Construction

Reference for the first quarter of 2025

About the objects being implemented for 2025 in the Department of construction, architecture and urban planning of kazalinsky district.
 
In total, 11 facilities are planned to be built in 2025. Of these, 7 objects are transitional from 2024 to 4 new ones.
For the implementation of these projects, 4.7 billion rubles were allocated from the Republican and regional budgets for 2025. the tenge was allocated.
Transitional objects from 2024:
1. "construction of a sports complex in Bekrysta bi village of Kazalinsky district"
The contract cost 398.494 million tenge in 2024-2025 within the framework of the program" Auyl –El besigi " 358.646 million tenge (RB 50.0 million tenge in 2024. 308.646 million tenge for 2025.) divided.
  To date, 50.0 million tenge has been disbursed, the necessary funds are 39.848 million tenge. 
Currently, work has been carried out on pouring concrete into the columns of the foundation, conducting a 10 KVA power line and maintaining a drinking water network.
The contractor is Zhylyk XXI LLP.
2. "construction of a sports complex from the Zhenis Park in Aiteke bi Village, Kazalinsky district"
The contract cost 628.743 million tenge in 2024-2025 within the framework of the program" Auyl –El besigi " 378.758 million tenge (RB 50.0 million tenge in 2024. 328.758 million tenge for 2025.) divided.
To date, 50.0 million tenge has been disbursed. The necessary funds are 249.985 million tenge.
At the moment, the foundation of the ghimrat has been poured.
  The contractor is Bolashak LLP.
3. "construction of a sports complex in the village of Kozhabakty, Kazalinsky district"
The contract cost 537.1 million tenge in 2024-2025 within the framework of the program" Auyl –El besigi " 395.0 million tenge (RB 50.0 million tenge in 2024. 345.027 million tenge for 2025.) divided.
To date, 50.0 million tenge has been disbursed.The necessary funds are 142.1 million tenge.
To date, work has been completed on pouring the foundation, masonry and laying the outer walls of the building to a height of 2 m. Brickwork was also carried out on the inner walls.

 


About the ongoing work and upcoming tasks in the field of construction, architecture and urban planning.

In total, 13 facilities are planned to be built in kazalinsky district in 2024. The total cost of the project is 10.9 billion tenge. For the implementation of these projects,5.8 billion rubles were allocated from the Republican, regional and district budgets for 2024. the tenge was allocated.
Of these: -10 new projects, with the construction of 3 facilities in transition from 2023.

Transitional objects:
1. "construction of intra-block gas networks in Abay settlement, Kazalinsky district"
The contract cost 343.094 million.tenge. (In 2023, the OB – 41.153 million tenge was allocated, in 2024 the RB - 25.384 million Tenge, the OB-281.056 million tenge.) To date, construction work has been completed and put into operation.
The contractor is " Remstroy "LLP, the author's supervisor is" Association "LLP, the technical supervisor is" Stroyservice KNK " LLP.
2." construction of a rural club for 100 seats in the village of Kuukey, Kazalinsky district"
The contract cost 335.752 million. tenge. In 2022, 10.0 million rubles were allocated from the regional budget for the start of construction. tenge. 325.752 million from the regional budget for the continuation of construction for 2023. the tenge was allocated. To date, construction work has been completed and put into operation.
The contractor is" SCS Engineering "LLP, the author's supervisor is" pus Shymkent "LLP, the technical supervisor is" Asem Kurylys Kyzylorda " LLP.
3. "construction of an administrative building at the Aiteke bi mine, Kazalinsky district"
The contract cost 341.2 million. tenge. In 2023, 5.0 million rubles were allocated from the regional budget for construction. tenge was allocated and 1.437 million tenge was disbursed. For 2024, 339,763 million tenge was allocated to the central bank.
The contractor is" SK Montazh and Stroy "LLP, the author's supervisor is" Shynar project "LLP, the technical supervisor is" Zhana Zhazy-K " LLP.

Документы
Information
06 марта 2025
Announcement of exposure screening review
Budget
27 января 2025
472 is the code and name of the administrator of the budget program of the municipal state institution " Department of Construction, Architecture and Urban Planning of the Kazalinsky district" for 2024-2026
Information
06 декабря 2024
Advertisement On consideration of exposure screening
Новости
Полезные материалы
Information about the work done by the district Department of Construction, Architecture and Urban Planning
Медиагалерея
События
Реализуемые проекты
Услуги
Организации
Часто задаваемые вопросы

Социальные медиа

Facebook
Instagram
Youtube
Вконтакте

Меню подвал

State of the Nation Address of the President of Kazakhstan
Website of the President of Kazakhstan
Website of the Prime Minister of Kazakhstan
Digital transformation concept
Life situations
National symbols
Terms and explanations
Central communications service under the President of the RK
Screen Reader
Құпиялылық саясаты