Pavlodar Stadium: A Story of sport complex and lost money

A modern stadium for national sports was to be built in Pavlodar which would become the pride of the city and a center of attraction for athletes and residents But the project turned into a story about lost millions an unscrupulous contractorand violations of the law The construction of the stadium for national sports in the Shcherbaktinsky Bridge area started with a budget of 261.5 million tenge but by completion the cost of the project had increased to 666.3 million tenge more than two and a half times However, the stadium was never completed

 

The contractor, Gradstroyservice LLP systematically missed deadlines and in May 2025, the contract with him was terminated An audit conducted by the Department of Internal State Audit for the Pavlodar region in June 2025 revealed serious financial irregularities 589.8 million tenge was transferred to the contractor although according to the documentsonly 555.3 million tenge worth of work was completed 34.5 million tenge was overpaid that isbudget money was gone but there was no result

 

When checking at the facility, it turned out that another 28.3 million tenge was paid for work that does not actually exist thus 28.3 million tenge was spent on unjustified payments In the amount of 62.8 million tenge of the budget, the expediency and legality of their spending were questioned as part of the funds were overpaid to the contractor and part was paid for work that actually did not exist But the story is not just about money In 2024work continued at the facility although the notice of commencement of construction and installation work expired in December 2023

 

The notification of the resumption of work was not sent to the state architectural and construction control bodies In addition the customer did not apply to the court in time to recognize the contractor as an unscrupulous participant in public procurement for which the head of the institution was brought to administrative responsibility and fined

 

Today, Gradstroyservice LLP has been declared bankrupt The revealed 62.8 million tenge is included in the company's debt to the state and is subject to recovery as part of the bankruptcy procedure

Дата публикации
23 февраля 2026
Дата обновления
24 февраля 2026
Тип
Analytics

Сейчас читают

20 октября 2026
Monitoring the timeliness of filing by employees and their spouses
20 октября 2026
Outcomes of audit activities in the health sector
Analytics
15 октября 2026
Итоги деятельности Департамента внутреннего государственного аудита по Жамбылской области за 9 месяцев 2026 года

Социальные медиа

Меню подвал

State of the Nation Address of the President of Kazakhstan
Website of the President of Kazakhstan
Website of the Prime Minister of Kazakhstan
Digital transformation concept
Life situations
National symbols
Terms and explanations
Central communications service under the President of the RK
Screen Reader
Құпиялылық саясаты