Construction

SI "Temir district Department of architecture, urban planning and construction»

 

Information about the work done for 10 months of 2020

      The volume of construction for 10 months of this year amounted to 7 679593.0 million tenge, which is 102.2% compared to the previous year 2019. The forecast for 11 months is 8 529593 million tenge or 100%. The annual forecast is 10,300. 0 million tenge and is 101%.

      For individual housing construction, 17,295 square meters were completed, which is 103.3 % compared to the previous year 2019. Forecast for 11 months 19495 sq. m. 101%. Annual forecast 20595 sq. m. 103.3%.

 

Name

Individual residential buildings (number)

Communal residential buildings (number)

t.Shubarkuduk

82 houses – 11099 sq. m.

 

v.Kenkiyak

8 houses - 1058 sq. m.

 

c.Temir

7 houses - 823 sq. m.

 

v.Shubarshi

7 houses – 865 sq. m.

 

v.Kenestuy

8 houses – 994 sq. m.

 

v.Shubarkuduk

2 houses – 229 sq. m.

 

v.Aksai

1 house – 143 sq. m.

 

v.Sarkol

4 houses – 525 sq. m.

 

v.Aksai

2 houses – 219 sq. m.

 

v.Taskopa

12 houses – 1253 sq. m.

 

v.Shygyrly

1 house – 87 sq. m.

 

Total:

134 houses - 17295 sq. m.

 

Completed projects in 2020

According to the program " Nurly Zher"

  1. "Reconstruction" Construction of engineering and communication infrastructure (gas supply) in the microdistrict "Kyzylzhar-3" in the village of Shubarkuduk, Temir district, Aktobe region". The total cost of the project is 104296.5 thousand tenge. 82529.0 thousand tenge was allocated from the Republican budget and 9170.0 thousand tenge from the regional budget. The winner was determined by "YERZAT" LLP at the price of 81268.8 thousand tenge. From the national budget 74075.2 thousand tenge and from the regional budget 7193.6 thousand tenge. The construction period is 3.5 months. High-pressure gas pipeline length-757.0 m; the length of the medium-pressure gas pipeline is 901.0 m; the length of the low-pressure gas pipeline is 7677.0 m; the total length is 9335 m. on 29.10.2020, construction work was completed. Gas networks have been connected to 226 separate land plots.

According to the program "Employment Road map"

  1. "Construction of the electric network in the "Kyzylzhar-3" microdistrict of the Temir district of the Aktobe region". The total cost of the project is 151727.0 thousand tenge. By the decision of the maslikhat No. 522 dated March 31, 2020, 149,595. 0 thousand tenge was allocated. The winner-LLP "OTES Aktobe". The price is 129 010.6 thousand tenge. The construction period is 4 months. VL-10 KV-0.839 km, KL-0.4 kV-0.305 km, VL-0.4 kV-10.773 km. The total length of 11,917 km 27.10.2020 year, construction work has been completed. The electric network is connected to 334 separate land plots.
  2. "Construction of the gas network in the "Kyzylzhar-3" microdistrict of the Temir district of the Aktobe region". The total cost of the project is 136279.0 thousand tenge. By the decision of the maslikhat No. 522 dated March 31, 2020, 130001.0 thousand tenge was allocated. The winner -LLP "OTES Aktobe". The price is 112 112.8 thousand tenge. Construction duration is 3 months. 26.10.2020 year, construction work has been completed. The gas network is connected to 325 separate land plots. Total length 9786m.
  3. "Construction of a water supply network in the "Kyzylzhar-3" microdistrict of the Temir district of the Aktobe region". The total cost of the project is 48997.0 thousand tenge. By the decision of the maslikhat No. 522 dated March 31, 2020, 44607.0 thousand tenge was allocated. The winner is BASPANA BUILD LLP. The price is 38,467. 8 thousand tenge. The construction period is 5 months. 07.07.2020 year, construction work has been completed. The water supply network is connected to 61 separate land plots. The total length is 2,3703 km.

 

According to the program " Auyl-El besigi"

  1. "Construction of a sports and recreation complex in the" Kyzylzhar "microdistrict in the village of Shubarkuduk, Temir district, Aktobe region". The total cost of the project is 450737.0 thousand tenge. In 2019, 250,000. 0 thousand tenge was allocated from the national budget and 12000,0 thousand tenge was fully disbursed from the regional budget. The winner was determined by Koktem-Stroy LLP at the price of 386123.6 thousand tenge. In 2020, 102718.0 thousand tenge was allocated from the national budget and 27191.0 thousand tenge from the regional budget, including 97512.0 thousand tenge for construction works from the national budget. tenge and from the regional budget 26612,0 thousand tenge. The construction period 2019-2020. For rent in December.

Land area-0.7 ha; number of Floors-2 floors;

Built-up area-2063.88 m2; Total area-2877.2 m2;

 

  1. "Construction of a sports and recreation complex on K. Baluanov street in Kenkiyak village of Temir district of Aktobe region". The total cost of the project is 316581.0 thousand tenge. The winner is RUS Tal LLP in the amount of 269825.9 thousand tenge. The construction period is 7 months. The construction period 2020-2021 years.
  2. "Construction of a sports and recreation complex on Geologist street in the village of shubarshi, Temir district, Aktobe region". The total cost of the project is 320139.0 thousand tenge. The winner - LLP "Strone", the price is 273078,3 thousand tenge. The construction period is 7 months. The construction period 2020-2021 years.

The purchase of housing under the program "Nurly jer"

In 2020, 25200.0 thousand tenge was allocated from the municipal housing Fund to Temir district for the purchase of housing for low-income large families. By order of the Minister of Finance of the Republic of Kazakhstan dated December 11, 2015 No. 648 "on approval of the Rules for public procurement", a competition was held in the "purchase of housing" method, 3 individual residential buildings were purchased in the village of Shubarkuduk, Temir district, Aktobe region. The total cost was 17,650. 0 thousand tenge.

Construction of schools

  1. " Construction of a secondary school for 320 students with a boarding school for 60 places in the "Kyzylzhar" microdistrict in the village of Shubarkuduk in the Temir district of Aktobe region". The total cost of the project is 1,225,082 thousand tenge. In 2018, construction work started through the state institution "Department of construction, architecture and urban development of Aktobe region". In 2019, 762038.0 thousand tenge was disbursed from the national budget. The winner is Sparta & Co LLP, price 1117676.4 thousand tenge. In 2020, 355704.1 thousand tenge was allocated from the national budget. The construction period 2018-2020. Commissioned in November.

320-seat school

The land area is 2,090 ha. The capacity of the school-320 seats

The built-up area is 2637.34 m2. Number of floors-1,2,3 floors

The total area of the building is 6053.29 m2

boarding School for 60 people

Capacity-60 seats. Number of floors-2 floors

Building area-1157.25 m2

The total area of the building is 2425.92 m2

 

  1. "Construction of a secondary school for 320 students with a boarding school for 60 places in the village of shubarshi, Temir district, Aktobe region". The cost of the project-1 150,377 thousand tenge. The winner is Babek-Kurylys LLP, price 1102793.5 thousand tenge. The construction period 2018-2021 years.

320-seat school

The land area is 2,072 ha. The capacity of the school-320 seats

The built-up area is 2590.0 m2. Number of floors-1,2,3 floors

The total area of the building is 5164.4 m2

Boarding school for 60 places

Capacity-60 seats. Number of floors-2 floors

Built-up area-782.0 m2

The total area of the building is 1783.1 m2

Completed projects for 2020-2021

  1. "Construction of an administrative building in the city of Temir, Temir district, Aktobe region". The total cost of the project is 60159.0 thousand tenge.
  2. " Construction of 2-storey 16-apartment communal rental housing in the "Kyzylzhar" microdistrict of the village of Shubarkuduk, Temir district, Aktobe region " the Total cost of the project is 158930.0 thousand tenge.
  3. "construction of a cattle burial ground (biothermal pit) in the village of Aksay in the Aksay rural district of the Temir district of the Aktobe region". The total cost of the project is 17171.6 thousand tenge.
  4. " Improvement of the Park located in the "Kyzylzhar" microdistrict of the village of Shubarkuduk, Temir district, Aktobe region " the Total cost of the project is 86076.0 thousand tenge.

6.12000,0 thousand tenge was allocated from the local budget for the development of design and estimate documentation and construction works for the construction of a multifunctional Playground (hockey box (court), football field) in the village of Shubarkuduk Of the Shubarkuduk rural district of the Temir district of the Aktobe region. Designer of Remstroyproekt LLP. Contract No. 16 dated 13.03.2020 for the amount of 510.0 thousand tenge. The total cost of the project is 18937.0 thousand tenge.

7.12000,0 thousand tenge was allocated from the local budget for the development of design and estimate documentation and construction works for the construction of a multifunctional Playground (hockey box (court), football field) in the village of Shubarkuduk of Zhaksymay rural district of Temir district of Aktobe region. Designer of Remstroyproekt LLP. Contract No. 19 dated 13.03.2020 for the amount of 510.0 thousand tenge. The total cost of the project is 19574.0 thousand tenge.

  1. The development of design and estimate documentation and construction work on the construction of multifunctional Playground (hockey rink (court), football field) in the village of Aksai Aksai rural district of Temir district of Aktobe region allocated from the local budget 12000,0 thousand tenge. The designer of LLP "Masterproekt". Contract No. 17 dated 13.03.2020 for the amount of 510.0 thousand tenge. The total cost of the project is 18119.0 thousand tenge.
  2. The development of design and estimate documentation and construction work on the construction of multifunctional Playground (hockey rink (court), football field) in the village Altykarasu Allegradosage rural district of Temir district of Aktobe region allocated from the local budget 12000,0 thousand tenge. The designer of LLP "Masterproekt". Contract No. 18 dated 13.03.2020 for the amount of 510.0 thousand tenge. The total cost of the project is 18591.0 thousand tenge.

Upcoming projects for 2020-2021

1.4500.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of a rehabilitation center in the village of Shubarkuduk, Temir district, Aktobe region. The designer of LLP "Masterproekt". The contract is 2975.0 thousand tenge. The task was given to develop it as a matter of urgency.

2.4500.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of a rehabilitation center in the village of Kenkiyak, Temir district, Aktobe region. The designer of LLP "Masterproekt". The contract is 2975.0 thousand tenge. The task was given to develop it as a matter of urgency.

3.900.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of an extension to the administrative building on N. Baiganin street in the village of Shubarkuduk, Temir district, Aktobe region. The designer of LLP "Gimaret+1". Contract No. 64 dated 27.07.2020 for the amount of 650.0 thousand tenge. The task was given to develop it as a matter of urgency.

4.3200.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of a sports hall located on the territory of the school-Lyceum No. 1 in the village of Shubarkuduk, Temir district, Aktobe region. The designer of LLP "Acts of engineering". Contract No. 74 dated 07.09.2020 for the amount of 2720.0 thousand tenge. The task was given to develop it as a matter of urgency.

5.3200.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of a sports hall located on the territory of the main school No. 6 in the village of Shubarkuduk, Temir district, Aktobe region. Designer of the design Bureau of Neftegazengineering LLP. Contract No. 71 dated 18.08.2020 for the amount of 2720.0 thousand tenge. The task was given to develop it as a matter of urgency.

  1. The development of design and estimate documentation for construction of sports hall, located on the territory Kerievsky high school Shubarkuduk village of Temir district of Aktobe region allocated from the local budget 3200,0 thousand tenge. The designer of LLP "Acts of engineering". Contract No. 76 dated 07.09.2020 for the amount of 2720.0 thousand tenge. The task was given to develop it as a matter of urgency.

7.3200.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of a sports hall located on the territory of the Sarkol secondary school in the village of Sarkol, Temir district, Aktobe region. The designer of LLP "Acts of engineering". Contract No. 73 dated 07.09.2020 for the amount of 2720.0 thousand tenge. The task was given to develop it as a matter of urgency.

8.3200.0 thousand tenge was allocated from the local budget for the development of design and estimate documentation for the construction of a sports hall on the territory of the Enbekshi school-kindergarten in the village of Enbekshi, Temir district, Aktobe region. The designer of LLP "Acts of engineering". Contract No. 72 dated 07.09.2020 for the amount of 2720.0 thousand tenge. The task was given to develop it as a matter of urgency.

General plan of Kenkiyak village in 2020

In 2020, 18000,0 thousand tenge was allocated from the local budget for the development of the General plan of Kenkiyak village in Temir district of Aktobe region. Designer PRK "Aktyubgrazhdanproekt". The contract is 15300.0 thousand tenge. The development period is until 31.12.2020.

Дата публикации
22 ноября 2020
Дата обновления
22 ноября 2020
Тип
Press releases

Сейчас читают

Press releases
18 марта 2022
02/16/2020 - Press release to the draft resolution of the Akimat of Temir district "On approval of the Rules for organizing and carrying out activities for the current or major repairs of facades, roofs of apartment buildings aimed at giving a unified architectural appearance to settlements of Temir district"
Announcement
18 марта 2022
Newspapers/magazines
18 марта 2022
DEVELOPMENT OF SMALL AND MEDIUM-SIZED BUSINESSES

Социальные медиа

Меню подвал

State of the Nation Address of the President of Kazakhstan
Website of the President of Kazakhstan
Website of the Prime Minister of Kazakhstan
Digital transformation concept
Life situations
National symbols
Terms and explanations
Central communications service under the President of the RK
Screen Reader
Құпиялылық саясаты