In the region, systematic work is being done to provide the population with high-quality drinking water. So at the beginning of 2020, out of 520 rural settlements, 174 villages or 33.5% were provided with centralized water supply, and 61.7% of the population. In 2019, under the State program “Development of regions until 2020”, 9.8 billion tenge were allocated from the republican and local budgets for the implementation of 31 projects on urban and rural water supply and sanitation (25 water supply projects, 6 water disposal projects).
Of these, 11 facilities were commissioned in 2019, as a result, 4 villages (5.3 thousand people, the village of Novoilinovka, Taranovsky district, the village of Zlatoust, Sarykolsky district, the village of Zabelovka, Zhitikarinsky district, and the village) were first connected to the centralized water supply system. Eastern Arkalyk city), improved water supply for 6 villages (21.4 thousand people, Denisovka and Nekrasovka villages of the Denisovsky district, the village of Chelgashi of the Karasu district, the villages of Amangeldy and Esir of Amangeldy district, Torgay of the Dzhangeldy district) and sanitation in Lisakovsk ( 40.2 thousand people) and Oktyabrsky (4.1 thousand people), for the remaining 20 projects, work will continue in 2020.
By the end of 2019, access to centralized water supply for the rural population increased from 59.5% to 61.7%, for villages from 31.4% to 33.5%.
As part of the implementation of the Nurly Zhol State Program, in 2019 the implementation of 1 heat supply project (Lisakovsk) began, at the expense of a budget loan. The project provides for the construction of 2 block-modular boiler rooms with a capacity of 2 MW and 7 MW with the reconstruction of heating networks with a length of 4.8 km. The facility is rolling over to 2020. At the beginning of the project in 2019, 111.9 million tenge were allocated and disbursed. For 2020, 662.5 million tenge are provided for the completion of work.
As part of the Regional Development Program until 2020 for heat supply in 2019, 2 facilities for a total amount of 452 million tenge were commissioned in Lisakovsk. Within the framework of the projects, 1.4 km of heating networks were reconstructed and the quality of heat supply to 5 thousand people was improved.
In order to leave the Arkalyk CHP from burning fuel oil for coal, as well as to increase its efficiency, a feasibility study and design estimates were developed in 2019 “Reconstruction of the heat supply system of the city of Arkalyk until 2030”, which received positive conclusions from the state examination. The total cost of the project amounted to 8.7 billion tenge. The project provides for the construction of a new boiler house with the installation of 3 steam and 2 hot water boilers operating on coal fuel in the territory of the existing thermal power plant.
At the end of 2019, the gasification level of the population of the region amounted to 56% (49.6% in Kazakhstan).
In 2019, 2.6 billion tenge (RB-1.3 billion tenge) was allocated for the implementation of 8 projects. Three facilities were commissioned (for the first time, the village of Nekrasovka was gasified - 614 people, the third stage of the village of Denisovka - 1400 people, the unreached part of the village of Pereleski of the Denisovsky district - 390 people and the unreached part of the village of Silantyevka, Altynsarinsky district - 584 people were gasified).
The implementation of 5 facilities will continue in 2020 (completion of gasification of the village of Auliekol - 11 thousand people and the village of Fedorovka - 2.6 thousand people, the commissioning of which is planned for 2020 and the construction of high-pressure gas pipelines to the village of Altynsarino with connection the villages of Adaevka and Bestobe of the Kamystinsky district (60 km), to the village of Kushmurun with the connection of the village of Chernigovka, Auliekolsky district (46 km) and to the villages of Sheminovka and Ozernoye of the Kostanai district (28 km), the commissioning of which is planned for 2021).
In 2020, it is planned to develop 3 projects (Construction of gas distribution networks in the village of Kushmurun, Auliekolsky district; Construction of gas distribution networks in the village of Altynsarino, Kamystinsky district; Construction of a gas supply pipeline from the village of Auliekol to the village of Dievka).