Construction of a road interchange at the intersection of Ryskulov Street and Kunayev Avenue is well underway in Shymkent.
Today, Mayor of the city Murat Aitenov visited the construction site, where he got acquainted with the work progress.
The length of the object along Kunayev Avenue is 1 km and along Ryskulov Street is 0.7 km. Commissioning is planned before the end of the year.
To date, work has been carried out here to replace 3.3 km of water and gas pipelines, dig tunnels, fill 60 meters of retaining walls, install 7 columns and fill 75 piles.
In addition, the construction of an underground passage is planned on this section of the road. Funds are provided for the development of design and estimate documentation for construction, and a public procurement competition is being held.
Murat Aitenov, having seen the work done, instructed the head of the industry to complete the construction of the facility in time to eliminate inconveniences such as traffic jams.
Press service of Shymkent city mayor's office