Information on the work done by the Department of Housing and communal services and housing inspection of koksu district for the 3rd quarter of 2020.

Gas supply system

 According to the internal gas supply system of Balpyk bi village of koksu district, 19.60 km of medium-pressure underground and 63.10 km of low-pressure gas pipelines were laid. In total, it is planned to connect 3,354 subscribers in the village of Balpyk BI, to date, gas pipelines have passed through 2,000 yards, 767 contracts have been signed, of which 708 have already been connected. In the village of balpyk bi, 49 streets are connected to the gas system. The length of the gas system is 119 km, the volume of gas consumption will be 21 million/m3 per year. In general, in the village of Balpyk bi, detailed explanatory work is carried out on the possibility, cost-effectiveness and benefits of connecting to gas to residents of the streets where gas pipelines are laid in accordance with the plan.

 In order to gasify the remaining settlements of Koksu district through the state institution" Department of energy and housing and communal services of Almaty region", it is planned to carry out construction and installation works for gasification of 4 villages of the District.

For the object" construction of gas distribution networks and supply gas pipeline in mambet village of koksu district", a public procurement procedure was carried out for 203,820,681 tenge, following the results of which Sunkar-2002 LLP was determined as the general contractor.

 For the object" construction of gas distribution networks and supply gas pipeline in Zhambyl village of koksu district", a public procurement procedure was carried out for 173,728,920 tenge, following the results of which Azia RC LLP was identified as the general contractor.

 "For the object "" construction of gas distribution networks and supply gas pipeline in Mukry village of koksu district"", a public procurement procedure was carried out for 432,738,104 tenge, as a result of which Sunkar-2002 LLP was determined as the general contractor."

 "For the object "" construction of gas distribution networks and supply gas pipeline in Beskainar village of koksu district"", a public procurement procedure was carried out for 280,771,560 tenge, following the results of which Sunkar-2002 LLP was determined as the general contractor."

Heat Supply System

In accordance with the resolution of the Akim of koksu District No. 263 dated June 29, 2020 "on the results of the 2019-2020 heating season and tasks for the upcoming 2020-2021 heating season", the district headquarters was established and the work plan was approved in accordance with the resolution of the Akim of Koksu District No. 251 dated September 04, 2020. Members of the district headquarters were assigned to rural districts to coordinate the work of the headquarters.

In the district, for the heating season 2020-2021, 783,334 tons of liquid fuel were delivered to budget institutions to date, 755,874 tons, or 96.5%, and 740 tons of solid fuel were fully delivered to date, or 100%.

In particular, in the field of Education, 40 educational institutions will operate during the 2020-2021 heating season. Of these, 4 Schools, 1 music school and 4 kindergartens are connected to the central heating system, 3 schools, 1 kindergarten are heated with coal, 18 schools and 9 kindergartens are heated with liquid fuel.

In the 2020-2021 heating season, a limit of 669942 liters of liquid fuel was approved for 18 schools and 9 kindergartens. 147387.0 thousand tenge was allocated for the purchase of liquid fuel. A contract was signed with Asar GROUP LTD LLP for the purchase of 669942 liters of liquid fuel. To date, 612,362 liters of liquid fuel have been delivered, or 91.4%. In the secondary school named after zh.Eginbayev approved an additional limit of 9000 liters of liquid fuel and in the secondary school named after T. Isabayev-8000 liters (due to non-compliance with the temperature regime)

4 schools connected to the central heating system have signed contracts for 2020 in the amount of 12,000.0 thousand tenge.

For the heating season 2020-2021, 5572.0 thousand tenge was allocated for the purchase of 400 tons of coal. The competition was not announced, it was scheduled for July). 22 tons for karatal primary school, 68 tons for Zhastar Sports Complex at zh.Eginbayev secondary school, 310 tons for secondary school No. 12 at Ainabulak station.

For the heating season, a contract was signed with GIG Master Fakel LLP for the current repair of heating boilers in the amount of 8000.0 thousand tenge. The fire boilers were prepared for the heating season and put on ucconservation). Liquid fuel storage tanks are fully calibrated. The 50-meter capacity for storing liquid fuel, located outside, is heated.

In 2020, 18 sealants were purchased for 18 liquid fuel heating schools. 9 kindergartens are also provided with sealants.

In 2020, the current repair of the heating system of the Algabas secondary school and major repairs of the heating system of the secondary school No. 5 are being carried out.

In the field of culture In order to obtain 90,392 tons, a public procurement procedure was carried out and fully delivered by Aikol trans oil LLP, a public procurement procedure was carried out for 60 tons of solid fuel in the amount of 900.0 thousand tenge was determined by the general contractor KARIMBAYEV Cengiz. Solid fuel has been fully delivered to date;

In the field of Health According to the results of the competition, 4,042.5 thousand tenge was allocated for 23,000 tons, Diesel Group was determined as the general contractor and Contract No. 90 was concluded on May 22, 2020, to date, work is underway on the full supply of 23,000 tons of liquid fuel. 5,040.0 thousand tenge was allocated for 280 tons, and the general contractor was Ars LLP, which concluded a contract No. 50 on May 18, 2020. to date, work has been carried out on the supply of 280 tons of solid fuel.

 

Landscaping

The design and estimate documentation for the object" improvement of courtyards of high-rise buildings in Balpyk bi village of Koksu District of Almaty region " was fully developed and an expert opinion was obtained (on October 10, 2018 No. TE-0030/18). The procedure for public procurement in the above-mentioned form was announced, and following the results of the competition, the general contractor was identified as "Corporation Tas" LLP. To date, the improvement of the territories of Myrzabekov and Tazabulak microdistricts has been completed by 100%, currently work has begun and is underway to improve the yards of multi-apartment residential buildings on Kablisa zhyrau, Daraboz Ana and Auezov streets. The object is fully completed.

 

Sanitary cleaning

         In accordance with the resolution of Almaty region No. 73 dated February 28, 2020 "on conducting spring-autumn months of sanitary cleaning, improvement and landscaping of settlements of the region", in Koksu district by the resolution of the district Akim No. 81 dated March 06, 2020 "on conducting a month of spring-autumn sanitary cleaning, improvement, landscaping of settlements", a headquarters for conducting a month of cleaning was established and an action plan was approved. Sanitary cleaning of the district was carried out 7 times a day. It will be attended by residents of 34 localities, including state and budgetary institutions. In order to carry out cleaning works, the district administration employs 4 units of special equipment. To date, 182 tons of solid household waste from 10 rural districts have been removed to special landfills.

Modernization of Housing and communal services

 To date, 8,533,069 tenge or 82.1% of the planned 10,587,552 tenge has been repaid for the modernization of houses No. 10 and No. 7 in Shadrin microdistrict.

Information about employment roadmap objects

In order to provide residents of Balpyk bi village of koksu district with high-quality drinking water without interruption, a public procurement procedure for the object "reconstruction and construction of the drinking water system of the central part of Balpyk bi village of Koksu district" was carried out, following the results of the competition, the general contractor was identified as "builder-TBS" LLP. On April 29, 2020, a contract was signed for the amount of 1,244,325,749 tenge. On May 06, 2020, a notification (coupon) was received about the start of construction and installation works. The capacity of the facility is 39.3 km, the completion date is December 01, 2020. According to the plan of 150 people, 66 people have been provided with work through the employment center.

A public procurement procedure was carried out for the object" installation of street lighting on Vinogradova Street in Akshatogan village of balpyk rural district of koksu district", following the results of the competition, the general contractor was identified as" Zhan-Miras " LLP. On May 03, 2020, a contract was signed for the amount of 5,446,848 tenge. The capacity of the facility is 0.8 km, and the facility is fully completed.

A public procurement procedure was carried out for the object" installation of street lighting on the central street of Akshatogan village of balpyk rural district of koksu district", following the results of the competition, the general contractor was identified as" Zhan-Miras " LLP. On May 03, 2020, a contract was signed for the amount of 8,054,958 tenge. The capacity of the facility is 1.2 km, and the facility is fully completed.

"A public procurement procedure was held for the object "" current repair of the stadium and Square on Idigov Street in zharlyozek village of koksu district"", and following the results of the competition, the general contractor was identified as ""specialized gas Management "" LLP." On April 31, 2020, a contract was signed for the amount of 24,427,715 tenge. The deadline for completion of the facility is OCTOBER 01, 2020. Through the employment center, according to the plan, there should be 4 people.to date, 4 people have been provided with work.

"A public procurement procedure was carried out for the object "" arrangement of a sports field in the village of Z. Tamshybay, koksu district"", following the results of the competition, the general contractor was identified as ""specialized installation and installation management of gas equipment "" LLP." On April 30, 2020, a contract was signed for the amount of 13,531,842 tenge. The deadline for completion of the facility is OCTOBER 01, 2020. Through the employment center, according to the plan, there should be 2 people.to date, 2 people have been provided with work.

 A public procurement procedure was held for the object" arrangement of a volleyball court with a mini-football field and a mesh fence on Zhaparbayev and Nurpeisov streets in the village of 50 years of Kazakhstan in koksu district", following the results of the competition, the general contractor was identified as" as-Sapa kurylys " LLP. On April 30, 2020, a contract was signed for the amount of 37,704,009 tenge. The deadline for completion of the facility is OCTOBER 01, 2020. According to the plan, there should be 5 people through the employment center.to date, 5 people have been provided with work.

Lean system

The project and estimate documentation for the object" reconstruction and construction of aryk networks in Balpyk bi village of Koksu District of Almaty region " has been fully developed and a positive expert opinion has been obtained. 300,000.0 thousand tenge for the 1st stage of construction and installation works in the state institution "Department of energy and housing and communal services of Almaty region" for the above-mentioned form.according to the results of the expert examination, the general contractor was identified as "TOLAGAI-2050". To date, 2 km of ditches have been installed and 2 km of trenches have been excavated. 5 people and 2 units of special equipment are involved. The total cost of this project is 1 billion tenge.

Housing of koksu district

public utilities and

head of the Housing Inspection Department                       А.Кокеtаеv

 