Akim of the region Asain Baykhanov checked the progress of repair of heating networks in Ekibastuz

Akim of the region Asain Baykhanov checked the progress of repair of heating networks in Ekibastuz

According to the results of hydraulic tests in the city of miners, 269 damages were identified (34 main and 235 intra-block). Work on their elimination has already begun, 25 teams will gradually carry out repair and replacement of networks.

By May 15, it is planned to complete the first stage of network repair and connect 137 MZhD, then 221 MZhD will be connected by May 25 and 246 MZhD are planned to be connected by June 10. A detailed list with schedules for connecting houses will be presented on the telegram channel of the CHP.

Reconstruction of the TM-5 and TM-12 trunk pipelines has also begun. Now the dismantling of old networks and other preparatory activities are being carried out there. In total, four heating mains will be updated. It is planned to complete the work until the end of August.

The head of the region noted that when updating heating systems, it is important to take into account corrosion protection, carry out all work in accordance with all necessary requirements and on time to ensure timely hot water supply in the homes of Ekibastuz residents.

 

The press service of the akim of Pavlodar region