Industrial zones

Information about the current state of Industrial zones of the Kyzylorda region
(January-March)

On the territory of the region there are 6 industrial zones with a total area of 511.9 hectares. To date, 245.5 hectares of land have been developed from the allocated land plots for 56 projects with a total cost of 197.2 billion tenge. About 6.7 billion tenge was allocated from the budget for the construction of infrastructure. Each industrial zone has a developed infrastructure (energy and water supply, natural gas supply, etc.). Out of 56 projects, 22 projects worth 65.3 billion tenge were implemented, where 349 jobs were created. In 2020, the introduced projects produced products worth 12.5 billion tenge.

No.

Industrial zones

Land area, ha

Project cost (billion tenge)

Workplaces

Projects

Total

Mastered

total

implemented

At the stage of implementation

1

Kyzylorda city

366

152,5 (41,5%)

128,8

1 101

11

1

10

2

Aral district

6

6,0 (100%)

1,7

135

4

2

2

3

Kazaly district

6,9

4,83 (70%)

0,172

43

8

6

2

4

Karmakshy district

15

4 (26,6%)

0,143

35

4

1

3

5

Zhalagash district

22

13,2 (59%)

0,758

149

19

8

11

6

Shieli district

96

65 (67,7%)

65,8

463

10

4

6

Total

511,9

245,5 (48%)

197,2

1928

56

22

34


Information about the current state of Industrial zones of the Kyzylorda region
(January-December)


On the territory of the region there are 6 industrial zones with a total area of 511.9 hectares. To date, 245.5 hectares of land have been developed from the allocated land plots for 56 projects with a total cost of 197.2 billion tenge. About 6.7 billion tenge was allocated from the budget for the construction of infrastructure. Each industrial zone has a developed infrastructure (energy and water supply, natural gas supply, etc.). Out
of 56 projects, 22 projects worth 65.3 billion tenge were implemented, where 349 jobs were created.
In 2020, the introduced projects produced products worth 12.5 billion tenge.

No.

Industrial zones

Land area, ha

Project cost (billion tenge)

Workplaces

Projects

Total

Mastered

total

implemented

At the stage of implementation

1

Kyzylorda city

366

152,5 (41,5%)

128,8

1 101

11

1

10

2

Aral district

6

6,0 (100%)

1,7

135

4

2

2

3

Kazaly district

6,9

4,83 (70%)

0,172

43

8

6

2

4

Karmakshy district

15

4 (26,6%)

0,143

35

4

1

3

5

Zhalagash district

22

13,2 (59%)

0,758

149

19

8

11

6

Shieli district

96

65 (67,7%)

65,8

463

10

4

6

Total

511,9

245,5 (48%)

197,2

1928

56

22

34


Information on the current state of the Industrial zones of Kyzylorda region
(January-July 2020)

There are 6 industrial zones with a total area of 904.9 hectares in the region. To date, from the allocated land plots, 243.5 hectares of land have been developed for 55 projects with a total cost of KZT 197 billion. About KZT 6.7 billion has been allocated from the budget for the construction of infrastructure. Each industrial zone has a well-developed infrastructure (energy and water supply, natural gas supply, etc.).
Out of 55 projects, 21 projects worth KZT 65.3 billion were implemented, where 339 jobs were created.
In 2019, the introduced projects produced products for KZT 9.2 billion, in January-May 2020, products for KZT 782.6 million were produced
In 2019, 5 projects were commissioned for KZT 166 million, with the creation of 14 new places.

No.

Industrial zones

Land area, ha

Project cost (billion tenge)

Workplaces

Projects

Total

Mastered

total

implemented

At the stage of implementation

1

Kyzylorda city

760

150,5 (19,8%)

128,6

1 101

10

1

9

2

Aral district

10

6,0 (60%)

1,7

135

4

2

2

3

Kazaly district

6,9

4,83 (70%)

0,172

43

8

5

3

4

Karmakshy district

15

4 (26,6%)

0,143

35

4

1

3

5

Zhalagash district

17

13,2 (77,6%)

0,758

149

19

8

11

6

Shieli district

96

65 (67,7%)

65,8

463

10

4

6

Total

904,9

243,5 (26,9%)

197

1926

55

21

34


Information on the current state of the Industrial zones of Kyzylorda region
(January-November)


In the region, there are 6 industrial zones with a total area of 909.9 hectares. To date, 216 hectares of land have been developed from allocated land plots for 50 projects with a total value of KZT 193.8 billion. About KZT 6.7 billion were allocated from the budget for the construction of infrastructure. Each industrial zone has developed infrastructure (energy and water supply, natural gas supply, etc.).
Of the 50 projects, 21 projects were implemented worth KZT 65.3 billion, where 346 jobs were created.
Following the results of 11 months of 2019, the introduced projects produced products worth KZT 5.3 billion.
Since the beginning of the year, 5 projects have been introduced for KZT 166 million, with the creation of 14 new places.

№

Industrial areas

Land area, ha

Project cost (billion tenge)

Workplaces

Projects

Total

Mastered

Total

Implemented

Under implementation

1

Kyzylorda city

760

125,2 (16,4%)

126,9

1 043

10

1

9

2

Aral district

10

5,0 (50%)

0,239

100

3

2

1

3

Kazaly district

6,9

4,83 (70%)

0,172

24

8

5

3

4

Karmakshy district

15

3,1 (20.6%)

0,081

20

2

1

1

5

Zhalagash district

22

12,7 (57,7%)

0,648

144

17

8

9

6

Shieli district

96

63 (65,6%)

65.8

459

10

4

6

Total

909,9

213,8 (23.5%)

193.8

1790

50

21

29

Дата публикации
08 октября 2020
Дата обновления
05 октября 2026
Тип
Useful information

Сейчас читают

Useful information
29 июля 2022
Report on the development of small and medium-sized businesses
Useful information
07 июля 2022
Investments in fixed assets
Useful information
08 октября 2020
Investment attractiveness of the region

Социальные медиа

Фейсбук

Меню подвал

State of the Nation Address of the President of Kazakhstan
Website of the President of Kazakhstan
Website of the Prime Minister of Kazakhstan
Digital transformation concept
Life situations
National symbols
Terms and explanations
Central communications service under the President of the RK
Screen Reader
Құпиялылық саясаты