Work on the dams in the villages of Teplichnoye, Pribrezhnoye, and the village of Beskol is progressing rapidly. All three protective structures will be fully encased in concrete. The project has been fully funded.
Furthermore, to prevent the collapse of power lines, the North Kazakhstan Regional Electric Distribution Company JSC is installing reinforced concrete and metal supports, as well as ice-breaking devices. The crossings are constructed using self-supporting insulated wires, significantly increasing the reliability and safety of the power supply.
Reconstruction of the road leading to the village of Pribrezhnoye has also begun, including the construction of a bridge. Installation of the bridge structure and soil stabilization with rubble stone are planned for the winter. The bulk of the work will be completed in 2026.