Completed work in the field of transport and roads for the 2st quarter of 2023
On the territory of the Karmakshy region there are motor roads with a total length of 341.05 km. Of them:
139 km - Republican;
42 km - regional;
160.05 km - roads of regional significance.
Funds allocated for road repairs:
In 2023, 503.0 million tenge was allocated from the regional budget to carry out works on the average repair of highways of regional significance "Samara-Shymkent- Akzhar- Turmagambet- Komekbayev". The total cost of the project is 1445.0 thousand tenge. Currently, work is underway with the contractor "Kyzylorda Zholdary" LLP.
In addition, 42,797,000 tenge has been allocated from the district budget for the current repair and maintenance of roads of regional significance, repair work begins with the contractor "Nurlyorda Service" LLP.
Completed work in the field of transport and roads for the 1st quarter of 2023
On the territory of the Karmakshy region there are motor roads with a total length of 341.05 km. Of them:
139 km - Republican;
42 km - regional;
160.05 km - roads of regional significance.
Funds allocated for road repairs:
Completed works in transport and automobile roads for II quarter 2022
In 2023, 503.0 million tenge was allocated from the regional budget for the medium repair of highways of regional significance "Samara-Shymkent" Akzhar, Turmagambet, Komekbaev. The total cost of the project is 1445.0 million tenge. Currently, in order to determine the contracting organization, a public procurement tender is being held. In addition, 42,797.0 thousand tenge was allocated from the regional budget for the maintenance of roads of regional significance.
On the territory of Karmakshinsky district there are automobile roads with a total length of 341.05 km. From NIH:
139 km-Republican;
42 km-regional;
160.05 km-roads of district significance.
Funds allocated for 2022:
capital repair of the Samara-Shymkent-Akzhar-Komekbayev highway is 239,121 thousand. TG.
For the current repair and maintenance of roads of district significance – 39,444.0 thousand tenge.
"In addition to these works, the project estimate documentation is ready for the average repair of 27 km of the road of district significance "Samara - Shymkent - Akzhar - Turmaganbet-Komekbayev" and the reconstruction of the entrance road to the village point of Kyzylorda." 5749.8 thousand tenge was allocated from the district budget.
It is planned to repair 12 streets with a total length of 5.8 km to the village of Zhosaly, and the following streets: esetova Street (0.3 km), Syrdarya Street (0.3 km), Adilova Street (0.285 km), Baizak tag Street (0.15 km), Iztleuova Street (0.43 km), Kobeyeva Street, Shegebayeva Street, Seifullina street (1.26 km), tauelsizdik Street (0.4 km), musirkegenova Street (0.65 km), zhanazarova Street (0.55 km), auezova Street (1.59 km).
Completed works in the field of transport and highways for the first quarter of 2022
Repair of highways:
There are highways with a total length of 335 km on the territory of Karmakshi district . Of these:
139 km-Republican;
42 km-regional;
154.7 km - roads of regional significance.
Funds allocated for 2022:
for the overhaul of the Samara-Shymkent-Akzhar-Komekbayev highway, OB - 239,121 thousand tenge.
For the current repair and maintenance of highways of regional significance – 39 444.0 thousand tenge.
Along with these works, design and estimate documentation is being prepared for the average repair of 27 km of the Samara- Shymkent-Akzhar-Turmaganbet-Komekbayev highway of regional significance and the reconstruction of the access road to the settlement of Kyzyltam.
Road signs.
In order to ensure road safety for 2022, 2605.0 thousand tenge was allocated from the district budget for the maintenance of traffic lights located at 4 intersections in the village of Zhosaly, as well as for laying a pedestrian lane along newly paved streets and along schools in the center of the village of Zhosaly.
In addition, in order to establish other necessary traffic control devices for 2022, together with employees of the district police department, work was carried out to study the necessary road devices in all settlements of the Karmakshinsky district.
In total, the survey determined the need to install 218 pieces of road signs and 66 meters of artificial obstacles in 6 places. In accordance with this, in order to install these road signs and pripyatstvii, estimated documentation has been developed and a budget application has been sent to the district Department of Economics and Budget planning in the amount of 11692.41 thousand tenge.
Completed work in the field of transport and highways at the end of 2021
In 2021, by the decision of the interdepartmental commission, 183755.0 thousand tenge was allocated from the republican budget for the average repair of 7 streets of the Akai rural district of the Karmakshi district within the framework of the Auyl El Besigi project, 20416.0 thousand tenge from the district budget.
On the portal of public procurement, by means of an open tender, the work on the average repair of A. Baitursynov, I. Zhansugurova, Zhenis, K. Satpayev, S. Konysova, Abai streets was won by Nuras and Company LLP, along Balgynbayev Street the dead end of Darenstroyservice LLP. To date, the work has been fully completed
Within the framework of the "Auyl-el besigi" program, 357.575 million tenge was allocated from the republican budget for the average repair of the streets of the village of Toretam, 39.730 million tenge was allocated from the district budget, According to the results of the public procurement competition, Dorstroy LLP was recognized as the winner. The works according to the design and estimate documentation have been fully completed and put into operation.
346523.0 thousand tenge was allocated for the average repair of Abay, Korkyt ata, K. Rustembekov, M. Kudabayeva, D. Myrzagalieva, Zheleznodorozhny streets in the village of Zhosaly with a length of 9.975 km, public procurement activities were carried out by means of a competition, according to the results of which Kyzylorda Zholdary LLP and Abu Zhusup LLP were recognized as winners. To date, the work has been fully completed
Implementation of measures on social and engineering infrastructure in rural settlements within the framework of the Auyl-el Besigi project, 121906.0 thousand tenge was allocated for the average repair of 3 streets of the village of III International (RB-109715.0 thousand tenge, MB-12191.0 thousand tenge).
Based on the results of public procurement
1. The winner of the "average repair of Kashkansu Street" is "Kyzylorda Zholdary" LLP. To date, the work has been fully completed.
2. The winner of the "average repair of Amangeldy Street" is "Kyzylorda Zholdary" LLP. To date, the work has been fully completed.
3. The winner of the "average repair of Bayterek Street" - Construction and Transport Company LLP. To date, work has been carried out on the laying of crushed stone and crushed stone, asphalting, provided for by the estimated documentation.
In 2021, 37.0 million tenge was allocated from the district budget for the current repair and maintenance of highways of Karmakshi district significance. The contracting organization is KazElectroCompany LLP. Work was carried out on mowing the grass of the roadsides and restoring the glades of roads, as well as work on winter maintenance of roads of regional significance.
Completed works in the field of transport and highways for the Third quarter of 2021
In 2021, by the decision of the interdepartmental commission, 183755.0 thousand tenge was allocated from the republican budget for the average repair of 7 streets of the Akai rural district of the Karmakshi district within the framework of the Auyl El Besigi project, 20416.0 thousand tenge from the district budget.
On the public procurement portal, by means of an open tender, the work on the average repair of A. Baitursynov, I. Zhansugurova, Zhenis, K. Satpayev, S. Konysova, Abai streets was won by Nuras and Company LLP, along Balgynbayev Street the dead end of dArensTroysErvice LLP. Currently, contracts have been concluded with these contractors and work is underway.
Within the framework of the "Auyl-el besigi" program, 357.575 million tenge was allocated from the republican budget for the average repair of the streets of the village of Toretam, 39.730 million tenge from the district budget, According to the results of the public procurement competition, Dorstroy LLP was recognized as the winner. According to the design and estimate documentation for the average repair of the streets of the village of Toretam, 67471 sq. m. were paved on 20 streets. m roads.
According to the design and estimate documentation, it is planned to carry out work on asphalting 2588 sq. m. m of the road, installation of road signs, application of road markings, compaction of roadsides.
346523.0 thousand tenge was allocated for the average repair of Abay, Korkyt ata, K. Rustembekov, M. Kudabayeva, D. Myrzagalieva, Zheleznodorozhny streets in the village of Zhosaly with a length of 9.975 km, public procurement events were held by the method of competition, according to the results of which Kyzylorda Zholdary LLP and Abu Zhusup LLP were recognized as winners. Repair work is currently underway.
Implementation of measures on social and engineering infrastructure in rural settlements within the framework of the Auyl-el Besigi project, 121906.0 thousand tenge was allocated for the average repair of 3 streets of the village of III International (RB-109715.0 thousand tenge, MB-12191.0 thousand tenge).
Based on the results of public procurement
The winner of the "average repair of Kashkansu Street" is "Kyzylorda Zholdary" LLP. To date, the work has been fully completed.
the winner of the "average repair of Amangeldy Street" is "Kyzylorda Zholdary" LLP. In connection with the emergence of disagreements on the results of the competition on the part of potential suppliers, a statement of claim was sent to the courts.
The winner of the "average repair of Bayterek Street" is Construction and Transport Company LLP. To date, work has been carried out on the laying of crushed stone and crushed stone, asphalting, provided for by the estimated documentation.
In addition, within the framework of the state program "Nurly Zhol", 239.1 million tenge was allocated from the regional budget for the overhaul of the Samara-sHymkent-aKzhar-Turmaganbet - Komekbayev highway of regional significance. Currently, the design and estimate documentation has been reissued, work is being organized to determine the contractor.
In 2021, 37.0 million tenge was allocated from the district budget for the current repair and maintenance of highways of Karmakshi district significance. The contracting organization is Kazelectrocompany LLP. Work is underway to mow the grass of the roadsides and restore the glades of roads.
Road signs
In order to prevent road safety for 2021, 2481.00 thousand tenge was allocated from the district budget, works were carried out to install road signs in the village of Toretam in the amount of 49 pieces and 12 meters of artificial obstacles in 1 place, 2 road signs and 12 meters of artificial obstacles on Tomanova Street. In the village of Zhosaly
Completed works in the field of transport and highways for the Second quarter of 2021
Repair of highways
357.575 million tenge was allocated from the republican budget for the average repair of 20 streets of the village of Toretam. According to the results of public procurement, Dorstroy LLP was recognized as the winner. To date, the relevant work is being carried out.
For 2021, 204171.0 thousand tenge was allocated for the average repair of A. Baitursynov, Zhansugurov, Zhenis, Konysov, Abay, Balgynbayev's dead end, K. Satpayev's streets of the Akai rural district. Currently, in order to determine the contractor, a tender is being held within the framework of the Law of the Republic of Kazakhstan "On Public Procurement".
346523.0 thousand tenge was allocated for the average repair of Abay, Korkyt ata, Rustembekov, M. Kudabayev, D. Myrzagalieva, Railway streets in the village of Zhosaly. In order to determine the contractor, a tender is held within the framework of the Law of the Republic of Kazakhstan "On Public Procurement".
According to the rural district of the III-International, 121,906.0 thousand tenge was allocated for the average repair of Amangeldy, Baiterek, Kashkans streets. Contractors - "Kyzylorda Zholdary" LLP, "Construction and Transport Company" LLP.
In 2021, 239.1 million tenge was allocated from the regional budget for the overhaul of the Samara-Shymkent-Akzhar-Turmaganbet - Komekbayev highway of regional significance. Currently, work is underway to develop design and estimate documentation.
In this regard, 37.566 million tenge was allocated from the district budget for the current repair and maintenance of highways of regional significance.Contractor organization KazElectroCompany LLP.
Road signs
In order to prevent road safety, 2481.00 thousand tenge was allocated from the district budget for 2021.In accordance with this, the relevant works are being carried out in the village of Toretam to install 59 road signs and 24 meters of artificial obstacles in 2 places.
In addition, for 2021, design and estimate documentation has been developed and a budget application has been submitted to the district department of economics and budget planning in the amount of 5422,800 thousand tenge for the installation of 140 pieces of road signs in the village of Zhosaly, for the installation of 309 pieces of road signs and 84 meters of artificial obstacles on all roads of settlements in the amount of 14862,414 thousand tenge, for marking 876 meters of the pedestrian crossing strip on the central streets of the village of Zhosaly in the amount of 960,744 thousand tenge.
At the same time, a budget application was submitted for the allocation of funds from the district budget in the amount of 10488,022 thousand tenge for the installation of road signs, transport and pedestrian traffic lights with a time counter indicator at the intersection of the streets of the village of Zhosaly Karmakshi district.
Passenger transportation:
On April 19, 2021, a competition was again announced for the right to service routes for regular intra-district (intra-village) transportation of passengers and luggage. However, the tender was declared invalid due to the fact that no applications were received from any carrier for a repeat tender.
Currently, a competition has been re-announced for the right to service routes for regular intra-district (intra-village) transportation of passengers and luggage. Prior to determining the winner of the announced competition, in order to coordinate passenger transportation in the Karmaksha district, IP "Dinara" for "intra - village direction No. 1 Zhosaly" and "Auyl Dur Ongar-Zhosaly settlement" and IP "Maksat" on the route "auyl Komekbayev-posselok Zhosaly" were issued temporary certificates for the right to service routes of regular intra-district (intra-village) transportation of passengers and luggage.
Explanatory work was carried out with car owners engaged in taxi services about the provision of services through a single control room, as well as more than 30 car owners engaged in taxi services, the requirements for taxi services were explained and relevant memos and comments were distributed.
From June 01 to 03, 2021, together with the representative office of the Ministry of Internal Affairs of the Republic of Kazakhstan in the city of Baikonur, as well as with the akimats of the village of Toretam and the aul district of Akai, studies of spontaneous (illegal) taxi stands in the village of Toretam and in the Akai aul district were conducted.
Completed works in the field of transport and highways for the FISRT quarter of 2021
Road repairs
The Republican budget allocated 357.575 million tenge for the average repair of 20 streets of Toretam village. To date, based on the results of public procurement, Dorstroy LLP has been recognized as the winner.
In addition, the state institution "Kyzylorda regional Department of passenger transport and highways" for 2021 presented the following projects: works on the current repair of 42 streets of the village of Zhosaly-146,752. 89 thousand tenge, for the average repair of 3 streets of the aul district of Akay-120,542. 0 thousand tenge, as well as budget applications were submitted under the Auyl-El besigi program for the following works::
|
Project name |
Cost, thousand tenge |
|
Medium repair of streets of Aldashbay Akhun aul district, Karmakshy district, Kyzylorda region |
86558,985 Republic of Belarus 2021j |
|
Installation of traffic control devices on the streets of all settlements of Karmakshy district, Kyzylorda region |
14862,414 AB 2021j |
|
Current repair of Tupboget street in Aldashbay Akhun aul district, Karmakshy district, Kyzylorda region. |
22579,738 Republic of Belarus 2021j |
|
Medium repair of streets of Karmakshy aul district, Karmakshy district, Kyzylorda region |
58112,56 Republic of Belarus 2021j |
|
Medium repair of streets of Kyzyltam settlement, Karmakshy district, Kyzylorda region |
104746,334 Republic of Belarus 2021j |
|
Current repair of Eskizhyluan street in the settlement of Kyzyltam, Karmakshy district, Kyzylorda region |
19796,603 Republic of Belarus 2021j |
|
Medium repair of streets in Torebay bi village, Karmakshy district, Kyzylorda region |
71538,859 Republic of Belarus 2021j |
|
Medium repair of streets of Aktobe aul district, Karmakshy district, Kyzylorda region |
92341,467 Republic of Belarus 2021j |
For 2021, 239.1 million tenge was allocated from the regional budget for the full completion of major repairs of 8.3 km of the Samara-Shymkent-Akzhar-Komekbayev regional highway.
In this regard, 37.566 million tenge was allocated from the district budget for the current repair and maintenance of roads of regional significance. To date, an estimated calculation has been developed and in April this year it is planned to hold public procurement competitions in order to determine the contractor.
Road signs
In order to prevent road safety in 2021, 2481.00 thousand tenge was allocated from the district budget.In accordance with this, 59 road signs and 24 meters of artificial obstacles are being installed in 2 places in the village of Toretam.
In addition, for 2021, design and estimate documentation was developed and a budget application was submitted to the district Department of economy and budget planning in the amount of 5422,800 thousand tenge for the installation of 140 pieces of road signs in the village of Zhosaly, for the installation of 309 pieces of road signs and 84 meters of artificial obstacles on all roads of settlements in the amount of 14862,414 thousand tenge, for marking 876 meters of the pedestrian crossing strip on the Central streets of the Village of Zhosaly in the amount of 960,744 thousand tenge.
At the same time, a budget application was submitted for the allocation of funds from the district budget in the amount of 10488,022 thousand tenge for the installation of road signs, transport and pedestrian traffic lights with a time counter indicator at the intersection of Zhosaly village streets of Karmakshy district.
Completed work in the field of transport and highways at the end of 2020
Repair of roads and streets:
In 2020, 34,074.0 thousand tenge was allocated from the district budget for the current repair and maintenance of highways of regional significance. In the course of these works, 2,977 m2 of roads have reached satisfactory condition thanks to patching. Currently, the contracting organization LLP "Bauyrzhan Kurylys" prepared 176 tons of sand with an admixture of salt for road sprinkling.
State Institution "Kyzylorda Regional Administration of Passenger Transport and Highways" for 2021 presents the following projects:
Repair of streets in the village of Toretam - 397304,524 thousand tenge;
Works on the current repair of the regional highway "Zhalagash-Zhosaly-Maral Ishan" - 99 237.2 thousand tenge;
363.71 thousand tenge for medium repair of 7 streets of the village of Toretam-118;
For medium repair of 3 streets of the Akai-120 village district 542.44 thousand tenge;
Works on current repair of 42 streets of Zhosaly village - 146 752.89 thousand tenge;
In 2021, 397 304, 524 thousand tenge were allocated for the average repair of the streets of the village of Toretam within the framework of the "Auyl - el besigі" program.
By road signs:
In 2020, 55 signs were installed in the village of Zhosaly in order to prevent road safety and 24 meters of artificial road obstacles were laid. These road signs and obstacles are installed in front of educational institutions.
In addition, in order to install other necessary road devices, funds were allocated from the district budget and work was carried out to arrange 26 automobiles in 4 places at street intersections and 12 pedestrian traffic lights, as well as 60 road signs were installed and 454 meters of pedestrian crossings in the village were marked. In addition, 31 road signs and 12 meters of artificial obstacles were installed in the village of Toretam.
Completed works in the field of transport and highways for the THIRD quarter of 2020
Road and street repairs
In 2020, 284805.0 thousand tenge was allocated for the following works in Karmakshy district. The average fixation 4-the streets of the village of Toretam length of 4.95 km 122126,1 thousand tenge on average repair of the street "Ali Bekibaev" in the aul district Zhanazhol with the length of 2 km - 17 137,0 thousand tenge on average repair of streets of the "Kazakh" in the aul district III-international length of 1.62 km - 35 992,0 thousand tenge on average repair of the street named after A. Imanov in aulnoy district of Aktobe, 1.8 km - 30 131,4 thousand for the average repair on M. Mametova street in Akzhar village, 0.85 km long - 21915.3 thousand tenge, for the average repair and lighting of Begim bi street, Sarbasuly in the settlement of Turmagambet, 1.4 km long-36,808. 2 thousand tenge, for the average repair of Mailyozek street in the aul district of Aldashbay Akhun, 0.8 km long-20695.0 thousand tenge. At the same time, in 2020, 34074.0 thousand tenge was allocated from the district budget for the current repair and maintenance of roads of regional significance. In the course of this work, it is planned to make a pit repair of 2977 m2 to restore the roads to a satisfactory condition. According to the results of public procurement, the winner of the competition was "Bauyrzhan Kurylys Company" LLP. Currently, pit work is underway.
By road signs:
In February of this year, together with employees of the office of the mayor of the village of Zhosaly and the district police Department, work was carried out to study the need to install road signs. As a result of this work, 55 signs will be installed and 24 meters of artificial road obstacles will be laid. Based on the results of the public procurement competition, a contract was signed with the contractor to carry out the above-mentioned works. Currently, the installation of road signs and artificial road barriers has been completed.
In January-February of this year, 175.68 tons of sand and salt in the amount of 3839.7 thousand tenge were sown on 14,640 square meters of roads in localities to ensure traffic safety during ice on roads of regional significance due to inclement weather.
For the replacement of obsolete and installation of new modern lights on Perekrestok streets "Bali Bazaar" and "Streuhof" in the village7279.0 thousand tenge was allocated from the district budget of Zhosaly. Following the results of the public procurement competition, an agreement was signed with the contractor Bagdarsham Service LLP to carry out the above-mentioned works. At the moment, all work on replacing the old and installing new traffic lights has been completed.
In addition, the district budget allocated 721.0 thousand tenge for the construction of a pedestrian lane with a length of 0.454 km on 34 streets of the village of Zhosaly in order to prevent the danger of pedestrians crossing the road. Based on the results of the public procurement competition, a contract was signed with the contractor to carry out the above-mentioned works. Currently, the construction of the pedestrian lane has been completed.
The Department of housing and communal services of passenger transport and highways of the Karmakshynsky district, together with employees of the administration of akimats of settlements, aul districts, as well as representatives of the district police Department, conducted work to study the need to install road signs in settlements and aul districts of the Karmakshynsky district. In the result, we prepared documentation and submitted budget request to the regional Department of economy and budget planning on the installation of road signs 369, 36 meters of artificial roadblocks in the amount of 13735,0 thousand tenge in the village of Zhosaly, the installation of road signs 49 and 60 meters (in 5 places) artificial roadblocks to the amount of 3247,0 in the village of Toretam and 309 traffic signs and 84 meters of artificial roadblocks in the amount of tenge 13304,0 in the rural districts of the Karmakshy region.
7.0 million tenge was allocated from the district budget for the construction of road signs in the village of Zhosaly. Due to the reduction of the district budget, 5.0 million tenge was returned to the budget, and the remaining 2.0 million tenge will be spent on the installation of 60 road signs that are of great importance today.At the moment, work is underway to determine the contractor. In addition, 2000,0 thousand tenge was returned to the budget out of 3247,0 thousand tenge allocated from the district budget for the construction of road structures in the village of Toretam. For the remaining 1247,0 thousand. the main contractor "IP Aitzhanov" is working on the installation of 31 road signs and 12 meters of artificial road signs in the village of Toretam .
Completed works in the field of transport and highways for the SECOND quarter of 2020
Road and street repairs
In 2020, 284,805,0 thousand rubles were allocated for the following works in Karmakshy district. Tenge. For the average repair of 4 streets of Toretam village with a length of 4.95 km - 122,126. 1 thousand tenge. For the average repair of the "Kali Beksebayeva" street in the Zhanazhol aul district with a length of 2 km - 17,137. 0 thousand tenge. For the average repair of "Kazak" street in the aul district III-international with a length of 1.62 km - 35,992. 0 thousand tenge; for the average repair of A. Imanov street in the aul district of Aktobe, 1.8 km - 30,131. 4 thousand tenge. On the middle building on the street of M. Mametova in the village of Akzhar, a length of 0.85 km 21915,3 thousand tenge. For the average repair and lighting of Begim bi street, Sarbasuly in the village of Turmagambet with a length of 1.4 km - 36,808. 2 thousand tenge. For the average repair of Mailyozek street in the aul district of Aldashbay Akhun with a length of 0.8 km - 20695.0 thousand tenge; Along with this, in 2020, 34074.0 thousand tenge was allocated from the district budget for the current repair and maintenance of roads of regional significance. In the course of this work, it is planned to make a pit repair of 2977 m2 to restore the roads to a satisfactory condition. Currently, a public procurement competition has been announced.
By road signs:
In February of this year, together with employees of the office of the mayor of the village of Zhosaly and the district police Department, work was carried out to study the need to install traffic signs and as a result of this work, 55 signs will be installed and 24 meters of artificial road obstacles will be laid. Based on the results of the public procurement competition, a contract was signed with the contractor to carry out the above-mentioned works. Currently, the installation of road signs and artificial road barriers has been completed.
For the replacement of obsolete and installation of new modern lights on Perekrestok streets "Bali Bazaar" and "Streuhof" in the village7279.0 thousand tenge was allocated from the district budget of Zhosaly. Based on the results of the public procurement competition, a contract was signed with the contractor to carry out the above-mentioned works. In addition, the district budget allocated 721.0 thousand tenge for the construction of a pedestrian lane with a length of 0.454 km on 34 streets of the village of Zhosaly in order to prevent the danger of pedestrians crossing the road. Currently, public procurement procedures are carried out within the framework of the Law of the Republic of Kazakhstan "on public procurement".
At the same time, the district budget allocated 2 million tenge for the installation of 60 road signs in the village of Zhosaly and 1247.0 thousand tenge for the installation of 31 road signs and 12 meters of artificial obstacles in the village of Toretam. Currently, a public procurement competition has been announced.
Completed works in the field of transport and highways for the First quarter of 2020
Road and street repairs
In 2020, 34074.0 thousand tenge was allocated from the district budget for the current repair and maintenance of roads of regional significance. Currently, the types and scope of repairs are being clarified.
The installation of traffic signs
In 2020, in order to ensure road safety and install the necessary road signs, 2481.0 thousand tenge was allocated from the district budget. First of all, it is planned to use these funds to install traffic signs at the locations of educational institutions in the village.Zhosaly. To do this, together with employees of the office of the mayor of the village.Zhosaly and the district police Department have carried out work to study the need to install traffic signs and as a result of this work, 55 signs will be installed and 24 meters of artificial road obstacles will be laid. Based on the results of the public procurement competition, a contract was signed with the contractor to carry out the above-mentioned works.
Due to the sharp deterioration of weather conditions in January and February of this year, 175.68 tons of special anti-ice mixture were sprinkled on the road sections of district significance with an area of 14640.0 square meters allocated from the budget to ensure traffic safety during icy conditions.
To replace outdated and install new modern traffic lights at the intersections of the village streets.7279.0 thousand tenge was allocated from the district budget of Zhosaly. Currently, work is underway to organize a public procurement competition.
At the same time, the district Department of economy and budget planning was sent a budget application for the allocation of funds in the amount of 721.0 thousand tenge for painting the markings of pedestrian crossings on 34 streets of the village.Zhosaly with a total length of 0.454 km.
As a result of the joint work of the Department with the offices of the akims of aul and village akims and the district police Department, it was established that it was necessary to install additional equipment that regulates traffic, namely: in the village.Zhosaly – 369 signs and 36 meters of artificial road obstacles; in the village.Toretam – 49 signs and 60 meters of artificial road obstacles; in other aul districts-309 signs and 84 meters of artificial road obstacles. To allocate funds for these works, a budget application for the total amount of 30286.0 thousand tenge was sent to the district Department of economy and budget planning.
Passenger transportation:
In the aul districts of Komekbayev, Kuandariya, Aldashbay Akhun, Dauylkol, Akzhar, Zhanazhol, III-international, buses and minibuses run 1 time a day, and IP "a" organizes passenger transportation in these directions.Zhumabekova", and residents of the aul districts of Aktobe, Torebay bi, and Irkol get to the district center and back by cars, the owners of which are engaged in private transportation. Residents of Karmakshy aul district use the route "Zhalagash-Zhosaly" 2 times a day.
To organize passenger transportation on intra-village routes #1 and #2 in the village.Zhosaly, LLP "Transport service ABOUR" issued a temporary license for a period of 2 months.
List of entrepreneurs engaged in passenger transportation on intra-district routes:
Completed works in the field of transport and highways by the end of 2019
About highways and streets: In 2019, 32.4 million tenge was allocated from the regional budget for the object "for the average repair of tekey Batyr street in the rural district of Turmagambet, Karmakshy district", and a public procurement competition was held. According to the results of the competition, the contractor Inc-AI LLP was identified as the winner. Asphalt is currently being laid.
In 2019, 34,074 million tenge was allocated from the district budget for the current repair and maintenance of roads of regional significance. These funds are used to restore roads, mow grass along roads, and maintain roads in winter. Contractor "Karmakshy Zholdary" LLP. To date, the contractor has completed all pit works on the highway between the villages of Akzhar and Turmaganbet.
In 2019, the regional budget allocated 22.8 million tenge for major repairs of the Samara-Shymkent-Akzhar-Komekbayev highway. Contractor "Kyran" repaired 0.5 km of the highway "Samara-Shymkent-Akzhar-Turmaganbet-Komekbayev".
As part of the program implementation of measures for social and engineering infrastructure in rural localities "Auyl-El besigi" in Karmakshy district in 2019, 283076.0 and 31453.0 thousand tenge were allocated from the Republican and local budgets for the average repair of streets in the village of Zhosaly, respectively. For these funds, the total amount of 314529.0 thousand tenge, the average repair of streets for a total length of 13.65 km was made. To date, the contractor "Kyzylorda Zholdary" LLP has completed all work. In addition, 13,886 thousand tenge was allocated from the district budget for the current repair of Temirzhol street in the village of Zhosaly. To date, the winner of "Nurlyorda Service" LLP is working on leveling the road and laying sand. The completion date is scheduled for 03.11.2019. In addition, 7500.0 thousand tenge was allocated for the demolition of the old part of the Shymkent-Samara highway at the expense of the own funds of the mayor's office of the village of Zhosaly (from the budget of the 4th level). The asphalt sand and gravel stone of the old road is planned to be laid on the streets in the center of the village of Zhosaly. At the moment the contractor LLP "Karmakshy literature" carries out the relevant work.
Completed works in the field of transport and highways for the SECOND quarter of 2019
About highways and streets: In 2019, 34,074 million tenge was allocated for the current repair and maintenance of roads of regional significance at the expense of the district budget. These funds will be used to restore roadsides, mow grass along roads and maintain roads in winter.
In 2019, 22.8 million tenge was allocated from the regional budget for major repairs of the Samara-Shymkent-Akzhar-Komekbayev regional highway. Work will continue with the allocated amounts of funds.
By road signs: For 2019, the regional budget allocated 77.0 thousand tenge, it is planned to install 2 road signs for citizens with disabilities. In addition, in order to prevent road accidents in 2019, 2363.00 thousand tenge was allocated from the district budget. Currently, 77 road signs and 12 meters of artificial road surfaces have been installed from the Yerzat Contracting company.
By passenger transport: The district has 2 villages of 12 rural districts, in 7 localities passengers are transported by special vehicles (Komekbayev, Kuandariya, Aldashbay Akhun, Turmaganbet, Akzhar, III-international, Zhanazhol) and in 3 localities (Aktobe, Irkol, Torebay bi). Passenger transportation is carried out in the settlements of Karmakshy and Kyzyltam on the route "Zhalagash-Zhosaly" and "Zhosaly-Kyzyltam-Kyzylorda". Minibuses on route 1 in the village of Zhosaly transport residents covering the territory of the village. A new Dostyk bus station was built in the district center in 2016, the fare was calculated for the district, the unified fare was approved by the resolution of the district akimat No. 314 of 23.08.2016, and after conducting explanatory work with entrepreneurs of the district, a competition for cargo and baggage transportation was announced on 10.10.2017 (held on 22.09.2016 and 03.04.2017). However, due to the fact that the documents of all potential service providers did not meet the requirements of the competition documentation, the competition was not held. In this regard, a temporary certificate of IP "a" was issued for routes No. 1, No. 2 and routes to localities.Zhumabekova" for transportation of passengers and Luggage through the Dostyk bus station.