On April 22, the heating season ended in the city of miners. And on April 24, Ekibastuzteloenergo LLP started hydraulic tests, which will identify sections of heating networks in need of repair. 119 damages have already been identified, work has begun on 25 of them.
Today, the head of the region visited 4 sites where pipes are being changed, and also visited the base of Grappa-Stroy LLP, responsible for carrying out repairs. The contractor assured that there is enough material and equipment.
In total, Ekibastuz intends to repair more than 40 km of heating networks. The most worn-out pipes will be replaced completely. Work is being carried out by 25 teams, they promise to complete them by June 10.
- We need a clear plan for each site in order to reduce the period of absence of hot water to a minimum with high-quality work. It is also necessary to monitor the work of the KSK to prepare houses for the upcoming heating season," said Asain Baykhanov.
The press service of the akim of Pavlodar region