NKR is preparing for the heating season

NKR is preparing for the heating season

The region is actively preparing for the upcoming heating season. The total amount of funding for preparatory activities is 44 billion tenge, which shows positive dynamics compared to the previous year. Of this amount, more than 33 billion tenge were provided by private investments.

 

🔹️ JSC "Sevkazenergo" allocated 27 billion tenge for the repair campaign. Work continues at Petropavl CHPP-2:

▪️reconstruction of the boiler unit and turbo unit,

▪️major repairs of 3 boilers and 2 turbo units,

▪️current repairs of 8 boiler units and 4 turbo units,

▪️completion of the construction of the chimney.

 

🔹️LLP "Petropavlovsk Heat Networks" allocated 1.5 billion tenge for the modernization of the heating infrastructure. Within the framework of these funds, it is planned:

 

▪️repair of 6.37 km of heating networks,

▪️reconstruction of 0.9 km,

▪️restoration of 4 km of thermal insulation.

 

🔹️The region's electric grid companies have planned:

 

▪️repair of 1,500 km of power transmission lines,

▪️reconstruction of 201 km of lines,

▪️repair of 221 substations.

 

🔹️In order to prepare for winter in the region's districts, the following will be carried out:

 

▪️preparation of 484 boiler houses, 636 educational facilities, 364 healthcare facilities, 162 culture facilities and 1.5 thousand multi-storey buildings

▪️purchase of 11 new boilers,

▪️repair of 6.3 km of heating networks.

 

In general, the repair campaign in the region is carried out according to schedule, work on connecting the new chimney to CHPP-2 is ahead of schedule.

 

❗️Following the meeting, the Akim of the region Gauez Nurmukhambetov gave a number of instructions on preparation for the upcoming heating season for the uninterrupted supply of heat to residents and facilities of the region.