GAS SUPPLY OF THE REGION:
Currently, by the end of 2023, 168 or 52.5% of 320 settlements, 886.5 thousand people or 95.5% are provided with gas.
In 2023, 16 villages with a population of more than 6.8 thousand people were gasified (Aiteke bi – Kumkuduk; Irgiz - Nura, Amankol; Uil – Ekpetal; Kargaly - Alimbet; Martuk - Karatausai, Baiturasai, Karabulak; Mugalzhar – Mugalzhar, Zharkemer, Zhanaturmys; Khromtau - Kuduksai, Karlau; Kobda - Bulak, Kosotkel; Shalkar - Yeset batyr).
In 2024, it is planned to gasify 7 villages (Baiganin – Korashi; Irgiz – Zharma; Martuk – Akmolasai, Baynassai; Mugalzhar – Zharyk; Temir – Altykarasu, Enbekshi) with a population of 2.8 thousand people.
As a result, 175 (54.7%) settlements or more than 889.2 thousand people (95.8%) will be covered by gas supply.
In addition, 21 design and estimate documentation worth more than KZT 21,343.1 million (SMR) has been developed providing for gasification of 27 villages. Also, 1 PSD is being developed (Shalkar – Alabas, Sarsai, Birshogyr).
In order to ensure uninterrupted gas supply to Aktobe, adjacent settlements and industrial facilities, design and estimate documentation was developed for the construction of the 3rd line of the gas pipeline branch to Aktobe from the Bukhara-Ural MG in the amount of 43.4 billion tenge, construction and installation works are currently underway (Otaustroy LLP, Shymkent, the total length is 166.7 km).
Currently, 87 km of trenches have been developed, 70 km of gas pipelines have been welded, of which 50 km of gas pipelines have been laid in a trench.
At the same time, 166.7 km of the gas pipeline were delivered from 166.7 km to the facility.
To date, 20.4 billion tenge has been disbursed.
If funds are allocated, the implementation of this project is planned to be completed in 2024.