Gasification report for the IV quarter of 2020
In 2020, 4.9 billion tenge (4,911.8 million tenge) was allocated for the implementation of 10 gas supply projects. Including: the republican budget of 3.5 billion tenge (3,473. 5 million tenge), the regional budget - 975.9 million tenge, the "Employment Roadmap" - 462.4 million tenge. Of these:
- Within the framework of the "Employment Roadmap" program, the following projects were implemented:
3 gas supply projects. Including: Muratbayev village of Kazalinsky district, Baisyn village of Shieli district, gas supply of non-gasified streets of Aralsk city of Aral district.
- At the expense of the republican and regional budgets, the implementation has been completed
3 projects (Zhaksykylysh settlement of the Aral district, Terenozek of the Syrdarya district, non-gasified streets of the village).Zhanakorgan district, Zhanakorgan), 4 projects (p. Zhosaly district, Karmakshy, Zhalagash Zhalagash district, the city of Kazalinsk Kazalinsk district, S. Bekezhanov Shieli district) passing for 2021.
As a result of the work carried out, 256.9 km of the gas pipeline was laid, more than
20 thousand residents of the region were able to use natural gas and the share of the gasified population was increased to 65%.
Gasification report for the III quarter of 2020
Today, the share of the population with access to natural gas is 63%.
Starting from 2019, gas supply projects are being implemented for 3 district centers (Zhosaly, Zhalagash, Terenozek) and the village of Zhaksykylysh in the Aral region. The total cost is 9,365. 8 million tenge. Including: the Republican budget - 8,429. 2 million tenge, the regional budget-936.6 million tenge.
For 2020, 4,577.9 million tenge was allocated for the implementation of these projects. Including: the Republican budget - 3,753. 6 million tenge, the regional budget-824.3 million tenge. As of today, 3,689. 5 million tenge or 80.6% has been disbursed.
In the first half of the year, the gas supply project for the village of Zhaksykylysh in the Aral region was completed. More than 5 thousand residents of the village were able to use natural gas.
For the remaining 3 projects, construction and installation works are carried out according to the approved work schedules.
At the same time, the regional budget allocated 70.4 million tenge to complete the project of gas supply to non-gasified streets of Zhanakorgan village. The facility has been put into operation.
91 million tenge was allocated from the regional budget for the development of gas supply projects in Toretam and Akay settlements of karmakshi district. Currently, design and estimate documentation is being developed.
As part of the employment Roadmap 2020, gas supply projects are being implemented for muratbayev locality in kazalinsky district, Baisyn locality in Shieli district,and gas supply for non-gasified streets in Aralsk. The total cost is 488.1 million tenge.
According to the "business Roadmap" program, 50 million tenge was allocated from the regional budget for the project gasification of the soda ash plant of aralsoda LLP, and work is underway.
Gasification report for the first half of 2020
Today, the share of the population with access to natural gas is 63%.
Starting from 2019, gas supply projects are being implemented for 3 district centers (Zhosaly, Zhalagash, Terenozek) and the village of Zhaksykylysh in the Aral region. The total cost is 9,365. 8 million tenge. Including: the Republican budget - 8,429. 2 million tenge, the regional budget-936.6 million tenge.
For 2020, 4,577.9 million tenge was allocated for the implementation of these projects. Including: the Republican budget - 3,753. 6 million tenge, the regional budget-824.3 million tenge. As of today, 2,511 million tenge or 54.8% has been disbursed.
In the first half of the year, the gas supply project for the village of Zhaksykylysh in the Aral region was completed. More than 5 thousand residents of the village were able to use natural gas.
For the remaining 3 projects, construction and installation works are carried out according to the approved work schedules.
At the same time, the regional budget allocated 70.4 million tenge to complete the project of gas supply to non-gasified streets of Zhanakorgan village. The facility has been put into operation.
91 million tenge was allocated from the regional budget for the development of gas supply projects in Toretam and Akay settlements of karmakshi district. Currently, design and estimate documentation is being developed.
As part of the employment Roadmap 2020, gas supply projects are being implemented for muratbayev locality in kazalinsky district, Baisyn locality in Shieli district,and gas supply for non-gasified streets in Aralsk. The total cost is 488.1 million tenge.
Gasification report for the I quarter of 2020
In 2020, for the completion of the gasification project in 4 localities (Zhosaly, Zhalagash, Terenozek, Zhaksykylysh), 5,304,346 thousand tenge was allocated from the national budget and 551,985 thousand tenge from the regional budget, a total of 5,856,331 thousand tenge.
Currently, 65-70% of construction and installation works have been completed. 85.5 km of gas pipelines have been built, which means that 27% of the allocated funds have been used. Construction of the projects will be completed in 2020.
"Construction of intra-block gas distribution networks in the village of Zhanakorgan of Zhanakorgan district" 7044 thousand tenge was allocated from the regional budget, currently construction and installation works are being completed. The completion date is may of this year.
90,985 thousand tenge was allocated from the regional budget for the development of design and estimate documentation for the construction of intra-block gas pipelines in the localities of Toretam and Akay, and for obtaining a positive conclusion of the state expertise. Currently, the results of the public procurement competition are being processed in court.
About the work done for 12 months 2019
For 2019 allocated from the Republican budget 4 349 556 thousand KZT.Including: 1 174.6 million tenge for the completion of 2 projects ("Construction of gas distribution networks on the left Bank of the Syrdarya river in the city of Kyzylorda" and "Construction of a gas pipeline branch from the Beineu-Shymkent main gas pipeline with the installation of AGRs in the village of Terenuzyak"), 3174.9 million tenge for the start of the gasification project in 4 localities (Zhosaly, Zhalagash, Terenozek, Zhaksykylysh).
In addition, 208.8 million tenge was allocated from the regional budget for co-financing. The following work was carried out on the projects:
1. Under the project " Construction of gas distribution networks on the left Bank of the Syrdarya river in the city of Kyzylorda "(stage 1-1.2 MPa high-pressure gas supply pipeline from AGRs-1 with the installation of GGRP-2) " construction and installation works are fully completed. The facility was commissioned in August 2019.
2. construction works have been completed Under the project "construction of a gas pipeline-branch from the Beineu-Shymkent main gas pipeline with the installation of AGRs in the village of Terenuzyak". The object was accepted by the act of state acceptance on September 25, 2019.
3. gasification works have been Started in 4 localities (Zhosaly, Zhalagash, Terenozek, Zhaksykylysh), and 50-55% of construction and installation works have been completed. Currently, 184.2 km of gas pipelines have been welded and 6 hydraulic fracturing units and 3 SHR units have been installed.Construction of the projects will be completed in 2020.
4.in 2019, 139.9 million tenge was allocated from the regional budget for the project "gas pipeline supply To residential buildings in the village of Ayteke bi of kazalinsky district". According to the project, construction and installation works were carried out, 7.8 km of gas pipelines were built, 2 units were installed.CURRENTLY, the object is fully completed and put into operation.
5. The project" Construction of intra-distribution networks in Zhanakorgan village, Zhanakorgan region ", the regional budget allocated KZT 88,2 million spent 9.7 km of gas pipelines, installed 1 unit SHRP
6.The development of design and estimate documentation and obtaining a conclusion of state examination of the project "Gas supply of the town of Kazaly Kazaly area" from the regional budget allocated 13.9 million tenge, at present, the project received a positive conclusion of state expertise.