Within the framework of the Roadmap in the agro-industrial complex of the East Kazakhstan region for the period 2022-2026, the implementation of 15 projects is envisaged, the correspondent reports Altainews.kz .
The total amount of investment projects in 2024 is 55799.5 million tenge, according to the Department of Agriculture of the East Kazakhstan region.
In particular, a number of important projects are planned in dairy farming, the relevant department informed. – These are 7 projects totaling 22698 million tenge.
It is noted that among them is the construction of a dairy farm for 616 heads by the forces of KT Khamzin and Co. in the Shemonaikhinsky district. The annual production capacity is 7,500 tons of milk, and the project cost is 3,600 million tenge. Within the framework of the program of replication of the experience of the North Kazakhstan region (North Kazakhstan region), loans in the amount of 1666 million tenge were carried out.
Another project concerns the construction of a dairy farm for 500 heads in Sugatovskoye LLP in the Shemonaikha district, " the relevant department reports. – Its production capacity is 4,000 tons of milk per year. The cost of the project is 3,000 million tenge.
We add that the next project for the construction of a dairy farm for 1000 heads is being implemented in Moyyldy Baikonur LLP, in the Altai region. The annual production capacity there is 10,000 tons of milk. The cost of this project is 10151 million tenge. Within the framework of the program of replication of the experience of the North Kazakhstan region, loans in the amount of 4698 million tenge were carried out.
Another project for the construction of a dairy farm for 300 heads is being implemented in Srednegornoye-2 LLP in the Altai region, the profile management adds. – The production capacity there is expected to be 2,920 tons of milk per year. The cost of the project is 1,500 million tenge.
Within the framework of the program of replication of the experience of the North Kazakhstan region, loans for 695 million tenge were carried out.
The next project for the construction of a dairy farm for 600 heads is being implemented in the Ukrainka farm in the Ulan district. The annual production capacity is 4,800 tons of milk, and the project cost is 2107 million tenge. Within the framework of the program of replication of the experience of the North Kazakhstan region, loans for 975 million tenge were carried out.
It is also reported that the construction project of a dairy farm for 1080 heads is being implemented in Rulikha LLP in the Shemonaikha district. The annual production capacity is 10,800 tons of milk, and the project cost is 1,250 million tenge. Within the framework of the program of replication of the experience of the North Kazakhstan region, loans for 578 million tenge were carried out.
The portfolio of investment projects is complemented by the construction of a dairy farm for 800 heads in AgroVostok LTD LLP, in the Ulan district. The production capacity is 2500 tons of milk per year. The cost of the project is 1,090 million tenge, the construction is carried out at its own expense.
As noted in the relevant department, these projects will give a noticeable impetus to the development of the East Kazakhstan region dairy industry.
Tahir Sapargaliev