Members of the public council discussed the preparation of thermal power plants, boiler houses, heating networks and housing stock of the cities of Pavlodar, Aksu, Ekibastuz for the heating season of 2023-2024.
Of the 40 units of energy source equipment planned in the field, work has been carried out at 18 facilities, for the rest repairs are carried out according to schedules.
To date, all social objects in the region are fully prepared for the heating season, the housing stock is 98% ready. In three cities of the region, the damage detected after hydraulic tests has been completely eliminated. Reconstruction of the main heat supply networks is also being completed.
- Our main task is to start and carry out the heating season in normal mode on time. To do this, a large-scale repair campaign is being conducted in all cities and districts of the region. All these works will be completed by September 22. The issue is under my special control," Asain Baykhanov said.
The press service of the akim of Pavlodar region