The head of the Ridder-Adaldyk Alany project office conducted monitoring on the technical condition of vehicles for winter maintenance of roads in the city of Ridder.
The contractor performing work on the winter maintenance of the roads of the city of Ridder is the Etalon Firm LLP.
In the period of heavy snowfalls, a full mobilization of snow removal equipment is carried out, in the amount of 26 units, which is quite enough for the timely execution of work.
For the timely execution of work, the contractor has the following composition of road equipment: graders - 7 units, loader - 2 units, tractors of all brands - 9 units, including type K-700 - 1 unit, KAMAZ - 6 units, Auger based on Ural - 1 unit.
Snow raking is carried out on 77 streets of the city, as well as on 156 streets of the private sector, about 21 sidewalks. 68 sections of roads and intersections are being filled with anti-slip material. Also in winter, work is carried out on filling pedestrian crossings and stops.