At present, an automated gas distribution station with a capacity of 250,000 m3/h is built to provide the Shymkent city with high-quality and uninterrupted natural gas. Currently, 95% of the work has been completed.
The city mayor Murat Aitenov visited the construction site of substation "Bozaryk".
After commissioning of the 220/110/10 kV substation with a capacity of 160 MW, about 250 thousand subscribers of the microdistricts Asar-2, Turan, Yntymak-2, Soltustyk sayazhay, m-d Batys, Bozaryk, Kaynarbulak, Shymkent city, Dostyk and Nursat will be provided with high-quality electricity.
Having seen the construction of the «Bozaryk» substation, Murat Aitenov instructed to speed up the work in order to provide the population with high-quality electricity.
Press service of Shymkent city mayor's office