The provision level of sewage system in Shymkent is 49.1%.
Today, the city has 838 km of sewer pipes, including 168 km of main and 670 km of internal systems. However, 73% of the pipes are worn out.
Currently, 3 main and 14 internal sewage systems are being built to provide the population with sewage.
The construction of the main sewer system in the Togys microdistrict will be completed by the end of 2020, and 24 multi-storey residential buildings will be connected to sewer system.
In addition, if the construction of the sewer collector is completed along Argynbekov street to collectors No. 2, 6 settlements with a population of 49 thousand people will be connected to the sewer system. These construction works will be completed by 2021.
After the completion of the main sewer system in blocks 25,26,28,29 in the Turan microdistrict, 27 multi-storey residential buildings will be connected to the sewer system.
Currently, the construction of internal sewage has begun in 14 microdistricts with a population of 140 thousand people. Construction is scheduled to be completed next year.
By the end of this year, at the expense of public and private investors, it is planned to put into operation for 136 multi-storey houses. Upon completion of these works, the city's sewer coverage will increase from 49.1% to 52.3%.
In addition, if the construction of internal sewage is completed in 2021-2022, the districts of Shymcity, Asar-2, Dostyk, Turan, and Soltutik sayazhay located in the Northern part of the city will be able to connect to the sewage system. 18-20 thousand cubic meters of wastewater per day will be added for additional cleaning.