GOV.KZ – Single platform for the digital resources of government agencies

Меню
Страницы
Contacts
Press Room
About the Department
Activity
Documents
Feedback
Все материалы
12 июля 2024
178 houses are being built in six villages

 The construction of residential buildings for flood victims is actively underway in the Wilsky district. Today, Deputy Akim of the region Asylbek Yesenbayev visited the district and got acquainted with the progress of construction. In addition to the district center, construction companies are building houses in the villages of Karatal, Akkemer, Kemer, Akzhar and Bestamak.

As you know, the central estate of the rural district named after Sh. Bersiev suffered the most. According to the reports provided by the akimat of the district based on the results of monitoring the construction stages, the construction of 133 houses has begun in Karatal. As of July 11, 129 of them had their foundations laid, 90 had walls erected, and forty had their roofs blocked. Plastering works are underway in more than 20 houses. Engineering networks have been connected to 15 houses, windows are already being installed there.

In Uil, half of the 20 houses under construction are waiting for communications to be connected. In the settlement of Akkemer, 16 families should be provided with a roof, five houses are being built in Akzhar, two each in Kemer and Bestamak. In many of them, the builders also switched to roofing, plastering and laying utility networks.

Recall, in addition, about 100 families have already purchased ready-made houses on the secondary market.

27 июня 2024
In the village of kobda, builders moved to cover the roofs of 61 houses

In the center of the flood-affected Kobda District, 15 construction companies are building 130 houses. At the moment, contractors have accelerated construction, increasing the labor force. As a result, the roofs of 23 residential buildings were completely closed, and the roofs of 61 houses are about to close.

✔️ Bricks were laid in some of the 121 residential buildings, and now the work on laying white-red bricks will be completed. The builders also began finishing the interior of the house, pouring the foundation of 9 houses.

📌 And in the village of Zharyk, 17 houses are being built. Everything is built of bricks and the walls are plastered.

The construction process is monitored by CCTV cameras.

23 апреля 2024
Restoration of the rights of service recipients
17 апреля 2024
Figure of the day: 1,165 families received a lump sum payment

Отбасыл families suffering from floods and finding themselves in difficult life situations are provided with a one-time social payment based on decisions of local representative bodies.

➤ Since April 6, 1,486 documents have been accepted in the region. Of these, 1165 families were paid 380.2 million tenge.

➤ Documents worth 116.4 million tenge for the remaining 321 families are under consideration.

17 апреля 2024
Land plots have been identified for the construction of new houses in the village of Kobda

📌 The head of state at one of the meetings of the operational headquarters on the agenda of the meeting of the heads of State instructed to ensure the beginning of construction of houses for subsequent completion in the end of the first step. Aktyubinskaya region has set up the implementation of the planned tasks.

Last week, more than 200 land plots for the construction of houses with a developed farm were announced in the will region. Today, land plots for construction of new residential buildings were raised in Kobdinsky district.

✔️ With representatives of construction companies in the village of Kobda, Yerzhan Muzdybayev was the head of the regional management of construction, architecture and architecture.

According to him, 102 houses were built in the village of Zharyk in this District — 27. today, the start of work on filling the fields on the territory, where new houses will be built.

"We have developed objects of construction in the village of Kobda between 15 sub-level organizations. They start building works on their own funds. In the course of two months, all construction works should be completed. The projects will be built in the area of 80 and 100 square meters. "The questions are resolved with the plants, the work will be carried out on the post of kirpicha and other construction materials""",
- Yerzhan Muzdybayev said.

Akim of Kobdinsky district Izgilik Tynymgereyev has said that the maintenance of technical facilities in the district center will continue.

"Today, 284 applications for the import of property from the village of Kobda have been made. During the period of technical assistance, 102 houses are not created, which means that the houses must be built. It is possible that this number will be increased, the post of technical assistance to the attached housing will continue",
"what's the matter?"

️ ️ New houses will also be built in Wilsk, Aitekebiysk, Temirsk and Irgizsky districts.

"To date, we have allocated 15 contractors for the drowned houses in the village of Kobda. They start construction work at their own expense. Within two months, all construction work should be completed. As for the projects, houses of 80 and 100 square meters will be built here. At the meeting with the population, the akimat of kobda district, by mutual agreement, will allocate houses in the future. Now agreements are concluded with factories, work is underway to supply bricks and block stones",

- says Yerzhan Muzdybayev.   Akim of kobda district Izgilik Tynymgereev said that the inspection of the technical condition of flooded houses in the district center continues.  

"To date, 284 applications have been received from residents of the village of Kobda about damage to property as a result of flooding. During the technical inspection, it was found that 102 houses will not be restored, that is, so many houses will have to be built. As the technical inspection of flooded housing continues, this number may increase in the near future",

- noted the Akim of the district.   New houses will also be built in the districts of Oyil, Aiteke bi, Temir and Irgiz.

26 марта 2024
The construction of a school for 60 places in the village of Terisakkan, kobda district is carried out in accordance with the production schedule. The contractor was obliged to complete the 2024 academic year in a timely and high-quality manner.
26 марта 2024
Together with the deputy akim of Aktobe region Asylbek Yessimkhanovich, we visited the construction of a long-term school. During the visit, the contractors were instructed to complete the construction efficiently and on time.
19 марта 2024
⚜️️ ️️The head of the department visited a number of construction sites.

As a result of the visit, Mugalzhar and Shalkar district visited the facilities where construction and installation work is underway.

Including:
- Construction of a 600-seat school in the MD. Samal, Kandahash city
- Construction of 320 schools in Emba city
- Visited the reconstruction facilities of the hospital in Shalkar.

He gave the contractors appropriate instructions that the construction should be completed in a timely and efficient manner.

14 марта 2024
Congratulations to everyone on the harbinger of Nauryz - Amal kuni!
14 марта 2024
⚜️The head of the department visited a number of construction sites.

✅As a result of the visit, Mugaljar and Shalkar district visited the facilities where construction and installation work is underway.

Including:
- Construction of a 600-seat school in the MD. Samal, Kandahash city
- Construction of 320 schools in Emba city
- Visited the reconstruction facilities of the hospital in Shalkar.

🏗He gave the contractors appropriate instructions that the construction should be completed in a timely and efficient manner.

Социальные сети
Меню подвал
State of the Nation Address of the President of Kazakhstan
Website of the President of Kazakhstan
Website of the Prime Minister of Kazakhstan
Digital transformation concept
Life situations
National symbols
Terms and explanations
Central communications service under the President of the RK
Screen Reader
Құпиялылық саясаты