Information about the current state of Industrial zones of the Kyzylorda region
(January-March)
On the territory of the region there are 6 industrial zones with a total area of 511.9 hectares. To date, 245.5 hectares of land have been developed from the allocated land plots for 56 projects with a total cost of 197.2 billion tenge. About 6.7 billion tenge was allocated from the budget for the construction of infrastructure. Each industrial zone has a developed infrastructure (energy and water supply, natural gas supply, etc.). Out of 56 projects, 22 projects worth 65.3 billion tenge were implemented, where 349 jobs were created. In 2020, the introduced projects produced products worth 12.5 billion tenge.
|
No. |
Industrial zones |
Land area, ha |
Project cost (billion tenge) |
Workplaces |
Projects |
|||
|
Total |
Mastered |
total |
implemented |
At the stage of implementation |
||||
|
1 |
Kyzylorda city |
366 |
152,5 (41,5%) |
128,8 |
1 101 |
11 |
1 |
10 |
|
2 |
Aral district |
6 |
6,0 (100%) |
1,7 |
135 |
4 |
2 |
2 |
|
3 |
Kazaly district |
6,9 |
4,83 (70%) |
0,172 |
43 |
8 |
6 |
2 |
|
4 |
Karmakshy district |
15 |
4 (26,6%) |
0,143 |
35 |
4 |
1 |
3 |
|
5 |
Zhalagash district |
22 |
13,2 (59%) |
0,758 |
149 |
19 |
8 |
11 |
|
6 |
Shieli district |
96 |
65 (67,7%) |
65,8 |
463 |
10 |
4 |
6 |
|
Total |
511,9 |
245,5 (48%) |
197,2 |
1928 |
56 |
22 |
34 |
|
Information about the current state of Industrial zones of the Kyzylorda region
(January-December)
On the territory of the region there are 6 industrial zones with a total area of 511.9 hectares. To date, 245.5 hectares of land have been developed from the allocated land plots for 56 projects with a total cost of 197.2 billion tenge. About 6.7 billion tenge was allocated from the budget for the construction of infrastructure. Each industrial zone has a developed infrastructure (energy and water supply, natural gas supply, etc.). Out
of 56 projects, 22 projects worth 65.3 billion tenge were implemented, where 349 jobs were created.
In 2020, the introduced projects produced products worth 12.5 billion tenge.
|
No. |
Industrial zones |
Land area, ha |
Project cost (billion tenge) |
Workplaces |
Projects |
|||
|
Total |
Mastered |
total |
implemented |
At the stage of implementation |
||||
|
1 |
Kyzylorda city |
366 |
152,5 (41,5%) |
128,8 |
1 101 |
11 |
1 |
10 |
|
2 |
Aral district |
6 |
6,0 (100%) |
1,7 |
135 |
4 |
2 |
2 |
|
3 |
Kazaly district |
6,9 |
4,83 (70%) |
0,172 |
43 |
8 |
6 |
2 |
|
4 |
Karmakshy district |
15 |
4 (26,6%) |
0,143 |
35 |
4 |
1 |
3 |
|
5 |
Zhalagash district |
22 |
13,2 (59%) |
0,758 |
149 |
19 |
8 |
11 |
|
6 |
Shieli district |
96 |
65 (67,7%) |
65,8 |
463 |
10 |
4 |
6 |
|
Total |
511,9 |
245,5 (48%) |
197,2 |
1928 |
56 |
22 |
34 |
|
Information on the current state of the Industrial zones of Kyzylorda region
(January-July 2020)
There are 6 industrial zones with a total area of 904.9 hectares in the region. To date, from the allocated land plots, 243.5 hectares of land have been developed for 55 projects with a total cost of KZT 197 billion. About KZT 6.7 billion has been allocated from the budget for the construction of infrastructure. Each industrial zone has a well-developed infrastructure (energy and water supply, natural gas supply, etc.).
Out of 55 projects, 21 projects worth KZT 65.3 billion were implemented, where 339 jobs were created.
In 2019, the introduced projects produced products for KZT 9.2 billion, in January-May 2020, products for KZT 782.6 million were produced
In 2019, 5 projects were commissioned for KZT 166 million, with the creation of 14 new places.
|
No. |
Industrial zones |
Land area, ha |
Project cost (billion tenge) |
Workplaces |
Projects |
|||
|
Total |
Mastered |
total |
implemented |
At the stage of implementation |
||||
|
1 |
Kyzylorda city |
760 |
150,5 (19,8%) |
128,6 |
1 101 |
10 |
1 |
9 |
|
2 |
Aral district |
10 |
6,0 (60%) |
1,7 |
135 |
4 |
2 |
2 |
|
3 |
Kazaly district |
6,9 |
4,83 (70%) |
0,172 |
43 |
8 |
5 |
3 |
|
4 |
Karmakshy district |
15 |
4 (26,6%) |
0,143 |
35 |
4 |
1 |
3 |
|
5 |
Zhalagash district |
17 |
13,2 (77,6%) |
0,758 |
149 |
19 |
8 |
11 |
|
6 |
Shieli district |
96 |
65 (67,7%) |
65,8 |
463 |
10 |
4 |
6 |
|
Total |
904,9 |
243,5 (26,9%) |
197 |
1926 |
55 |
21 |
34 |
|
Information on the current state of the Industrial zones of Kyzylorda region
(January-November)
In the region, there are 6 industrial zones with a total area of 909.9 hectares. To date, 216 hectares of land have been developed from allocated land plots for 50 projects with a total value of KZT 193.8 billion. About KZT 6.7 billion were allocated from the budget for the construction of infrastructure. Each industrial zone has developed infrastructure (energy and water supply, natural gas supply, etc.).
Of the 50 projects, 21 projects were implemented worth KZT 65.3 billion, where 346 jobs were created.
Following the results of 11 months of 2019, the introduced projects produced products worth KZT 5.3 billion.
Since the beginning of the year, 5 projects have been introduced for KZT 166 million, with the creation of 14 new places.
|
№ |
Industrial areas |
Land area, ha |
Project cost (billion tenge) |
Workplaces |
Projects |
|||
|
Total |
Mastered |
Total |
Implemented |
Under implementation |
||||
|
1 |
Kyzylorda city |
760 |
125,2 (16,4%) |
126,9 |
1 043 |
10 |
1 |
9 |
|
2 |
Aral district |
10 |
5,0 (50%) |
0,239 |
100 |
3 |
2 |
1 |
|
3 |
Kazaly district |
6,9 |
4,83 (70%) |
0,172 |
24 |
8 |
5 |
3 |
|
4 |
Karmakshy district |
15 |
3,1 (20.6%) |
0,081 |
20 |
2 |
1 |
1 |
|
5 |
Zhalagash district |
22 |
12,7 (57,7%) |
0,648 |
144 |
17 |
8 |
9 |
|
6 |
Shieli district |
96 |
63 (65,6%) |
65.8 |
459 |
10 |
4 |
6 |
|
Total |
909,9 |
213,8 (23.5%) |
193.8 |
1790 |
50 |
21 |
29 |
|