Preparing for the upcoming heating season

Preparing for the upcoming heating season

Due to the increase in the average daily outdoor air temperature above +10, the heating season in Balkhash, village, has been completed Since April 17, 2019. Sayak and MKR.Konyrat.

In accordance with the approved action plan, work is underway in the city and surrounding villages in accordance with the schedule to prepare heat and power facilities, boiler houses, residential buildings and social and cultural life objects for the upcoming heating season.

Completion of repair works according to the schedule at the reporting date is 40%.

The CHP plant:

This year, in preparation for the heating season, major repairs of boiler unit No. 6, extended maintenance of boiler unit No. 8 and turbine unit No. 3, current repairs of boilers No. 7, 9, turbine units No. 2, No. 6, and No. 7 were carried out. At present, St. # 6. major repairs of the boiler unit are completed, 100% completed. St. # 7 on the reporting date will be carried out on the current repair of the boiler unit. The total amount of repair work at the Balkhash thermal power station amounted to 1 291 million U.S. dollars.tenge.

Repair of the main equipment of the Balkhash CHPP is carried out in accordance with the approved schedule.

CSE "Trilaterals" »:

In preparation for the 2020-2021 heating season, 117.8 million us dollars were allocated. 5.46 km of main (3.89 km) and quarterly (1.48 km) heating networks are planned to be overhauled.

To date, 61.36% of heating networks are being overhauled (20.27% of main networks, 76.63% of quarterly networks). Plan for insulation of thermal networks MSE "su Zhylu TRANS" 8300 m2.

In addition, this year the regional budget allocated 172 million tenge for the repair of heating networks. also, 350 million tenge was allocated from the local budget. tenge, where work is being carried out to replace emergency sections of the city's heating networks with a total length of 13 km.

W / aoaroot.

The total length of the networks is 18 km.).

Sayak Village.

The total length of the networks is 16.1 km.).

4 units of TOM-1 boilers were also purchased for the amount of 42,130 thousand tenge. In 2020, we plan to combine modular boiler houses into three facilities at su Zhylu TRANS. In particular, it is planned to combine modules 1 and 2 in the first place, modules 3 and 4 in the second, and modules 5 and 6 in the third. According to the results of enterprises will be reduced transport costs for enterprises (supply of coal, removal of slag), the number of staff to 10 employees, electricity, etc. Konyrat and Sayak villages.

KGP "Balkhashenergo".

Power transmission is performed in normal mode. The city has a stable electricity supply.

In accordance with the approved measures to prepare for the heating season 2020 - 2021, 97.928 million us dollars were spent.547 km of cable and overhead power lines in the amount of 5, 547 million tenge.

To date, 2,930 km of cable transmission lines have been repaired, which is 53%.

KGP "Balassa":

Today the cold water supply is in normal mode.

The water level in the reservoirs is the following level: Balkhash - 5.60 M, MD. Konyrat-4.1 m., village Sayak-of 1.89 m.

In preparation for the heating season 2019-2020, it is planned to repair 10.04 km of water supply networks for a total of 137,565. 5 thousand tenge.and 1.46 km of sewer networks for the amount of 32.5 thousand tenge.

To date, works have been performed to replace water supply networks with a total length of 0.87 km, which is 8.5%, and works have also been performed to replace sewer networks with a length of 122 M (1-2, 8 Marta street), which is 8.4%.

Work continues on closing closed sewer and water wells in an open and non-standard way, as of 30.06.2020 – 23 wells were closed.

housing:

Preparatory work is underway to prepare residential buildings for the upcoming heating season.

In General, the city is preparing residential buildings on schedule.

According to the schedule of preparation and delivery of houses for acts of readiness for the heating season 2020-2021, KSK 30.06.2020 should prepare and receive acts of readiness for 232 houses. In the KGP "su Zhylu TRANS" for 160 houses, an application from the KSK was submitted. Of these, 158 homes were reviewed and reviewed. During the inspection and review, comments were identified, and an order for Troubleshooting was issued.

At the end of the school year, educational institutions are planning to start preparations for the heating season 2020-2021. To date, 13 educational facilities have received 100% certificates of readiness for the heating season.

It is planned to purchase 90 tons of coal for educational and cultural facilities in Gulshat village in August this year.