THE CONSTRUCTION OF A TRANSPORT INTERCHANGE AT THE INTERSECTION OF RYSKULOV-KONAYEV STREETS IS WELL UNDERWAY

THE CONSTRUCTION OF A TRANSPORT INTERCHANGE AT THE INTERSECTION OF RYSKULOV-KONAYEV STREETS IS WELL UNDERWAY
Shymkent city mayor Murat Aitenov got acquainted with the progress of construction of a number of objects aimed at the development of roads and public transport in the city.
To date, the construction of a transport interchange at the intersection of Ryskulov-Konayev streets is well underway. Work has now been done to replace 3.3 km of water pipelines, gas pipelines, tunnel construction (150 m), to fill supporting walls (130 m), to install of columns (7) and pouring piles of 90 pieces.
It is planned to open Konayev Avenue for traffic through the tunnel until September 1 this year, and Ryskulov Street until November 1.
In general, the construction of the transport interchange is planned to be completed in December 2021.
 
Press service of Shymkent city mayor's office