Implementation of the action plan on issues raised at meetings of the akim of Kyzylorda city with the population of the village, rural district, and city as of the IV quarter of 2023 in accordance with the Decree of the President of the Republic of Kazakhstan dated 3 March 2022 No. 826.

№

Event content

Term of execution

Progress of execution

Responsible person

Kyzylorda city

1.  

The issue of holding an inventory of unused garden land plots at the dachas  “Pishchevik” and “Yagodka”

December

Following the resolution of the Akim of the Kyzylorda region dated March 18, 2015 No. 880 and the joint decision of the Maslikhat of the Kyzylorda region dated March 18, 2015 No. 265, the horticultural associations “Pishchevik” and “Yagodka”, located in the western part of the city of Kyzylorda, were assigned to the administrative territory of the city of Kyzylorda with a total area of 13599.5 hectares, these cottages are included to the city limits.

On the territory of these dachas “Pishchevik” and “Yagodka”, appropriate inventory work was carried out, according to the results of which 434 land plots from the territory of the horticultural association “Pishchevik” were transferred to the database of the Unified State Cadastre of Real Estate (USCRE) and the graphic part, of which: 365 land plots were fenced and construction facilities were built.

In addition, 161 plots of land have been transferred to the territory of the horticultural association "Yagodka", according to the USCRE database, construction work has been carried out and 112 fenced land plots have been identified.

D. Tursynabyev

P. Shamuratov

D. Syrlybayev

2.  

The issue of considering the possibility of extending the route of public transport to the cottages “Pishchevik” and “Yagodka” to the inner territory of the cottage

December

The public transport route to the cottages “Pishchevik” and “Yagodka” has been extended to the inner territory at the request of residents.

G.Yerkebay

D. Islamov

Zh. Faizullayev

M. Zhusip

3.  

The issue of ensuring the passage of public transport to the territory of the “Enbek” cottage

December

On the territory of the cottage “Enbek” and cottages PMK-29, and PMK-66 are served by public transport No. 2, 12, 28, 30.

G.Yerkebay

D. Islamov

Zh. Faizullayev

M. Zhusip

4.  

The issue of major repairs in the courtyard of the multi-story residential building No.137 A on Tolebi Street

December

In 2023, 800 million tenges were allocated from the regional budget, and the yards of 18 multi-story residential buildings in the city (Azamat Kurylys LLP) were overhauled. This year, 185.0 million tenges has been allocated from the regional budget for the overhaul of the courtyards of 19 additional multi-story residential buildings, construction, and installation works are currently underway (contractor “DarenStroy” LLP, total project cost: 403.5 million tenges).

Including in the courtyard of the multi-storey residential building No. 137 A on Tole bi Street (the deadline is the end of December).

G.Yerkebay

Zh. Faizullayev

5.  

The issue of taking appropriate measures to restore wells that were not installed following the requirements for the construction of access drinking water pipes to the Orbita cottage

December

Newly conducted drinking water systems for the Orbita cottage located around the city territory were not accepted on the balance sheet of the State Enterprise “Water system”. However, on the part of the enterprise, the Orbita cottage is supplied with drinking water through the “Left bank” with a pumping station for lifting water, located in the Arai area. The contractor restored wells that were not installed during the construction of the entrance drinking water pipes.

G.Yerkebay

D. Islamov

Zh. Faizullayev

B. Abdigapparuly

Tasboget village

6.  

The issue of installing night lights on K. Abenov Street

December

At the expense of the self-government account of the Akim's office of Tasboget village, 8.0 million tenge is provided, work on installing night lights on 3 streets has been fully completed (K. Abenov Street has been introduced).

G.Yerkebay

A. Tynyshtykbai

7.  

The issue of carrying out work on laying stone along the streets of Zh. Duisenbayeva and T. Taimanova

December

In 2023, within the framework of the “Kiyrshyk tas” project of engineering infrastructure in the village of Tasboget, 705.5 million tenge was allocated from the regional budget for laying rubble on 14 streets of the village (including T. Taimanov Street) and 7 streets of Sabalak cottage (including Zh. Duisenbayeva), contractor of Bakadil LLP, Aknur Avto LLP, construction work has been fully completed.

G.Yerkebay

A. Tynyshtykbai

Belkul village

8.  

The issue of building a pedestrian crossing along K. Abdikadyrov Street

2024

Design and estimate documents have been developed for the construction of 1.6 km of pedestrian paths along K. Abdikadyrov Street and a budget application has been submitted to the city budget for 64.3 million tenge.

G.Yerkebay

D. Tursynabyev

G. Baimakhanova

Zh. Sadu

9.  

The issue of laying a pedestrian path 60 meters away at the place of descent from the pedestrian bridge

December

At the place of descent from the pedestrian bridge in the village, a sidewalk (paving stones) is fully installed, and the remains from the central square with the support of sponsors to carry out a pedestrian crossing of 60 meters.

G.Yerkebay

Zh. Sadu

Kosshinyrau Rural District

10.          

Repair of streets, laying of stone in the settlement of Dosan

December

To date, work is underway to lay rubble on 10 streets of the village of Dоsan. The contracting organization of Aknur Auto LLP. Construction work is scheduled to be completed by the end of December.

G.Yerkebay

S. Abdikadyrov

Kyzylzharma rural district

11.          

The problem of continuing the repair work on Seksenbayev Street, which began in the summer, but has not been completed

December

A repeated public procurement competition was held to carry out repair work on Seksenbayev Street, the work was fully completed and put into operation through the winning Contractor Aizon LLP. The cost of the project is 21.0 million tenge.

G.Yerkebay

Sh. Abdirakhmanov

Kyzylozek rural district

12.          

To consider the issue of lighting the “Tagzim Square” located on Abylaikhan Street in the village of Karaozek

December

During the dismantling of lampposts along Argyn Street in the rural district, work is underway to install 2 pieces of remaining night lampposts on Tagzim Square, the work will be fully completed by the end of December.

G.Yerkebay

S. Abdizhappar

 

13.          

The issue of cleaning up the buried sections of the Ortalyk canal located in the rural district

December

The excavation and clearing of the buried sections of the Ortalyk canal in the rural district was carried out entirely through sponsorship.

G.Yerkebay

S. Abdizhappar

Karauyltobe rural district

14.          

The issue of installing additional sports simulators on the territory of the playground located in the center of the rural district

December

The work on laying the rubber coating and installing additional simulators on the territory of the playground located in the center of the rural district was fully carried out by Ali Project Construction LLP (the total cost of the project is 7.0 million tenge).

G.Yerkebay

Е. Akhetov

 

Akzharma rural district

15.          

The issue of installing stops on the territory of the Akzharma rural district

December

In order to install stops in Baimurat Batyr village in the number of 3 pieces, in Taldyaral settlement in the number of 2 pieces, 6,369.0 thousand tenge is provided from the city budget. Currently, the winning contractor is working on the part of IE “Gulim”. Term of completion - the end of December.

G.Yerkebay

S. Abdireev

 

16.          

Carrying out major repairs of dilapidated playgrounds in the rural district

December

In order to lay artificial turf on 3 dilapidated playgrounds in the rural district, 1,118.0 thousand tenge was allocated from the city budget. In accordance with the Law on Public Procurement, installation works by the winning contractor FE “Farabi” have been fully completed.

G.Yerkebay

S. Abdireev

 

Talsuat rural district

17.          

The issue of installing night lights on Street No. 7 in Talsuat Rural District

December

The public procurement tender for the installation of night lights on street No. 7 was announced 2 times, but the winner was not determined. From one source, having concluded a contract with “MK Service-Ltd” LLP, the works were carried out in full (volume of funds 1.8 thousand tenge, number of columns -18).

G.Yerkebay

E. Beisenbayev

18.          

Work on capturing stray dogs

December

Until this period of 2023, a special team was called in where 135 stray dogs were caught. The work in this direction will be carried out during the year.

For Determination:

Kyzylorda City Veterinary Station, the Law of RK from 30 December 2021 №97 “on responsible treatment of animals” came into force, in connection with which the work on catching and destruction of stray dogs and cats is stopped. At present, the catching of aggressive, non-viable cat dogs is carried out, upon written application of the owner of the animal, and in the presence of the local district police inspector, anaesthetisation is carried out at the expense of the enterprise.

G.Yerkebay

N. Tolegenov

(by agreement)

E. Beisenbayev

Aksuat rural district

19.          

The issue of installing a bus stop near school lyceum No. 268 in the rural district

December

In order to install 2 stops from the rural district (near the western entrance of the village and school-lyceum № 268), held a public procurement competition for the amount of 2 million 170 thousand tenges, allocated from the city budget, the winner was determined as individual entrepreneur “Ermek”. At present, the supervisory authority is being established, after the determination of the supervisory institution, the work will be fully completed by the end of December.

G.Yerkebay

N. Bakhyt

 

 

20.          

The issue of night lighting of A. Kudabayev Street in the rural district

December

Within the framework of the program “Auyl - El besigi” to install night lamp posts in 1.4 kilometers on A. Kudabaeva Street allocated 28.4 million tenges, the work is being carried out by the contractor “Ai-Sultan Company” LLP, and the completion date - is the end of December. (To date, 85% of the work has been completed).

G.Yerkebay

N. Bakhyt

 

 

21.          

The issue of construction of a pavement in the area of school No. 268 (between D. Akmurzaeva and B. Zhonbaev Streets)

December

In order to construct pedestrian paths between D. Akmurzaev and B. Zhonbaeva streets, through which students of school-lyceum No. 268 attend school, with the support of sponsors, a pavement (paving stone), leftovers from the central square, was completely installed.

G.Yerkebay

N. Bakhyt

 

 

Дата публикации
22 декабря 2023