On Saturday, January 2, akim of Pavlodar region paid a visit to the power plants and combined heat and power plant in Ekibastuz.
At GRES-1 named after B.Nurzhanov akim of the region was told about the situation in the production and storage of coal. Today, 254 th tons of solid fuel are stored in the enterprise. This reserve is enough for 7 days. Abylkair Skakov charged to increase the coal supply at the station.
“It is impossible to simplify the situation. It is necessary to optimize fueling”, akim of the region said to the head of GRES-1.
At GRES-2, the head of the region was informed that they continued to prepare for the construction of the power unit N3. The technical and financial audit of the project is conducted. In addition, more than 7000 tons of equipment from China is expected at the enterprise.
“Not so long ago the Minister of Energy Nurlan Nogayev arrived there. We discussed the project with him. As soon as we complete the correction of the design and estimate documentation, we will give it to the state examination”, the head of the enterprise Vladimir Astashov noted.
At the Ekibastuz combined heat and power plant, akim of the region was reported about the progress of the heating season. People of some multi-story apartment buildings in the city periodically complained of underheating. One of the reasons was the inconsistent connection of pumps to the heating networks, which allowed heating some houses and flats at the expense of others. Abylkair Skakov entrusted to solve the problem.
The head of the region also visited the city police department. According to its head Vasily Sklyar, only two crimes were registered in the city on the first day of 2021. In both cases, the drunk drivers were arrested and suspended the driver’s licenses. In general, the situation in Ekibastuz is stable.