Information on the implementation of the action plan on issues raised at the meetings of the Akim of the city of Kyzylorda in the IV quarter with the population of the village subordinate to the city, rural district and city in accordance with the Decree of the President of the Republic of Kazakhstan dated March 3, 2022 No. 826
|
O/N |
Event content |
Term of execution |
Progress of execution |
Responsible officer |
|
Kyzylorda city |
||||
|
1. |
In view of the increase in the number of students at School No. 261 in the Al-Farabi residential area, consider accommodating students in a school located in an adjacent area or constructing an extension. |
July 2023 |
This residential area has a large population. For this reason, in secondary school No. 261, student places exceeding the planned capacity are determined. To solve the shortage of places in school No. 261, a 600-seat school is being built along the Kyzylorda-Zhezkazgan highway. The term of operation of the school is planned to be introduced in 2023. In addition, in the Shanghai microdistrict, on Kultekenova Street, there is a "Baiterek School.kz" the school was put into operation in the 2022-2023 academic year, 62 students study from the residential area of Al-Farabi. For the 2023-2024 academic year "Baiterek School.kz" the number of students in the school is expected to increase. |
A. Kasymova G. Yerkebay Zh. Seilov E. Bogdanov (by agreement) G. Baymakhanova |
|
2. |
The issue of increasing the number of rubbish bins in the Al-Farabi residential area. |
December |
Currently, the State Enterprise "Kyzylorda Su Zhuyesi" systematically organizes work to ensure the sanitary cleanliness of the city streets. Solid household waste from Al-Farabi Street is exported according to the schedule. In addition, the issue of increasing the number of garbage containers in this residential area is being considered. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
3. |
Consideration of lighting on Syganak Street and construction of a pavement. |
March 2023 |
Syganak Street is included in the list of streets requiring the installation of light poles and the construction of sidewalks. At the same time, the amount of funds necessary for the development of design estimates and obtaining the conclusion of a comprehensive examination for the installation of light poles and the construction of a sidewalk on Syganak Street will be calculated, and it will be proposed to allocate funds from the city budget. |
G. Yerkebay Zh . Seilov Zh . Fayzullaev G. Baymakhanova |
|
4. |
The issue of installing a traffic light at S. Lapin Street and Beybitshilik Street. |
March 2023 |
For the installation of a traffic light at S. Lapin Street and Beybitshilik Street a study will be carried out with the relevant specialists and after the survey the street will be included in the list of streets where traffic lights need to be installed around the city. |
G. Yerkebay Zh . Seilov Zh . Fayzullaev G. Baymakhanova |
|
5. |
Consideration of upgrading multi-storey residential building No. 30 in the Titov residential area. |
March 2023 |
A budget request has been submitted for the year 2023 for the overhaul of apartment building No. 30 Titov. The total amount of funds required is 157.4 million tenge. |
G. Yerkebay Zh. Fayzullayev A. Rysbek T. Kulmaganbetov |
|
6. |
Consideration of the construction of a cultural recreation park in the Titov and Gagarin residential areas. |
March 2023 |
For the construction of a cultural park in the residential areas of Titov and Gagarin, work is under way to provide entrepreneurs with vacant land in the yard of the M. Yeralieva Culture House, located on Kashaubayev Street. |
G. Yerkebay A. Kasymova Zh . Seilov Zh.Tazhmakhanov G. Omarov A. Anuar J. Fayzullaev B. Amangeldiev G. Baymakhanova |
|
7. |
Consideration of repairing the roof of multi-storey residential building No. 15 " B " on A. Kashaubaev Street. |
July 2023 |
In accordance with Article 32 of the Law of the Republic of Kazakhstan "On Housing Relations", it is stated that the owners of apartments and non-residential premises are obliged to take measures to maintain the common property of the condominium object and ensure its safe operation, including carrying out current and major repairs of the common property of the condominium object. Also, together with the established working group, relevant specialists conducted explanatory work on the norms of the law for owners of apartment buildings. Nevertheless, for the repair of the roof of the apartment building No. 15 "B" on Kashaubaeva St., with the sponsorship of entrepreneurs, appropriate work will be carried out. |
G. Yerkebay Zh. Fayzullayev A. Rysbek T. Kulmaganbetov |
|
8. |
Carrying out specific measures to study and improve the quality of drinking water in multi-storey residential buildings located in the residential area of Arai. |
December |
In order to improve the quality of drinking water supplied to the residential area of Arai, the State Enterprise “Kyzylorda Su Zhuyesi” approved in November an action plan for cleaning and flushing clean water tanks of the “Arai” intake structure, which provides this area with drinking water. According to this event, work was carried out on cleaning, washing and neutralization of 2 pieces of clean water tanks with a volume of 1000 m3 each. In the future, it is planned to carry out a complete flushing, disinfection of drinking water systems of residential areas “Arai 2” and “Arai 3” with the installation of drain wells. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
9. |
Consideration of connecting M. Abdrazakov Street to the centralised sewage system. |
July 2023 |
On the part of the State Enterprise "Kyzylorda Su Zhuyesi", together with the Department of Urban Construction, studies and clarifications are being carried out on connecting M. Abdrazakov Street to a centralized sewerage system. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
10. |
The issue of cleaning the “Sarkyrama” canal. |
April 2023 |
The contractor organization for the maintenance of the irrigation systems of the “Sarkyrama” canal will regularly carry out cleaning work in the spring period. |
G. Yerkebay Zh. Fayzullayev |
|
11. |
The issue of building an irrigation water ditch on Tauke Khan Street. |
March 2023 |
In order to bring the ditch water to Tauke Khan Street, the amount of necessary funds will be calculated and a proposal will be submitted to the city budget in the future. |
G. Yerkebay Zh . Seilov Zh . Fayzullaev G. Baymakhanova |
|
12. |
Complete gas supply to the “Zhastar Uyi” multi-storey residential building and renovation of the windows located in the entrance hall. |
March 2023 |
In order to fully supply gas to the multi-storey residential building "Zhastar uyi", design and estimate documentation has been developed and submitted for state examination. In addition, calculations will be made for the entrance windows of this multi-storey residential building and appropriate repairs will be made by the sponsored entrepreneur. |
G. Yerkebay Zh . Seilov A. Rysbek Zh . Fayzullaev G. Baymakhanova |
|
13. |
The problem of installing an artificial road barrier at the intersection of E. Ernazarov and S. Toraigyrov Street. |
December |
Employees of the Department of Internal Affairs carried out work on the study of the installation of artificial road barriers at the intersection of Yernazarov and S. Toraigyrov streets and included in the plan for 2023 in the list of streets and dead ends requiring the installation of artificial irregularities. In order to carry out these works, calculations will be prepared, and a budget application will be sent in the future. |
G. Yerkebay Zh . Fayzullaev A. Zhanazarov (by agreement) |
|
14. |
Consideration of upgrading multi-storey residential building No. 18 "A" in the Merey neighbourhood. |
July 2023 |
On the basis of the state program of Housing and communal development "Nurly Zher" for 2020-2025, a budget application for 2023 was submitted in order to carry out major repairs of the multi-apartment dormitory No. 18a of the Merey microdistrict. The amount of necessary funds is 64.0 million tenge. |
G.Yerkebay Zh. Fayzullayev A. Rysbek |
|
15. |
The issue of installing and equipping children's playgrounds in the yard of multi-storey residential building 80 "A" on S. Toraigyrov Street. |
December |
Currently, 38 sports and children's playgrounds are being built in the city. Of these, 28 sports and children's playgrounds have been completed and put into operation. A playground has been installed on the adjacent territory of the multi-apartment residential building No. 80 "A" on Toraigyrov Street of the city with the support of individual entrepreneurs, but it has become outdated due to careless operation. Currently, this playground is being renovated by an individual entrepreneur. |
G.Yerkebay Zh. Fayzullayev |
|
16. |
Consideration of building a pavement on Karatogai Street. |
July 2023 |
Karatogai Street is included in the list of streets requiring the construction of a sidewalk in the city. At the same time, the amount of funds necessary for the development of design estimates and obtaining the conclusion of a comprehensive examination for the construction of a sidewalk on Karatogai Street will be calculated, and in the future it will be proposed to allocate funds from the city budget. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova |
|
17. |
Consideration of the issue of installing a traffic light at the intersection of K. Makhambetov and Karatogai streets. |
March 2023 |
On the issue of installing a traffic light at the intersection of K. Makhambetov and Karatogai streets, relevant specialists will carry out work on the study, after conducting a survey of the city, they will be included in the list of streets on which it is necessary to install a traffic light. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev A. Zhanazarov (by agreement) G. Baymakhanova |
|
18. |
The issue of issuing a technical passport to residents of a multi-storey residential building No. 6 of the Left-Bank quarter 4 (houses issued by the category of socially vulnerable groups). |
January 2023 |
4th quarter on the left bank №6, №4, №8, №9 the state registration of the land act, technical passport of multi-storey residential buildings has been developed and carried out. In order to transfer to the balance of the relevant institution, work is being carried out jointly with the city finance department. In the future, it will be carried out according to the tolling act. |
G. Yerkebay A. Anuar |
|
19. |
The issue of locating a social shop in the Left Bank residential area. |
December |
In order to stabilize socially significant food products, a social store near the house Left Bank No. 22, has been operating on a permanent basis since April 2022. In addition, in December of this year, a social corner will be opened in the residential area of the Left Bank, the “Kyzylorda Optomarket” trading house, located next to the Bolashak University building. In addition, additional land plots from this residential area are being specified. |
Zh. Seilov N. Azirbek B. Amankeldiev S. Yerniyazov (by agreement) G. Kozhakhmetov G. Omarov |
|
20. |
The issue of installing a fence and special places for solid waste disposal in the Baiterek neighbourhood. |
December |
Special places for solid household waste disposal have been installed in the Baiterek microdistrict, fencing works have been carried out. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
21. |
The issue of willow planting in the entrance lands of Kyzylorda city. |
March 2023 |
In 2023, a budget application for the planting and maintenance of willow trees for the upcoming 2023 will be submitted to the city of Kyzylorda. The required amount of funds is 10.0 million tenge. |
G. Yerkebay Zh. Fayzullayev |
|
22. |
Organisation of drug abuse control and prevention activities around the city. |
December |
Employees of the Police Department of the city of Kyzylorda (ex.letter dated 12/15/2022 No. 2-23/19814) organized measures to combat and prevent drug addiction, the results of which are being investigated. In addition, the schools of the Kyzylorda City Department of Education are working on the basis of a joint action plan for 2022 on preventive measures “prevention of drugs and drug addiction”, developed with the aim of forming a retarding force in the younger generation in the fight against drug addiction with the introduction into everyday life of new initiatives to combat the disease of the XXI century at the global level. In all educational organizations, orders have been issued on the organization of the work of an intra-school and classroom narcological post, which forms the introduction of students to the skills of a healthy lifestyle and the prevention of abuse of funds that negatively affect the moral and psychological nervous system, managers and members of the drug point have been appointed. Corners of drug stations have been created in the walls of schools and classrooms. Legal hours were held among students of grades 8-11 on the prevention of smoking, vaping. Documentaries “drug addiction – the disease of the century”, “about the harm of smoking for the body”, “about the dangers of gambling, drug addiction” were shown at the class hours. Contests and sports competitions on the formation of a healthy lifestyle were held in all secondary education organizations. In particular, sports competitions on the theme “Drug Addiction is the disease of the century” (togyzkumalak, chess, checkers), “ Sport is against drugs!” sports games (volleyball, basketball, football, hand ball, table tennis), national sports game “Healthy generation”, “we are for a healthy lifestyle!” poster contest “life without drugs is a miracle!” video contest “No drugs!” flash mobs on the topic “let's lead a healthy lifestyle!” seminar, debate “child's health is most important”, debate “no drugs!” organized essay contests. |
A. Kasymova A. Ormanov E. Bodanov (by agreement) A. Zhanazarov (by agreement) |
|
23. |
Consideration of free public transport for 50% of pensioners, 100% of citizens with disabilities. |
March 2023 |
Currently, by a joint resolution and decision of the Akimat of the city of Kyzylorda and the Kyzylorda city Maslikhat, for free travel by public transport to citizens with visual impairments in the city, it has been sent to carriers for execution. At the same time, in 2023, a calculation will be developed and a proposal will be made for free travel in public transport to pensioners of the city and other categories of citizens with disabilities. |
G. Yerkebay Zh. Fayzullayev M. Zhusip |
|
Belkul village |
||||
|
24. |
Consideration of renewal of electric poles of Zheruyyk, Saryarka, Birlik streets. |
July 2023 |
The state expertise of design and estimate documentation for the renovation of electric poles of Zheruyyk, Saryarka, Birlik streets has been developed and carried out. The amount of necessary funds for the work is 76.0 million tenge. |
G. Yerkebay Zh . Seilov A. Anuar G. Baymakhanova Zh . Sadu |
|
25. |
Consideration of the construction of a cultural centre in the village of Belkul. |
July 2023 |
On the issue of the construction of a house of culture in the village of Belkol, a state examination of design and estimate documentation was developed and carried out through the regional construction department. A budget application was submitted to the Regional Department of Economics and Budget Planning for the necessary funds – 604.0 million tenge. |
G. Yerkebay A. Kasymova J. Seilov A. Anuar G. Baymakhanova Zh . Sadu |
|
26. |
The issue of lighting from Zelenaya Street to School No. 189. |
March 2023 |
A proposal has been submitted to the city budget for the upcoming 2023 for lighting work from Zelenaya Street to School No. 189. The amount of necessary funds is 3.0 million tenge. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova Zh. Sadu |
|
27. |
The issue of the overhaul of Birkazan Street in Birkazan Township. |
July 2023 |
The state examination of design and estimate documents related to the overhaul of Birkazan Street in the settlement of Birkazan has been developed and carried out. The amount of necessary funds is 39.0 million tenge. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova Zh. Sadu |
|
28. |
Consideration of repairing the roof of the apartment building No. 12 in the village. |
March 2023 |
In accordance with Article 32 of the Law of the Republic of Kazakhstan "On Housing Relations", it is stated that the owners of apartments and non-residential premises are obliged to take measures to maintain the common property of the condominium object and ensure its safe operation, including carrying out current and major repairs of the common property of the condominium object. Also, together with the established working group, relevant specialists conducted explanatory work on the norms of the law for owners of apartment buildings. However, for the repair of the roof of apartment building No. 12 in the village, in case of sponsorship from entrepreneurs, appropriate work will be carried out. |
G. Yerkebay Zh. Fayzullayev A. Rysbek T. Kulmaganbetov Zh. Sadu |
|
29. |
Consideration of balancing the bow area. |
March 2023 |
Work is underway to clarify, review work on balancing the area of the bow in the village. After determining the amount of appropriate funds for these works, the paperwork will be carried out in the coming 2023. |
G. Yerkebay Zh. Sadu |
|
Tasboget village |
||||
|
30. |
Consideration of the issue of assigning the status of "Human settlement" to the Sabalak suburban area. |
July 2023 |
The Master Plan of the city of Kyzylorda in 2019 was amended accordingly and approved by the Decree of the Government of the Republic of Kazakhstan dated 06.06.2019 No. 374. The validity period is 2025. As part of the Master Plan, which has been amended, the Sabalak region is included in the “Dacha” report. Given that the relevant changes to the General Plan of the city as a whole were made in 2019, there is a risk that the changes will be ineffective with the allocation of additional funds in the near future. Therefore, in order to effectively spend the funds allocated from the budget, the issue of changing the status of “dachas” within the boundaries of the “Sabalak” region and the city to a “microdistrict” is being considered to review the newly developed master plan for 2025. |
G. Yerkebay G. Omarov G. Kozhakhmetov S. Syzdykov |
|
31. |
Consideration of the construction of a new polyclinic in the village of Tasboget. |
July 2023 |
In order to positively resolve the issue of the construction of a new model city polyclinic in the village of Tasboget, the Health Department of the Kyzylorda region /ex. letter No. 11-13/5765, 12/20/2022/ in the future, work is underway to implement through private investors or at the expense of the republican budget. |
G. Yerkebay A. Kasymova Zh. Seilov A. Anuar S. Pazilov (by agreement) G. Baymakhanova S. Syzdykov |
|
32. |
Consideration of the construction of a sports complex in the village of Tasboget. |
July 2023 |
A land plot for the construction of a sports and recreation complex of a new modern project has been identified in the village, design and estimate documentation has been developed. The conclusion of the state expertise on the construction of a sports complex in the village of Tasboget in 2020 was received. The required amount of funds is 559.9 million tenge. |
G. Yerkebay Zh . Seilov A. Kasymova A. Anuar A. Ormanov G. Baymakhanova S. Syzdykov |
|
33. |
Consideration of asphalting or paving of S. Maikanova and Makhambetov Streets in the village. |
July 2023 |
Design and estimate documents have been developed for the work on laying rubble on 7 streets of the village (Seifullin, Muratbayev, Makhambetov, Moldagulova, Maykanova, Duisenov, Uteuov) and a positive expert opinion has been received. Now an application has been submitted to the regional budget for the implementation of the project for a total amount of 251.9 million tenge. The terms of the design and estimate documentation is 2022-2025. |
G. Yerkebay Zh . Seilov Zh . Fayzullaev A. Anuar G. Baymakhanova S. Syzdykov |
|
Rural district Kyzylzharma |
||||
|
34. |
Consideration of the construction of a 900-seat school in the Kyzylzharma rural district. |
July 2023 |
Currently, on the basis of the "Zhaily mektep project, projects of 11 schools in the region have been approved from the republican budget. It is planned to build 8 schools in the city of Kyzylorda in 2023 and the construction of a 900-seat school was introduced in the Kyzylzharma rural district. |
G. Yerkebay A. Kasymova Zh. Seilov E. Bogdanov (by agreement) A. Anuar G. Baymakhanova M. Seilov |
|
35. |
The issue of strengthening internet connectivity in some areas of the rural district. |
December |
At the beginning of 2022, “Beeline” and “Altel” telecom operators were issued a letter of recommendation for the construction of Internet poles. To date, the city Department of Architecture and Urban Planning has secured a special land. Currently, these telecom operators are legalizing state registration documents. After legalization in 2023, “Beeline” and “Altel” telecom operators will begin work on installing an Internet tower in rural districts. |
B. Akhmet N. Saduakas M. Seilov |
|
36. |
Consideration of asphalting of A. Menlibayeva Street. |
July 2023 |
For 2023, 591.7 million tenge is provided for the average repair of roads on 23 streets of the rural district within the framework of the "Auyl el Besigi" program. This list also includes A. Menlibayev Street, funds-23.4 million tenge. The work will be carried out in the upcoming 2023. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova M. Seilov |
|
37. |
Consideration of construction of pavements on R. Batyrbaev, K. Seksenbaev, Al-Farabi, A. Doskhozhin, A. Abenov, Y. Zhakhaev, A. Kunanbaev streets. |
July 2023 |
In 2019, design and estimate documentation was developed for the construction of a sidewalk on 5 main streets with access to social facilities in the village. However, due to the expiration of the project documentation, a budget application has now been submitted to the city Department of Economics and Budget Planning to carry out work on updating the design and estimate documentation, 4.0 million tenge is provided for the development of design and estimate documentation for 2023. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova M. Seilov |
|
38. |
Works to restore drinking water pressure in apartment building No. 2 on R. Batyrbaev Street. |
December |
To restore the normal pressure of drinking water in the apartment building No. 2 of the Batyrbayev st., work is currently underway on the installation of a special pump by the “Kyzylorda Su Zhuyesi” State Enterprise. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov M. Seilov |
|
39. |
Consideration of the construction of a sports complex in the Kyzylzharma rural district. |
July 2023 |
Currently, a new sports school is being built on the site of the old kindergarten under the administration of the rural district. In the summer of 2023, construction works will be completed and a sports school will be put into operation. The customer is the city construction department, the designing institution: "Proectservice" LLP estimated cost of 2.9 billion tenge, received the conclusion of the state examination /No.19-0372/20/ dated 10/22/2020. |
G. Yerkebay A. Kasymova Zh. Seilov A. Anuar A. Ormanov G. Baymakhanova M. Seilov |
|
40. |
Consideration of extending the public transport route in the direction of No. 15 to the dispensary in the rural district. |
December |
Currently, on the issue of extending the public transport route in the direction of No. 15 to the outpatient clinic in the rural district, work is underway on a new review of the road scheme. |
G. Yerkebay Zh. Fayzullayev M. Zhusip M. Seilov |
|
Rural district of Kosshynyrau |
||||
|
41. |
Provision of Dosan village with an electricity grid as required. |
July 2023 |
In order to provide the village of Dosan with the necessary power grid, the urban construction department has developed design and estimate documentation and received a positive conclusion of the state expertise. The amount of necessary funds for construction works is 428.0 million tenge, currently an application has been submitted to the republican budget. |
G. Yerkebay A. Anuar E. Kalenov (by agreement) S. Abdykadyrov |
|
42. |
Documenting the canal bridges in Abay village /Bridge over Altynbay, Zhappar canal, bridge over the intake canal of the Zhappar canal, two bridges over the intake canal of the Yeshpan canal/ and taking appropriate action. |
July 2023 |
In execution A bridge in the village of Abai /Altynbay, along the Zhappar canal, a bridge in the intake canal of the Zhappar canal, two bridges in the intake canal of the Yeshpan canal/ studies have been carried out in order to issue documents for bridges on canals. Currently, the documents for the recognition of ownerless property have been submitted to the Kyzylorda City Department of Justice. |
G. Yerkebay Zh. Fayzullayev Zh. Nurymbetov (by agreement) A. Zhylkaidarov (by agreement) S. Abdykadyrov |
|
43. |
The problem of restarting the light fittings on the electrical columns under the Stalin canal. |
December |
Floodlights on electric columns located near the bridge of the Stalin Canal are fully activated. |
G. Yerkebay Zh. Fayzullayev E. Kalenov (by agreement) S. Abdykadyrov |
|
Rural district of Karauyltobe |
||||
|
44. |
Consideration of converting a cultural centre under construction from diesel to a gas-fuelled device. |
December |
Work is underway to study the issue of transferring the house of culture under construction from diesel fuel to a gas device. |
G. Yerkebay A. Anuar E. Akhetov |
|
45. |
Carrying out works on laying rubble on the newly populated territory (12 streets). |
July 2023 |
The design and estimate documentation has been developed and the conclusion of the state expertise has been obtained for the work on laying rubble on 12 streets with a total length of 9 km. Currently, a public procurement tender has been announced on a transitional basis for 2022-2023. The cost of the project is 319.0 million tenge. In the future, after determining the winner, construction and installation work will be carried out. |
G. Yerkebay Zh. Seilov A. Anuar G. Baymakhanova E. Akhmetov |
|
46. |
Consideration of asphalting of the Zheltoksan Street. |
July 2023 |
To carry out the asphalting of Zheltoksan Street with a length of 1.35 km, a budget application for support under the “Auyl el Besigi” program was sent. The project cost is 29.4 million tenge. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova E. Akhetov |
|
Rural district Akzharma |
||||
|
47. |
Consideration of the construction of an outpatient clinic in the rural district. |
July 2023 |
The design and estimate documentation for the construction of a medical outpatient clinic in the village of Baymurat Batyr rural district was prepared, a positive conclusion of the state examination was received /No. 0037/220/ dated 17.03.2022/ For a total amount of 422.0 million tenge, documents were submitted to the regional construction department. |
G. Yerkebay A. Kasymova Zh. Seilov A. Anuar S. Pazylov (by agreement) G. Baimakhanova S. Abdireev |
|
48. |
Consideration of the construction of wells in the newly constructed area in the settlement of Taldyaral. |
March 2023 |
A tender notice in accordance with the law on public procurement in the amount of 15 million tenge was submitted for the development of design and estimate documentation for the installation of a well on the newly built territory in the Taldyaral settlement. |
G. Yerkebay Zh. Fayzullayev A. Yessenov (by agreement) G. Baimakhanova S. Abdireev |
|
49. |
The issue of carrying out a survey and identification of rangeland habitats in the Taldyaral settlement. |
December |
Work is underway to survey the pasture lands of cattle in the Taldyaral settlement. In addition, in the autumn, ways of using agricultural land for pasture purposes are envisaged. |
G. Yerkebay S. Abdireev G. Omarov |
|
50. |
Installation of newly installed electricity meters (smart meters) on electricity poles in an accessible location. |
January 2023 |
Work on the installation of newly installed electric meter devices (smart meter) on electric poles in an accessible location is scheduled for January and February 2023. |
G. Yerkebay Zh. Fayzullayev B. Karakozov (by agreement) S. Abdireev |
|
51. |
The issue of strengthening internet connectivity in some areas of the rural district. |
December |
In order to strengthen the Internet connection in some territories of the rural district, special letters were sent to the Interregional Communications Inspectorate of the Telecommunications Committee for Shymkent, Zhambyl, Turkestan and Kyzylorda regions and telecom operators TELE2, Activ. Resolute work is currently underway. |
B. Akhmet N. Saduakas S. Abdireev |
|
Rural district of Kyzylozek |
||||
|
52. |
The issue of regulating public transport intervals in the rural district (runs until midday). |
December |
In December of this year, a new public transport route No. 29 was opened through “Kyzylorda Bus Park” LLP. Public transport runs 3 times a day to the Kyzylozek rural district. |
G. Yerkebay Zh. Fayzullayev M. Zhusip S. Abdyzhappar |
|
53. |
Carrying out repair work on the wiring of electrical networks in the locality and consideration of service vehicles for electricians. |
July 2023 |
In order to develop design and estimate documentation for the reconstruction of electrical networks in the locality, an application was submitted to the city budget. The project cost is 6.1 million tenge. Installation works are planned for May-June 2023. In addition, electricians will be provided with centralized service vehicles in case of emergency situations. |
G. Yerkebay Zh. Fayzullayev E. Kalenov (by agreement) S. Abdyzhappar |
|
54. |
Consideration of building a pavement in the streets of the rural district. |
July 2023 |
In order to implement this issue, design and estimate documentation has been developed for the construction of a sidewalk along Abylaikhan Street in the rural district, an application has been submitted to the city budget. The project cost is 21.6 million tenge. Other streets of E. Dautbayev, Sh. Ibraeva will be gradually included in the list of streets on which the sidewalk will be built in the future. |
G. Yerkebay Zh. Seilov A. Anuar Zh. Fayzullayev G. Baymakhanova S. Abdyzhappar |
|
55. |
Consideration of repairing the “Kozhak” bridge on the access road in the rural district. |
July 2023 |
An application has been submitted to the city budget for the allocation of 5.2 million tenge necessary for the development of design and estimate documentation for the overhaul of the “Kozhak” bridge across the access road in the rural district. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova S. Abdyzhappar |
|
Rural district Talsuat |
||||
|
56. |
The issue of coverage of the newly built area by the electricity grid. |
July 2023 |
In order to provide the newly built territory with an electric grid, design and estimate documentation for this territory has been developed. Currently, an application has been sent to the republican budget. If funds are allocated, construction work will be carried out. The customer is the city construction department. An agreement has been concluded with the designing institution: “Dimash Service” LLP. The estimated cost is 69.7 million tenge, the conclusion of the state examination was received /dated 24.08.2022, No. MARAT-0053/22/. |
G. Yerkebay Zh. Seilov A. Anuar Zh. Fayzullaev E. Kalenov (by agreement) G. Baymakhanova A. Zhylkybai |
|
57. |
Consideration of the issue of blocking the newly dug canal on the Syrdarya River and pumping water along the old riverbed passing by the village in order to solve the problem of irrigation water in the rural district. |
March 2023 |
The letter of the Aral-Syrdarya basin Inspectorate for the regulation of the use and protection of water resources of the Republic of Kazakhstan dated 09.02.2022 No. 03-8/651 states that in 2007-2008, work was carried out to correct the riverbed in the village area due to the threat to the Talsuat rural district, horticultural associations and other objects of the national economy from the Syrdarya River. The risk of flooding may increase if the riverbed is restored again. |
G. Yerkebay Zh. Fayzullayev Zh. Nurymbetov (by agreement) S. Nurymbetov (by agreement) A. Zhylkybay |
|
58. |
The issue of the proper installation of electricity networks and asphalting along Syrdarya Street and No. 7. |
July 2023 |
In order to provide electricity to the newly built territory in the rural district /Syrdaria Street, No. 7 are also on the list/ design and estimate documentation has been developed. The customer is the city construction department. The project institution has signed a contract with Dimash Service LLP. The estimated cost is 69.7 million tenge, the conclusion of the state examination was received /dated 08/24/2022 No. MARAT-0053/22/. Currently, an application has been sent to the republican budget. If funds are allocated, construction work will be carried out. |
G. Yerkebay Zh . Seilov Zh . Fayzullaev A. Anuar G. Baymakhanova E. Kalenov (by agreement) A. Zhylkybai |
|
59. |
The problem of ensuring the safety of students at lunchtime and in the evenings of secondary school No. 178 which is located on Abai Street. |
December |
In secondary school No. 178 of the city Department of Education, located in Talsuat rural district, from 07.30 to 08.00 in the morning, from 13.30 to 14.00 and from 18.30 to 19.00 in the evening, a duty schedule of male teachers has been drawn up. On duty from September 1, 2022-2023 academic year. During the school visit and return from school, the duty will be continued for safety reasons when students attend classes. In addition, road barriers and a road sign are installed in 2 places at the school. Ensuring the safety of students in this school is entrusted to the district police inspector N.Smagulov and the officers on duty of the patrol police battalion (outgoing letter dated 12/15/2022 No. 2-23/19814). |
A. Kasymova E. Bogdanov (by agreement) A. Zhanazarov (by agreement) A. Zhylkybai |
|
60. |
Consideration to install night lighting fixtures on the pavement along the “Kyzylorda-Jalagash” highway to 3 social facilities under the responsibility of the “Oblast Employment and Social Programmes Coordination Department”. |
July 2023 |
At the beginning of the year, the office of the akim of the Talsuat rural district submitted design and survey reports, a letter from the city department of Housing and Communal Services, passenger transport and highways /dated 09.02.2022 N01-03/160 / submitted a budget application for the development of design and estimate documentation in the amount of 3.0 million tenge for the installation of lighting and the sidewalk device for 1240 meters was supported. In 2023, design and estimate documentation with expertise will be developed and a budget application will be submitted. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova A. Zhylkybay |
|
Rural district Aksuat |
||||
|
61. |
Consideration of building a sports complex in the rural district. |
July 2023 |
In execution The corporate fund "Samruk-Kazyna Trust" plans to build a sports complex with an area of 720 square meters in the amount of 239 million tenge from the center of the rural district. Currently, the equipment necessary for construction has been delivered. Construction work of the sports complex is planned to begin this year and put into operation in 2023. |
G. Yerkebay A. Kasymova Zh. Seilov A. Anuar A. Ormanov G. Baymakhanova M. Akmyrzayev |
|
62. |
The issue of providing electricity to residential buildings on U. Tokmaganbetova Street (transformer modernization). |
December |
In execution Design and estimate documentation has been prepared for the repair of transformers located in the rural district, and materials necessary for regulating electrical networks along U. Tokmaganbetova Street have also been ordered. The work will be carried out in January 2023. |
G. Yerkebay A. Anuar Zh. Fayzullayev E. Kalenov (by agreement) M. Akmyrzayev |