Blue fuel acceptance center and its automatic distribution is planned to be commissioned in the autumn of this year. It will be able to distribute 250 thousand cubic meters of gas per hour.
The launch of an automated gas distribution station (AGDS) of the latest model will allow to provide gas supply for the city population. The city mayor Murat Aitenov got acquainted with the progress of construction of the future AGDS No. 3, and instructed the contractors to strengthen the work.
According to the plan, GDS No. 3 should be commissioned in 2021, but the head of the city instructed to complete its construction at the end of this year.
With the commissioning of the station, not only ordinary consumers will be provided with blue fuel, but also large industrial plants that cannot operate without gas. Only last year, about a hundred entrepreneurs asked to supply gas.After analyzing these issues, the city mayor noted that there are reasons for an early implementation of this project which will give impetus to the further development of the city's green economy.
M. Aitenov said that from the beginning of the year the emphasis was on the implementation of strategically important projects, including the automated gas distribution station No. 3, the construction of which were funded. Thanks to this, residents will no longer experience a shortage of natural gas.
The total length of the gas pipeline is 58 km. 220 km of it covers the distance from the main gas pipeline "Beineu-Bozai-Shymkent" to the automatic gas control station. Now this section is being laid a high-pressure gas pipeline with a diameter of 426 mm.
- A pipeline is laid from the AGDS in two directions. The length of the Western pipeline is 22 kilometers, 16 km of which have been completed. In the Eastern part, 12 from the 16 kilometers are involved.
When the plant is put into operation, it will be able to distribute up to 250 thousand cubic meters of gas per hour. "The pipelines are filled in immediately after the completion of pressing works," says Sultan Kaliakparov, a representative of StoryGaz Company LLP. - Places of welded joints are covered with special waterproof materials that are not afraid of corrosion. The pipeline itself will last 50 years."
The total cost of the gas project is more than nine billion tenge. According to the terms, its implementation provided for three years. However, the contractors intend to deliver the object in autumn.