Reconstruction of the Taldykorgan-Kalbatau-Ust-Kamenogorsk highway continues. The Minister of Industry and Infrastructural Development Beibut Atamkulov visited the construction sites and checked the progress of work together with the Chairman of the Committee for Roads of the MIID RK Sairanbek Barmakov and the Chairman of the Board of JSC NC “KazAvtoZhol” Ulan Alipov.

 

In 2017, a large-scale project for the reconstruction of a highway with a length of 763 kilometers began. For three years, the road workers have almost completed work and this year it is planned to open traffic for transport along the entire route. The main purpose of the reconstruction is to transfer the road from the third technical category to the first and second with a widening of the carriageway to ensure safe and uninterrupted traffic.

 

Thus, from Taldykorgan to Ust-Kamenogorsk after completion of reconstruction at an acceptable speed, it will be possible to get in 7-8 hours. It is noteworthy that the route is one of the important arteries leading to the resort area of Lake Alakol, so the implementation of the project is important for the tourism cluster of Kazakhstan. For example, from Ust-Kamenogorsk to the resort area, Kazakhstanis will be able to get in 4-5 hours.

 

The head of the MIID RK visited three reconstruction sites in Almaty and East Kazakhstan regions. Full-scale road construction works are being carried out here, in which about 3,000 people are involved. The general contractors are Todini Central Asia LLP, K-Dorstroy JSC and CITIC Construction Co, LTD.

 

It is worth noting that the major repair works of the Taldykorgan-Kalbatau-Ust-Kamenogorsk highway were last carried out almost 20 years ago.

 

Let us remind that in 2020, Kazakhstan will open traffic on 2600 km of national roads.

 

For reference:

 

In the section of km 287-685 with a total length of 385.3 km in the Almaty region 1,541 people have been mobilized and 860 units of equipment have been involved. In total, since the beginning of the year, road workers have completed 673 thousand cubic meters of earthwork, and work has also been completed on 166 culverts and 23 bridges. In addition, 6.5 km of crushed stone foundation and 5 km of the top layer of asphalt pavement has been completed.

 

Since the beginning of the year, 143 thousand cubic meters of excavation work has been completed and 44 culverts installed on the reconstruction site, km 685-880, with a total length of 195 km in the East Kazakhstan region. Also, the road workers carried out 2.5 km of the placement of crushed stone foundation and 1.5 km of the top layer of asphalt pavement. On this site, 638 people and 320 units of equipment are involved.

 

The reconstruction section, km 880-1073, with a total length of 189 km in the East Kazakhstan region, 182 thousand cubic meters of earthworks have been completed, work has been completed on 89 culverts, 3 bridges, 1 overpass is under construction. Also, 11 km of crushed stone foundation, 6 km of the upper layer of asphalt and 3 km of the lower layer of asphalt concrete pavement have been placed. The site employs 462 employees and 277 units of equipment.