During the visit, he inspected the repair work of JSC «Ridder CHP». To date, the current repair of boiler units No. 2,3,6 and turbine generators No. 1,2,5 has been completed. Boiler No. 1 has been repaired by 13%, turbine No. 4 by 15% and turbine No. 4 by 36%. In accordance with the approved schedule of KEGOC JSC, it is planned to complete the work by September 30, 2022. As of August 8 of this year, 8.0 thousand tons of coal have been accumulated at the CHP. 152 wagons or 10.5 thousand tons were delivered to JSC «Ridder CHP» in June, 122 wagons or 8.5 thousand tons in July.
Since the beginning of August, 10 wagons have been delivered daily.
According to the results of the conducted crimping of heating networks, 350 m of emergency 6 sites were identified. To date, repair work on emergency networks has been completed.