction of a house of culture for 600 seats in Kent Aitek bi Kazalinsky district in 2019, 360420.0 thousand tenge for 2020 and 98000.0 thousand tenge for 2021. The general contractor of Kazkurylys Service LLP. The facility is scheduled for commissioning in October 2021.
505000,0 thousand tenge was allocated for the construction of a polyclinic for 250 visits per shift in Kent Aitek bi of Kazalinsky district in 2020, 1945,109 million tenge for 2021 (RB-1705,098 million tenge; OB-240,011 million tenge.) The general contractor is SCS Engineering LLP. The facility is scheduled for commissioning in December 2021.
According to the "Employment Roadmap" program, 471779.0 thousand tenge was allocated from the National Fund of the Republic of Kazakhstan for the construction of a school for 250 places in Kent Aitek bi Kazalinsky district. The general contractor is SCS Engineering LLP. Construction started in September of this year and earthworks are currently underway.
According to the state program "Auyl-El besigi", only 139303.5 thousand tenge was allocated for the construction of the extension of the gymnasium No. 226 named after B.Mergenbayev in Kent Aitek bi of the Kazalinsky district, including from the RB-128032.0 thousand tenge, from the OB-11271.5 thousand tenge. The general contractor is SCS Engineering LLP. The construction period is 4 months.
In addition, the department provides 4 public services. In total, since the beginning of the year, in the district, taking into account the acceptance certificates of 119 residential buildings and 33 construction projects, state services have been provided for 540 draft designs, 734 architectural and planning tasks and the issuance of 1282 address certificates.
Information on the work done for the first half of 2021 on the construction, architecture and construction of Kazalinsky district
Certificate of completed works in the kazalinsky District Department of construction, architecture and urban planning for the 2nd quarter of 2021
In 2021, the District Department of construction, architecture and Urban Planning provided a total of 1 1 billion. 128 million. 8 projects are being implemented for the amount of 727 thousand tenge, of which 3 projects are being implemented from 2020.
In particular,:
- Construction of" gas supply of Kazalinsky district, Kazalinsky city". (The project cost is млн 982.0 million.tenge. The object is transitional from 2020)
The general contractor is "GBC Kurylys" LLP, the contract amount is 846.7 million tenge. 683,242 million tenge for 2021."I don't know," he said.
According to the contract, the facility will be transferred to 2022, but in accordance with the schedule of Works approved by the general contractor, it is planned to complete the construction work by October this year and connect the city of Kazalinsk to gas.
To date, 7.5 km of low-pressure surface gas pipelines and 1,800 m of medium-pressure underground gas pipelines have been laid, and 3,800 pieces of concrete stands have been installed.
A total of 58,914 km of gas networks will be involved in the project. Installed PGB-1 PC., GRP-9 PCs. 1,565 residential buildings, 28 enterprises and 51 business facilities will be provided with blue fuel.
- "Construction of drinking water supply networks to residential buildings in zhankozha batyr settlement, arykbalyk rural district, kazalinsky District" (project cost 121,210 million tenge. The object is transitional from 2020)
For 2020, 10.0 million tenge was allocated from the district budget. in 2021, 116.359 million tenge was allocated and disbursed. TG was divided.
The general contractor is Altyn aidarly LLP. The allocated funds were fully disbursed and the facility was put into operation on June 29, 2021.
- "Construction of drinking water supply networks to residential buildings in the village of Maydakol, akzhona rural district, kazalinsky district" (the project cost is 87.4 million tenge. The object is transitional from 2020)
For 2020, 10.0 million tenge was allocated from the district budget. in 2021, 83.064 million tenge was allocated and disbursed.TG was divided.
The general contractor is Altyn aidarly LLP. 208 residential buildings will be provided with a drinking water service network. The allocated funds were fully disbursed and the facility was put into operation on June 29, 2021.
Provision of external engineering networks for the object" construction of 10 rental 1-storey 4-apartment residential buildings in Aiteke bi village, Kazalinsky district, Kyzylorda region": including
- External power supply-млн 17,395 million for 2021. TG was divided. The construction completion date is April 2021.
The general contractor is Energomera LLP. tenge. The facility was put into operation on April 12, 2021.
- Supply of external gas networks-млн 12,706 million for 2021. tenge was allocated. The general contractor is "AES and Limited" LLP, the facility was put into operation on May 11, 2021.
- Supply of external drinking water and sewerage networks-млн 35,378 million for 2021. tenge was allocated.
The general contractor is Altyn aidarly LLP. The facility was put into operation on May 27, 2021.
- Master Plan and improvement of the object" construction of 10 rental 1-storey 4-apartment residential buildings in Aiteke bi village, Kazalinsky district, Kyzylorda region": - the project cost is 75,922 million tenge. For 2021, the regional budget allocated 19,046 million tenge for construction and installation works.
A contract was signed with the general contractor "SCS Engineering" LLP for the amount of 68.293 million tenge. The construction completion date is August 2021. Construction and installation works are carried out intensively in accordance with the approved schedule.
- "Construction of engineering infrastructure for new residential quarters of Aymakash microdistrict of Aiteke bi village, Kazalinsky district, Kyzylorda region" (construction of roads)
161,537 million tenge for 2021. according to the results of Public Procurement, a contract was signed with the general contractor "RB Stroy" LLP, the contract amount was 157.602 million tenge. tenge. The construction completion date is December 2021. Construction and installation works are carried out intensively in accordance with the approved schedule.
In parallel with the implementation of these projects, the Regional Department of construction, architecture and urban planning is building 2 projects that have been moving since last year, construction of the 1st project will begin this year, in particular:-
- Construction of the object" House of culture for 600 places in Aiteke bi village, kazalinsky district " - the project cost is 924.2 million tenge.
Construction and installation work began in 2019, and it is planned to put it into operation in August 2021.
The customer is the Department of construction, architecture and urban planning of Kyzylorda region. The general contractor is KazStroyService LLP.
Work is underway on the installation of stage equipment and the installation of a Des unit at the facility.
- Construction of" Polyclinic for 250 visits per shift in Aiteke bi village of kazalinsky district " - the project cost is 1 billion 945 million tenge.
Construction and installation work began in 2020, and it is planned to put it into operation in December 2021. The customer is the Department of construction, architecture and urban planning of Kyzylorda region. The general contractor is SKS Engineering LLP.
Construction and installation works are carried out intensively in accordance with the approved schedule.
- "Construction of a sports hall in the village of Aiteke bi, Kazalinsky district, Kyzylorda region, as an annex to the building of gymnasium No. 226 named after B. Mergenbayev" - the project cost is 128.032 million tenge.
The customer is the Department of construction, architecture and urban planning of Kyzylorda region. The general contractor of" SKS Engineering " LLP has been identified and signed a contract. Construction and installation works are carried out intensively in accordance with the approved schedule.
To finance the employment roadmap program for kazalinsky district for 2021-
- Construction of the administrative building of the institution for the protection of forests and wildlife in kazaly (project cost 231.7 million tenge);
- Construction of an annex to the administrative building of the kazalinsky District Department of internal affairs (project cost 33.5 million tenge);
- Construction of a school for 250 places in the village of Aiteke bi, kazalinsky District (project cost 982.4 million tenge);
- Construction of a sports complex (project cost 348.1 million tenge) in the village of K. Prirovsky, kumzhiek rural district, kazalinsky district to date, within the framework of the program "Auyl El besigi", a public procurement competition is being held with the allocation of 194,200 million tenge from the National Fund.
Along with these projects, "construction of 12 rental 2-storey 12-apartment residential buildings in the village of Aiteke bi, Kazalinsky district" (the project cost is 2.0 billion rubles."construction of a kindergarten for 90 places in the village of Bozkol, Kazalinsky District" (project cost 373.9 million tenge), "construction of a kindergarten" Urimtal" for 140 places in the city of Kazalinsk "(project cost 676.9 million tenge)," construction of a cattle burial ground (BioThermal pit) in the village of Zhankent, Kazalinsky District " (project cost 16.9 million tenge, in the future, if the financial issue is resolved in the clarification of budget funds, these projects will be implemented;
In 2020-2021, new projects are being developed at the expense of funds allocated from the district budget, in particular:
- Projects for the construction of a gas supply facility in the settlements of Zhalantos batyr, K. Priimov of kazalinsky district and a 1-storey 2-Apartment 10-rental residential building in Kazaly, a 1-storey 2-Apartment 10-rental residential building in Aiteke bi village have been developed and are currently under examination, and after receiving the conclusion, they are submitted for financing.
In addition, since the beginning of the year, 32.3 million tenge has been allocated from the district budget for the development and examination of design and estimate documentation for 8 projects, and projects are being developed:-
- "Project of a village club for 100 seats in the village of Kaukey, kazalinsky district";
- "Project for laying a gas pipeline to the production area of Aiteke bi village of kazalinsky district";
- "Project for equipping residential buildings with low-pressure gas networks and 0.4 kv electric networks with a land plot of 210 hectares in the village of Aiteke bi, kazalinsky district" ;
- "Project of a hangar-type Sports Complex in the village of U. Tuktibayev, kazalinsky district";
- "Project of a sports complex for 160 seats in the village of Aiteke bi, kazalinsky district";
- "Project of intra-block gas networks in Basykara settlement, kazalinsky district";
- "Project of animal burial grounds of standard design (BioThermal pit) from 2 rural districts of kazalinsky district (Maydakol, Mailybas);
In addition, the department provides 4 public services. In total, since the beginning of the year, the district has taken into account the acceptance certificates of 82 residential buildings and 10 construction sites, provided 171 draft contracts, 239 architectural and planning tasks and 363 public services for issuing address certificates.
In addition, the department provides 4 public services. In total, since the beginning of the year, the district has taken into account the acceptance certificates of 178 residential buildings and 40 construction sites, provided 389 contracts for draft projects, 538 architectural and planning tasks and 798 public services for issuing address certificates.
Certificate of work done for the 1st quarter of 2021 by the Department of Construction, Architecture and Urban Planning
In 2021, the district department of construction, Architecture and urban planning allocated 901 million tenge. In the amount of 793 thousand tenge, 7 projects are being implemented, of which 3 projects are being transferred from 2020.
In particular:
- Construction of "gas supply of the city of Kazaly, Kazalinsky district". (The project cost is 982.0 million tenge. The object passing from 2020)
General contractor "MBK Kurylys" LLP, the contract amount is 846.7 million tenge.
According to the contract, the object is transferred to 2022, but in accordance with the work schedule approved by the general contractor, it is planned to complete construction work by October of this year and connect the city of Kazalinsk to gas.
A total of 6.5 km of low-pressure aboveground gas pipelines and 1,400 m of medium-pressure underground gas pipelines have been completed to date, and 3,500 pieces of concrete bollards have been installed.
In total, 58,914 km of gas networks will be laid under the project. Installed PGB-1 pc., GRPSH-9 pcs. The blue fuel will cover 1,565 residential buildings, 28 institutions-enterprises and 51 business objects.
- "Construction of drinking water networks to residential buildings in the settlement of Zhankozha batyr of Arykbalyk rural district of Kazalinsky district" (project cost 121,210 million tenge). The object passing from 2020)
For 2020, 10.0 million tenge was allocated from the district budget. 116,359 million tenge was allocated and spent for 2021. selected tg.
General contractor of "Altyn aidarly"LLP. The completion date is scheduled for July 2021. 334 residential buildings will be provided with a drinking service network.
- "Construction of drinking water networks to residential buildings in the village of Maydakol, aul district of Akzhona, Kazalinsky district" (project cost 87.4 million tenge). The object passing from 2020)
For 2020, 10.0 million tenge was allocated from the district budget. 83.064 million tenge was allocated and disbursed for 2021.
General contractor of "Altyn aidarly"LLP. The completion date is scheduled for July 2021. 208 residential buildings will be provided with a drinking service network. Currently, intensive construction and installation work is underway.
Provision of external engineering networks for the object " construction of 10 rental 1-storey 4-apartment residential buildings in the village of Aiteke bi of Kazalinsky district of Kyzylorda region":-
External power supply - 15.656 million tenge for 2021. selected tg. The completion date is April 2021.
General contractor of Energomera LLP. tenge. Construction and installation works are being completed, and documentation for the delivery of the object is being prepared.
Supply of external gas networks-11.436 million tenge for 2021. tenge was allocated. The completion date is May 2021.
General contractor "AES and Limited" LLP, construction and installation works have been started and are being carried out.
Supply of outdoor drinking water and sewerage networks - 31.840 million tenge for 2021. tenge was allocated.
The completion date is July 2021. General contractor of "Altyn aidarly"LLP. To date, having signed a contract with a contractor, construction and installation work has begun.
- "Construction to provide engineering infrastructure for new residential quarters of the Aimash microdistrict of the Aiteke bi settlement of the Kazalinsky district of the Kyzylorda region" (road construction ):-
For 2021, 161.537 million tenge was allocated, according to the results of public procurement, a contract was concluded with the general contractor "RB Stroy" LLP, the amount of the contract was 157.602 million tenge. The completion date is December 2021. Permits have been obtained for the start of construction and installation work, which will begin in April.
In parallel with the implementation of these projects, the regional Department of Construction, Architecture and Urban Planning is building 2 projects that have been transitioning since last year, and construction on the 1st project will begin this year, namely:-
- Construction of the "house of culture for 600 people in the village of Aiteke bi of Kazalinsky district" - the project cost is 924.2 million tenge.
Construction and installation work started in 2019, and commissioning is scheduled for May 2021.
The customer is the Department of Construction, Architecture and Urban Planning of the Kyzylorda region. General contractor "Kazstroy Service" LLP.
The facility is undergoing works on outdoor landscaping, landscaping, construction of sidewalks, finishing of external walls, installation of internal installations and furniture, connection of the heating system.
- Construction of a "polyclinic for 250 visits per shift in the village of Aiteke bi of Kazalinsky district" - the project cost is 1 billion 945 million tenge.
Construction and installation work started in 2020, and commissioning is scheduled for December 2021. The customer is the Department of Construction, Architecture and Urban Planning of the Kyzylorda region. General contractor of "SKS Engineering" LLP.
Construction and installation works are carried out in accordance with the approved schedule.
- The project "construction of a sports hall building as an extension to the building of the B. Mergenbayev gymnasium school No. 226 in the village of Aiteke bi, Kazalinsky district, Kyzylorda region" - the project cost is 128.032 million tenge.
The customer is the Department of Construction, Architecture and Urban Planning of the Kyzylorda region. The general contractor is SKS Engineering LLP and the contract is signed. Construction and installation work will begin at the end of the heating season.
To finance the Employment Roadmap program for the Kazalinsky district for 2021-
- Construction of the administrative building of the institution for the protection of forests and wildlife in the city of Kazaly (project cost 231.7 million tenge);
- Construction of an extension to the administrative building of the Department of Internal Affairs of the Kazalinsky district (project cost 33.5 million tenge);
- Construction of a school for 250 places in the village of Aiteke bi, Kazalinsky district (project cost 982.4 million tenge);
- It is proposed to build a sports complex in the Village of Primova of the Kumzhiyek rural district of the Kazalinsky district (the project cost is 348.1 million tenge), it is planned to start construction work if the financial issue is resolved.
Along with these projects, "construction of 12 rental 2-storey 12-apartment residential buildings in the village of Aitek bi, Kazaly district" (project cost 2.0 billion tenge), "construction of a kindergarten for 90 places in the village of Bozkol, Kazaly district" (project cost 373.9 million tenge), "construction of a kindergarten "Urymtal" for 140 places in Kazaly" (project cost 676.9 million tenge), "construction of a cattle burial ground (biothermal pit) in the village of Zhankent of Kazalinsky district" (the project cost is 16.9 million tenge, if the financial issue is resolved in the future with the clarification of budget funds, this will be implemented in the projects;
In 2020-2021, new projects are being developed with the funds allocated from the district budget, in particular:
- Projects have been developed for the construction of a gas supply facility for the settlements of Zhalantos Batyr, K. Primov, Kazalinsky district, and 10 rental 1-storey 2-apartment residential buildings in Kazaly, 10 rental 1-storey 2-apartment residential buildings in the village of Aitek bi, which are currently under expert review and after receiving an opinion are submitted for construction financing .
In addition, since the beginning of the year, 32.3 million tenge has been allocated from the district budget for the development and examination of design and estimate documentation for 8 projects.:-
- Project of the village club for 100 seats in Kakukey village of Kazalinsky district»;
- The project of the gas pipeline to the production zone "Aiteke village" of the Kazalinsky district"»;
- "Project for equipping residential buildings with low-pressure gas networks and a 0.4 kV electric network that lag behind the developed project for a land plot of 210 hectares in the village of Aiteke bi, Kazalinsky district";
- Project of a sports complex of the Angara type in the village of Tuktibayev, Kazalinsky district»;
- Project of a sports complex with 160 seats in the village of Aiteke bi, Kazalinsky district»;
- "Project of intra-block gas networks in Basykara settlement of Kazalinsky district»;
- Project of a typical animal burial ground (biothermal pit) from 2 rural districts of Kazalinsky district (Maydakol, Maylybas));
In addition, the department provides 4 public services. In total, since the beginning of the year, the district has taken into account the acceptance certificates of 82 residential buildings and 10 construction projects, provided state services for the issuance of 171 draft designs, 239 architectural and planning tasks and 363 address certificates.
Работы в сфере строительства
Справка 2020 г
В 2020 году районным отделом строительства, архитектуры и градостроительства было реализовано 11 проектов на 1 млрд. 591 млн. тенге, из них 2 проекта переходящие с 2019 года, 3 проекта переходящие на 2021 год
В частности:
Программа развития регионов до 2020 года
1) «Обеспечение инфраструктурой жилых домов (строительство дорог), строящихся на земельном участке площадью 81 гектар от города Казалы» переходящий с 2019 года. Сумма договора - 134,6 млн. тенге. На 2019 год выделено 120,929 млн. тенге, на 2020 год 13,671 млн. тенге, средства освоены в полном объеме. (Подрядчик ТОО «СтройМодульАстана»).
Строительно-монтажные работы были завершены 13 ноября 2020 года и приняты в эксплуатацию.
Государственная программа жилищно-коммунального развития «Нұрлы жер»
2) на строительство 18-квартирного арендного многоэтажного жилого дома в поселке Айтеке би в 2019 году выделено 140,950 млн. тенге, на 2020 год 7,85 млн. тенге. Генеральный подрядчик ТОО "Бер-Нур Тараз". Сумма договора 148,8 млн. тенге. Строительно-монтажные работы были завершены 13 октября 2020 года и приняты в эксплуатацию.
3) на строительство 1-этажного 4-квартирного жилого дома в п. Айтеке би было выделено 285,292 млн. тенге из республиканского бюджета, 96,785 млн. тенге из областного бюджета, всего 382,077 млн. тенге. Генеральный подрядчик ТОО "Мунай Курылыс". Сумма договора 382,077 млн. тенге. Строительно-монтажные работы завершены 30 ноября 2020 года и приняты в эксплуатацию.
Государственная программа поддержки и развития бизнеса «Дорожная карта бизнеса 2025»
4) строительство» обеспечение инфраструктуры транспортно-логистического центра (питьевая вода, канализация, телефонизация, электро -, газоснабжение) в поселке Айтеке би Казалинского района. Выделенные средства составили 148,8 млн. тенге. Генеральный подрядчик ТОО "Казстройсервис". Сумма договора составила 178,931 млн. тенге. Строительно-монтажные работы объекта завершены и приняты в эксплуатацию 27 ноября 2020 года.
В рамках Дорожной карты занятости проведено строительство 3 проектов:
5) обеспечение инженерными сетями (электричество, газ, вода) жилого района Аймакаш поселка Айтеке би Казалинского района. Было выделено и освоено 243,546 млн. тенге. Подрядчиком по обеспечению водоснабжением и газоснабжением является ТОО «Жылу-ХХІ», подрядчиком по электроснабжению ТОО "Энергомера".
Строительно-монтажные работы объекта завершены и введены в эксплуатацию в июле, августе, сентябре 2020 года. Согласно плану создано 50 рабочих мест, из них 25 трудоустроены по направлениям центров занятости населения. Работы по электроснабжению завершены в июле этого года, по водоснабжению - в августе, по газоснабжению - в сентябре. Всего будет предоставлено 120 земельных участков.
6) строительство внутриквартальных газовых сетей в населенном пункте Гани Муратбаева Казалинского района. Было выделено и освоено 239,507 млн. тенге. Генеральный подрядчик ТОО "Сапак". Согласно плану создано 60 рабочих мест, по направлению центров занятости трудоустроено 30 человек. Строительно-монтажные работы на данном объекте завершены и приняты в эксплуатацию 15 декабря 2020 года.
(по проекту рассмотрено 293 дома, фактически охвачено 320 домов, около 100 домов подключены к газопроводу)
7) строительство сельского клуба на 150 мест в селе Аксуат Майлыбасского сельского округа. Было выделено и освоено - 210,823 млн. тенге. Генеральный подрядчик ТОО "Болашак".
Согласно плану создано 52 рабочих места, из них 26 будут привлечены по направлениям центров занятости населения, 26 человек полностью трудоустроены. Принят в эксплуатацию 15 декабря 2020 года.
В рамках программы "Ауыл-ел бесігі"
8) на строительство сервисных водопроводов к жилым домам в населенном пункте Бекарыстан би было выделено 210,823 млн. тенге. Генеральный подрядчик ТОО "Намыс-Курылыс". Сумма договора составила 174,061 млн. тенге. Строительно-монтажные работы на данном объекте полностью завершены и приняты в эксплуатацию 03 декабря 2020 года.
Областным управлением строительства, архитектуры и градостроительства выполнено строительство 4 объектов
- Строительство «Поликлиники на 250 посещений в смену в поселке Айтеке би Казалинского района». На 2020 год было выделено 505,0 млн. тенге. Дополнительно необходимый объем средств составил 1,946 млрд. тенге. В настоящее время ведутся строительные работы.
- «Строительство административного здания в поселке Айтеке би Казалинского района Кызылординской области». На 2020 год было выделено 148,9 млн. тенге. Объект введен в эксплуатацию в октябре 2020 года.
- «Строительство дома культуры на 600 мест в поселке Айтеке би Казалинского района» с 2019 года. На 2019 год из областного бюджета выделено 465,8 млн. тенге. в 2020 году было выделено и освоено 360,42 млн. тенге. В настоящее время ведутся строительные работы.
- «Строительство детского сада на 90 мест в селе Аксуат Казалинского района» с 2019 года. На 2019 год из областного бюджета выделено 152,3 млн. тенге. В 2020 году выделено и освоено 244,533 млн. тенге. Строительно-монтажные работы завершены в июле 2020 года и приняты в эксплуатацию.
Наряду с этой работой из районного бюджета на августовскую сессию 2020 года выделено и освоено 20,0 млн тенге на начало строительства сервисных водопроводных сетей к жилым домам в населенном пункте Майдаколь и Жанкожа батыр. Объекты – переходящие на 2021 год. Генеральный подрядчик ТОО «Алтын Айдарлы».
(Строительство сервисных водопроводных сетей к жилым домам в селе Майдаколь – 81,753 млн. тенге);
(Строительство сервисных сетей водоснабжения к жилым домам в селе Жанкожа батыр – 114,739 млн. тенге)
Кроме того, на строительство газоснабжения города Казалы Казалинского района из республиканского бюджета на 2020 год выделено 200,0 млн. тенге, из районного бюджета – 3,976 млн. тенге. Стоимость проекта 982,0 млн. тенге. Генеральный подрядчик ТОО «МБК Курылыс». Объект переходящий на 2021 год.
На сегодняшний день проведено 1700 метров газопроводов низкого давления, установлено 500 штук бетонных тумб, установлены железные столбы.
Проекты, представленные на финансирование строительно-монтажных работ:
Для полного завершения строительства 10 4-х квартирных жилых домов, начатых в поселке Айтеке би, должны быть проведены работы по обеспечению наружными инженерными сетями.
В связи с этим бюджетная заявка на сумму 141,401 тыс. тенге передана в областное управление строительства, архитектуры и градостроительства.
«Строительство 12 арендных 2-х этажных 12-квартирных жилых домов в поселке Айтеке би Казалинского района». Объем финансирования строительства 2011,546 млн. тенге.
Проект «Строительство детского сада на 90 мест в с. Бозколь Казалинского района» разработан в 2019 году. Объем финансирования строительства составил 373,927 млн. тенге. Предлагается выделить средства в рамках Дорожной карты занятости.
Разработка проектно-сметной документации и проекты, предлагаемые к финансированию
На начало 2020 года из районного бюджета выделено 42,3 млн тенге на разработку новых проектов, разработано 4 проекта. В частности:
- На разработку и экспертизу проектно-сметной документации на строительство школы №170 на 250 мест в поселке Айтеке би выделено 24,9 млн. тенге. Стоимость проекта 982,449 млн. тенге. Предлагается выделить средства в рамках Дорожной карты занятости.
- На разработку и экспертизу проектно-сметной документации проекта пристройки к школе-гимназии №226 (спортивный зал) выделено 3,5 млн тенге. Стоимость проекта 128,032 млн. тенге. Предлагается выделить средства в рамках проекта «Ауыл ел бесігі».
- На проект по обеспечению внешней инженерной инфраструктурой 12 арендных 2-х этажных 12-квартирных жилых домов поселка Айтеке би выделено 12,9 млн тенге, проект разработан. Стоимость проекта 511,701 млн. тенге. На финансирование строительства рекомендовано областное управление строительства, архитектуры и градостроительства.
- На разработку и экспертизу проектно-сметной документации 1 тренажерной и стритбольной площадки в поселке Айтеке би выделено 1,0 млн тенге, проект разработан . Стоимость проекта составила 20,918 млн. тенге. Предлагается выделить средства в рамках Дорожной карты занятости.
Наряду с этой работой на 2020 год из районного бюджета выделено 30,6 млн тенге, разрабатывается 5 проектов.
- Разработка и экспертиза проектно-сметной документации на строительство объекта «Газоснабжение населенных пунктов Жалантос батыр, К. Пиримов Казалинского района», спортивного комплекса В С. К. Пиримов и строительство 10 арендных 1-этажных 2-х квартирных жилых домов в г. Казалы и 10 арендных 1-х этажных 2-х квартирных жилых домов в п. Айтеке би.
Работы в сфере строительства
9-месячная справка
В 2020 году на реализацию 8 проектов было выделено в общей сложности 1 млрд. 368 млн. тенге (616,8 млн тенге из РБ, 750,9 млн тенге из ОБ).
В частности:
В рамках Дорожной карты занятости выделено 243,546 млн тенге на строительство инженерных сетей (электричество, газ, вода) в микрорайоне Аймакаш, поселок Айтеке би Казалинского района Кызылординской области, стоимость проекта - 243,546 млн тенге. Сумма договора - 214,448 млн тенге. За счет выделенных средств освоено 214,448 млн тенге. Подрядчик по работам водоснабжения и газоснабжения – ТОО «Жылу XXI», а по электроснабжению - ТОО «Энергомера». Количество работающих через центр занятости - 25 человек. Срок строительства 12.05.2020-31.09.2020 (3,5 месяца)
На сегодняшний день строительство электроснабжения, водоснабжения и газоснабжения завершены.
Наряду с этим проектом был разработан и внесен на финансирование из областного бюджета проект строительства дороги в микрорайоне Аймакаш. Стоимость проекта 175,2 млн тенге. В случае реализации проекта из нового жилого массива будет переведено около 120 земельных участков.
В рамках Дорожной карты занятости выделено 239,507 млн тенге на строительство внутриквартальных газопроводов в селе Гани Муратбаев Казалинского района. Стоимость проекта составляет 270,426 млн тенге. Сумма контракта - 219,033 млн тенге. Из выделенных средств освоено 157 миллионов тенге. Подрядчик "Сапак" ПК. Газопроводы будут проложены в 293 домах согласно проекту,
Количество работающих через центр занятости - 30 человек. Срок строительства 20.05.2020-05.10.2020 (4,5 месяца). На сегодняшний день выполнено более 80% всех работ, остальные работы - это обследование газопровода, строительство газопроводов в жилые дома, подключение перекрестков.
В рамках Дорожной карты занятости выделено 210,823 млн тенге на строительство сельского клуба на 150 мест в селе Аксуат Майлыбасского сельского округа Казалинского района. Стоимость проекта составляет 230,806 млн тенге. Сумма договора - 187,759 млн тенге. Из выделенных средств освоено 93,0 млн тенге. тенге. Подрядчик - ТОО «Болашак». Количество работающих через центр занятости - 26 человек. Срок строительства 25.05.2020 - 25.04.2021 (11 месяцев). Согласно контракту, строительные работы должны быть завершены в 2021 году, но подрядчик планирует завершить их в декабре этого года. На сегодняшний день заложен фундамент объекта, уложены стены, покрыта крыша, проведены работы по ограждению, ведется строительство зрительного зала здания, строительство уличного туалета, закладывается фундамент парового котла.
По программе «Ауыл-Ел бесігі» было выделено 168,2 млн. тг на проект «Проведение сервисного водопровода к жилым домам в селе Бекарыстан би Казалинского района». Сумма договора - 137,5 млн тенге. Из выделенных средств освоено 90,0 миллионов тенге. Всего будет обслужено 467 домов.
Подрядчик ТОО «Намыс Курылыс». Количество работающих через центр занятости - 8 человек. Срок строительства 20.05.2020- 05.12.2020 (6,5 месяцев). На сегодняшний день проложено 17,7 км водопроводов, смонтировано 92 железобетонных колодца. Подведены инженерные сети к 430 домам и 3 учреждениям.
В рамках Программы регионального развития до 2020 года проводятся работы по «Обеспечению инфраструктурой участка в 81 га в г. Казалинск Казалинского района Кызылординской области». Стоимость проекта 169,3 млн тенге. Генеральный подрядчик - ТОО «СтройМодуль Астана». Сумма договора составляет 142,650 млн тенге (РБ-128,979 млн тенге, ОБ-13,671 млн тенге).
Строительство шести 18-квартирных многоэтажных жилых домов в поселке Айтеке би в рамках государственной программы жилищного строительства «Нурлы жер». Подрядчик - ТОО «БерНурТараз».
В рамках государственной программой жилищного строительства «Нурлы жер» из республиканского бюджета выделено 285,292 миллиона тенге на строительство 10 одноэтажных 4-х квартирных домов стоимостью 424,7 миллиона тенге в поселке Айтеке би. По результатам государственных закупок победителем был определен ТОО «Многопрофильная строительная фирма« МунайКурылыс». Сумма договора - 382,077 млн тенге (РБ-285,292 млн тенге, ОБ-96,785 млн). Срок строительства 8 месяцев.
Бюджетная заявка на софинансирование в размере 96,8 млн тенге подана в областное управление строительства из-за отсутствия средств. Если финансовые вопросы будут полностью решены, строительство будет завершено и сдано в эксплуатацию в этом году.
Через центр занятости трудоустроено 19 человек.
Строительство объекта «Обеспечение инфраструктурой транспортно-логистического центра в поселке Айтеке би Казалинского района Кызылординской области (внешнее водоснабжение, канализация, телефония, электричество, газоснабжение)» в рамках государственной программы поддержки и развития предпринимательства «Дорожная карта бизнеса-2025». Стоимость проекта 210,82 млн тенге. Сумма договора составляет 178,249 млн тенге. Генеральный подрядчик - ТОО «КазстройСервис».
В августе из районного бюджета было выделено 10,0 млн тенге на строительство систем технического водоснабжения жилья в селе Майдаколь, а сегодня проводятся государственные закупки. (Заключение эксперты 11.02.2019 № ЭПРО-0053/19. Необходимые средства на выполнение строительных работ - 81,753 млн тенге).
В августе из районного бюджета было выделено 10,0 миллионов тенге на строительство систем технического водоснабжения жилых домов в селе Жанкожа батыр. (Заключение эксперты 11.11.2018 № ЭПРО-0332/18. Необходимые средства для финансирования строительных работ - 114,739 млн тенге).
Программа регионального развития до 2025 года. В октябре текущего года на строительство объекта «Газоснабжение г. Казалинска Казалинского района Кызылординской области» планируется выделить 200,0 млн тенге из области. (Заключение эксперты от 03.07.2019 №14-0093/19. Общая сметная стоимость проекта - 1026,907 млн тенге. Необходимые средства для финансирования строительных работ - 981,191 млн тенге)
Поэтому на начало строительных работ по данному объекту из районного бюджета выделено 3,7 млн тенге, проводятся государственные закупки.
С начала года на строительство 8 объектов было выделено 178,628 тыс. тенге из республиканского бюджета, 1 155,839 млн. тенге из областного бюджета, всего 1 334,467 млн. тенге. Ведутся строительно-монтажные работы.
В частности:
Строительство дома культуры на 600 мест в поселке Айтеке би. Стоимость проекта составляет 948,2 млн. тенге. Генеральным подрядчиком является ТОО «ҚазқұрылысСервис». В 2019 году из областного бюджета было выделено и освоено 550,0 млн. тенге. А на 2020 год было выделено 222,322 2020 млн. тенге. Заказчик областное управление строительства, архитектуры и градостроительства.
Строительство детского сада на 90 мест в селе Аксуат Майлыбасского сельского округа. Стоимость проекта составляет 460,462 млн. тенге. Генеральный подрядчик ТОО «Орион LTD». В 2019 году из областного бюджета было выделено и освоено 147,725 млн. тенге. На 2020 год выделенл 142,276 млн. тенге. Заказчик областное управление строительства, архитектуры и градостроительства.
В рамках государственной программы жилищного строительства "Нұрлы жер" построено 6 многоэтажных 18-ти квартирных арендных жилых домов в поселке Айтеке би. Стоимость проекта млн 171,820.тенге. Генеральный подрядчик ТОО «Бер-Нур-Тараз». В 2019 году было выделено и освоено 141,033 млн. тенге. На 2020 год выделено 7,85 млн. тенге. Ведутся строительно-монтажные работы. Заказчик отдел строительства, архитектуры и градостроительства Казалинского района.
Обеспечение инфраструктурой (строительство дорог) земельных участков под ИЖС площадью 81 гектар в городе Казалинск Казалинского района. Стоимость проекта 169,3 млн. тенге. Генеральный подрядчик ТОО «СтройМодуль Астана». В 2019 году было выделено 136,779 млн. тенге из республиканского бюджета. 13,671 млн. тенге из областного бюджета на софинансирование и освоено 128,979 млн. тенге. На 2020 год выделено 13,671 млн. тенге, ведется строительство. Заказчик отдел строительства, архитектуры и градостроительства Казалинского района.
Строительство поликлиники на 250 посещений в смену в поселке Айтеке би. Стоимость проекта 2753,0 млн. тенге. Генеральный подрядчик ТОО «SCS Инжинеринг». На 2020 год выделено 550,0 млн. тенге, ведется строительство. Заказчик областное управление строительства, архитектуры и градостроительства.
Строительство административного здания государственного коммунального предприятия по охране лесов и животного мира в городе Казалинск. Стоимость проекта 253,2 млн. тенге. Генеральным подрядчиком является ТОО «ҚазқұрылысСервис». На 2020 год выделено 50,0 млн. тенге, ведется строительство. Заказчик областное управление строительства, архитектуры и градостроительства.
Строительство административного здания в поселке Айтеке би. Стоимость проекта составляет 152,3 млн. тенге. Генеральный подрядчик ТОО «Орион LTD». На 2020 год выделено 148,9 млн. тенге, ведется строительство. Заказчик областное управление строительства, архитектуры и градостроительства.
Обеспечение транспортно-логистического центра в поселке Айтеке би инфраструктурой (внешние сети водоснабжения, канализации, телефонизации, электроснабжения, газоснабжения) в рамках государственной программы «Дорожная карта бизнеса-2025» для поддержки и развития бизнеса. Стоимость проекта 210,82 млн. тенге. Генеральным подрядчиком является ТОО «ҚазқұрылысСервис». На 2020 год выделено 178,628 млн. тенге из республиканского бюджета, 20,261 млн. тенге из областного бюджета. Ведется работы по заключению договоров с подрядчиком. Заказчик отдел строительства, архитектуры и градостроительства Казалинского района.
Также в текущем году в целях обеспечения жильем многодетных семей, социально уязвимых групп населения ведутся работы по приобретению 3-х комнатных 40 квартир. В случае выделения средств многодетные семъи и социально уязвимые группы населения будут обеспечены жильем.