Akim of NKR inspected construction of water distribution networks in Yakor village

Akim of NKR inspected construction of water distribution networks in Yakor village

Repair work on the water supply of the village of Yakor is in full swing. Design and estimate documentation was developed back in 2020. 13.8 km of new water pipes will be laid here. At the moment, most of the work has been completed. It will be possible to complete the repair ahead of schedule, by September. About 100 residents of the village have already applied for connection of houses to water supply. The head of the region wrote about this in his social networks.

"In North Kazakhstan region, out of 635 villages of the region, 406 are provided with centralized water supply. This year, 12.3 billion tenge has been allocated to this area. We will build and reconstruct 135 km of networks," Kumar Aksakalov shared with subscribers.

At the moment, 55 villages are covered by the works. In 15 of them, the water supply system will be improved by the end of the year. These are the villages of Pokrovka and Beloye of the Mamlyutsky district, Anchor and Beskol of the Kyzylzhar, Toksan bi of the G. Musirepov district, Kirovo of Taiynsha district, Obrazets and Sulyshok of M. Zhumabayev, Timiryazevo, Leninskoye, Michurino, Belogradovka and Moskvoretskoye of Timiryazev district, Krivoshchekovo and Novopokrovka of Shal Akyn district.

Also, in 10 villages, where water was taken from wells or brought earlier, water supply will appear. In the Yesil district, these are the villages of Talapker, Polyakovka, Ilyinka, Madeniet, in the Kyzylzhar district - Dubrovnoye, in the Zhambyl district - Kazanka, in the Taiynsha district we will supply water to the villages of Gorkoye, Makashevka, Letovochnoye and Roshchinskoye.