Information on the implementation of the action plan on issues raised at the meetings of the Akim of the city of Kyzylorda in the III quarter with the population of the village subordinate to the city, rural district and city in accordance with the Decree of the President of the Republic of Kazakhstan dated March 3, 2022 No. 826
|
O/N |
Event content |
Term of execution |
Progress of execution |
Responsible officer |
|
Kyzylorda city |
||||
|
1. |
Consideration of the issue of external repair of apartment buildings No. 4a, No. 11 in the Syrdarya microdistrict |
November |
Special equipment was transferred to the exterior repair work of apartment buildings No. 4a, No. 11 of the Syrdarya microdistrict, repairs were made at the expense of the owners' own funds. |
G. Yerkebay Zh . Seilov Zh . Fayzullaev A. Rysbek T. Kulmagambetov G. Baymakhanova |
|
2. |
Consideration of special equipment (crane) for repair work in multi-storey residential building No. 9 of the Syrdarya microdistrict |
September |
Special equipment (crane) has been allocated for the current repair of the apartment building No. 9 of the Syrdarya microdistrict. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
3. |
The issue of installing benches for city residents on the pavement on S. Beybarys Street, from Bekshora Street to N. Nazarbayev avenue |
October |
Works have been carried out on the construction of 2 recreation areas for residents of the city at pedestrian crossings from S. Beybarys Street, Bekshora Street to N.Nazarbayev Avenue. Contractor organization is "SKB CONSTRUCTION" LLP. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova |
|
4. |
The issue of cleaning works inside aryks in the Syrdarya microdistrict |
September |
Cleaning works were carried out inside the irrigation ditches in the Syrdarya microdistrict by "Kyzylorda Tazalygy" LLP. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
5. |
The issue of trapping wild dogs and cats in the city |
In a permanent order |
According to the information of the State Enterprise "Kyzylorda City Veterinary Station" of the Veterinary Department of the Kyzylorda region /dated 12.09.2022 No.01-409/, on March 2, the Law of the Republic of Kazakhstan No. 97 "on responsible treatment of animals" of December 30, 2021 came into force, work on catching and destroying wild dogs and cats was suspended. However, at present, according to the written statement of the owners of aggressive, unable to survive dogs and cats, as well as with the participation of the district police of the State Enterprise "Kyzylorda City Veterinary Station" conducts trapping and disinfection. |
Zh. Seilov N. Azirbek N. Tulegenov (by agreement) |
|
6. |
Consideration of reconstruction (modernisation) of apartment building No. 28 on Bekturganov Street |
December |
In order to modernize the multi-apartment residential building No. 28 on Bekturganov Street in 2021, design and estimate documentation was developed and an application for 63.0 million tenge was submitted to the republican budget. After considering the source of funds, construction and installation work will be carried out. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev A. Rysbek G. Baymakhanova |
|
7. |
The issue of installing a special railing inside and in front of the entrance of apartment building No. 17 " B ", Yesenov str. |
September |
Works on the installation of railings inside and in front of the entrance of the apartment building No. 17 "B" on Yesenov Street were carried out by the State Enterprise "Kyzylorda su Zhuyesi". |
G. Yerkebay Zh. Fayzullayev A. Rysbek |
|
8. |
Question about the launch of 4 night lights installed on the playground in the courtyard of the apartment building No. 17 "B" on Yesenov St. |
September |
The night lighting fixtures of the playground in the courtyard of the apartment building No. 17 "B" on Yesenov St. are fully launched by the institution of the SLLP "Energoservice". |
G. Yerkebay Zh. Fayzullayev E. Yessenbayev (by agreement) |
|
9. |
Works on cleaning the basement of an apartment building No. 18 on G. Musirepov Street from water and garbage |
September |
The corresponding work on cleaning the basement of the apartment building No. 18 on G.Musirepov Street from groundwater and garbage was carried out by CAO "Azamat". |
G. Yerkebay Zh. Fayzullayev A. Rysbek |
|
10. |
Carrying out works on the arrangement of the sewage system of an apartment building No. 20 on G. Musirepov Street |
October |
The multi-apartment residential building No. 20 on G. Musirepov Street in 2020 was financed from the republican budget and major repairs were carried out. Currently, the relevant specialists have investigated the defect in the basement and carried out restoration work /the old sewer network has been cut down, the drainage system in the basement has been completely stopped/. |
G. Yerkebay Zh. Fayzullayev A. Rysbek |
|
11. |
The issue of cleaning, poisoning of tick-borne insects on the roofs of apartment buildings No. 10, No. 52 of the Shugyla microdistrict |
September |
In accordance with Article 32 of the Law of the Republic of Kazakhstan "On Housing Relations", owners of apartments and non-residential premises are obliged to take measures to maintain the common property of the condominium object and ensure its safe operation, including carrying out current and major repairs of the common property of the condominium object. In addition, the management body of the condominium of apartment buildings No. 10, No. 52 of the Shugyla microdistrict is LLP "Kyzylorda su zhuyesi". In this regard, the managing body of the condominium facility, together with the owners, carried out work on cleaning the roof from ticks. |
G. Yerkebay A. Rysbek E. Uzakbayev (by agreement) |
|
12. |
Carrying out garbage collection (asphalt residues) in the courtyards of apartment buildings No. 3,5,7 of the Shugyla microdistrict |
September |
Cleaning of garbage (asphalt residues) in the courtyards of apartment buildings No. 3,5,7 of the Shugyla microdistrict was completely carried out by the State Enterprise "Kyzylorda su Zhuyesi". |
G. Yerkebay Zh. Fayzullayev A. Rysbek T. Kulmaganbetov |
|
13. |
Consideration of the issue of drinking water from an apartment building No. 51 in the Shugyla micro-district to the private sector (residential buildings No. 122, 124 on Bukharbai Batyr Street) |
September |
In 2010, due to the lack of connection points to the centralized drinking water supply of residential buildings No. 122, No. 124 of Bukharbai Batyr, a technical condition was issued by the State Enterprise "Kyzylorda su Zhuyesi" for connecting drinking water supply to residential house No. 51 of the Shugyla microdistrict. According to the residents of the apartment building No. 51 of the Shugyla microdistrict, currently, due to the presence of other points of connection of the centralized water supply, the owners of residential buildings No. 122, No. 124 were warned about the need to connect to another nearby water supply. In case of non-compliance, the owners will be disconnected from the water supply of the apartment building No. 51. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
14. |
Work on putting the electrical networks in order near the apartment building No. 54 of the Shugyla microdistrict |
September |
Works were carried out by the repair team of the city power grid management to arrange the laid electrical wires between two poles in front of apartment buildings No. 51,52,54 of the Shugyla microdistrict. |
G. Yerkebay Zh. Fayzullayev E. Yessenbayev (by agreement) |
|
15. |
Consideration of creating conditions for the public to use the recreation area in the courtyard of the Zhas Orda housing complex (water park) in the Shugyla neighbourhood |
September |
On July 31, 2015, by the decree of the Akimat of the city of Kyzylorda, the water park located in the Shugyla microdistrict was put into operation for 10 years to the enterprise "City Houses of Culture, clubs and folk collectives" of the city Department of Culture and Language Development. At the same time, an agreement has been concluded with the establishment of the IE "Zhas Orda" for the creation of a recreation and wellness area on this territory. The resolution of the Akimat of the city is valid until May 25, 2025. In this regard, a meeting was held with the mentioned entrepreneur, who informed that from May 2023 he would work on the development of a recreation area (water park). |
A. Kasymova Zh. Tazhmakhanov |
|
16. |
Work on cleaning the basement of an apartment building No. 21 of the Akmeshit microdistrict from water and garbage |
September |
On the part of the State Enterprise "Kyzylorda su Zhuyesi", the basement of the apartment building No. 21 of the Akmeshit microdistrict was cleaned accordingly. That is, the faulty pipeline from the basement to the inspection well has been replaced, and the waste water has been removed by a pump. |
G. Yerkebay Zh. Fayzullayev A. Rysbek T. Kulmaganbetov |
|
17. |
Cleaning of irrigation water supply systems in the yard of apartment building No. 12 in Akmeshit microdistrict |
September |
LLP "Kyzylorda tazalygy" carried out cleaning of irrigation water networks in the courtyard of an apartment building No. 12 of the Akmeshit microdistrict. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
18. |
Consideration of the issue of reconstruction (modernization) of an apartment building No. 29 of the Akmeshit microdistrict |
December |
In order to modernize the multi-apartment residential building No. 29 of the Akmeshit microdistrict, a budget application was submitted in 2020 and finances were allocated. However, there were disagreements on the part of the residents and they refused major repairs. To carry out major repairs of dilapidated apartment buildings located in the city of Kyzylorda, where there are currently problems with the basement, a leaky roof, a faulty sewer pipeline, explanatory work will be carried out with the owners of apartments of a residential building, as well as a survey will be conducted with the written consent of 70% of residents and signatures will be collected that they have "no objections" to the modernization of the residential building and special meetings with residents will be organized. In addition, after preparing a defective act for the reconstruction of an apartment building, drawing up design estimates and issuing an expert opinion, the documents will be submitted to the republican budget for consideration of financial resources. Upon receipt of a positive decision, repairs will be carried out in accordance with the law "On Housing Relations". According to these laws, repeated explanatory work is currently being carried out with the owners of this apartment building. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev A. Rysbek G. Baymakhanova |
|
19. |
The issue of carrying out work on cleaning up garbage in the area around the apartment building No. 30 of the Akmeshit microdistrict |
September |
LLP "Kyzylorda Tazalygy" carried out a complete garbage collection work around the apartment building No. 30 of the microdistrict. In addition, work was carried out to clean stagnant water in the basements. |
G. Yerkebay Zh. Fayzullayev T. Kulmaganbetov |
|
20. |
The issue of construction of playgrounds in the city |
November |
Work on the placement of playgrounds in the city is ongoing. In 2020, within the framework of the “Employment Roadmap” program, 30 playgrounds were built and put into operation, and in 2021 these works were continued and construction and installation works of 25 playgrounds were carried out. Playgrounds, first of all, were placed in the courtyards of multi-storey residential buildings of the city in accordance with the requests of residents. 2022 has been declared the “Year of Children”. In this regard, with the support of the akim of the region and individual entrepreneurs, 50 sports and children's playgrounds are planned to be built in Kyzylorda. Currently, 37 sports and children's playgrounds are being built. Of these, 17 sports and children's playgrounds have been completed and put into operation. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova |
|
21. |
The problem of public transport |
October |
In order to solve the problem of public transport in the city, it is planned to purchase large-capacity buses. On this occasion, relevant reports have been prepared, documents have been drawn up, and a proposal has been made. The proposal provides for coverage of the entire territory of the city, which means a radical solution to the problem of public transport. Currently, in order to purchase buses, an agreement has been concluded with the manufacturer "QazTehna" LLP (Karaganda) and 82 buses have already been delivered and are providing services. The remaining 68 buses will be provided by the end of the year. |
G. Yerkebay Zh. Fayzullayev R. Yersultanuly |
|
22. |
Carrying out appropriate work to reduce crime in the city |
In a permanent order |
According to the Kyzylorda City Police Department /Dated 09/16/2022 No. 30-247 / 15136/, in order to ensure daily rounds of inspectors of precinct police stations and patrol police, appropriate raid measures are being carried out to reduce crime in the city. |
G. Yerkebay Zh. Seilov A. Kasymova Zh. Fayzullayev A. Zhanazarov (by agreement) |
|
23. |
The issue of lighting the children's playground located in the yard of T. Ryskulov Secondary School No. 222 |
September |
A playground has been built in the courtyard of T. Ryskulov Secondary School No. 222 by “Alem Kurylys Corporation” LLP. The playground includes a football field, a children's playground and a physical education playground. In order to provide this children's playground with night lighting, the contractor was instructed, in the future it will be fully provided with lighting. |
G. Yerkebay Zh. Fayzullayev |
|
24. |
Carrying out cleaning works of the Kyzylzharma canal in the area of R. Alshynbayev Street |
September |
The contractor organization "SKKB CONSRUCTION" LLP carried out a complete cleaning of the Kyzylzharma canal in the area of R. Alshynbayev Street. Customer: SI "City Department of housing and communal services, passenger transport and highways". |
G. Yerkebay Zh. Fayzullayev Zh. Nurymbetov (by agreement) |
|
25. |
Consideration of the issue of asphalting Kurmangazy Street |
November |
20.3 million tenge was allocated from the regional budget for the average repair of Kurmangazy Street with a length of 0.4 km, work was carried out under an agreement with the contractor "Kyzylorda Zholdary" LLP and at the moment the work is fully completed. |
G. Yerkebay Zh. Seilov Zh. Fayzullayev G. Baymakhanova |
|
Belkul village |
||||
|
26. |
Consideration of the construction of a children's playground on the outskirts of the village of Belkul. |
September |
Relevant research work has been carried out on the construction of a children's playground on the outskirts of the village of Belkul. Currently, the construction of a sports and children's playground is underway on Abdikadyrov Street. |
G. Yerkebay Zh. Seilov Zh. Sadu Zh. Fayzullayev G. Baymakhanova |
|
27. |
Consideration of the construction of a sidewalk to the central street of the village of Belkul. |
December |
A budget application for the amount of 24.1 million tenge has been submitted for the construction of a sidewalk on the central street of the village of Belkul. A public procurement tender is currently being held from the city budget in the amount of 5.0 thousand tenge. |
G. Yerkebay Zh. Seilov Zh. Sadu Zh. Fayzullayev G. Baymakhanova |
|
Tasboget village |
||||
|
28. |
Installation in an accessible location of newly installed electricity meters (smart meter) on electrical columns |
November |
Currently, the works of JSC “Kyzylorda Distribution Electric Grid Company” are underway to place electricity metering devices of the “Alfa Smart AS100” brand (smart meter) installed on electric poles in accessible places, the completion date is 2023. |
G. Yerkebay S. Syzdykov Zh. Fayzullayev B. Karakozov (by agreement) |
|
Rural district Kyzylzharma |
||||
|
29. |
Consideration of the issue of masonry work on the street 4 "B" of the Kyzylzharma rural district |
October |
Currently, within the framework of the stone laying project on 42 streets of Kyzylzharma-1 and Kyzylzharma-2 of the outskirts of the Kyzylzharma rural district, according to the program "Development of Regions" from the city budget for 3.6 million tenge, the contractor institution "UAD" LLP carried out stone laying on 4 "B" streets with a length of 0.4 km and commissioned into operation. |
G. Yerkebay Zh. Seilov M. Seilov A. Anuar G. Baymakhanova |
|
Rural district of Kosshynyrau |
||||
|
30. |
Digging and cleaning of irrigation and drainage canals in the rural district |
October |
Currently, 25.9 million tenge has been allocated to the R-2.2 canal of the rural district, 8.1 km of the canal has been cleaned. In addition, 18.6 million tenge was allocated for the Yeshpan canal, 3.9 km was cleared. 20.5 million tenge was allocated for the Altynbai canal, 10.5 km was cleared. |
G. Yerkebay S. Abdykadyrov Zh. Fayzullayev A. Zhylkaidarov (by agreement) |
|
31. |
To study the illegally formed quarry at the burial ground of S.Ishan in the village and take appropriate measures |
September |
According to the Kyzylorda City Police Department (No. 2-23/14919 dated 09/14/2022), together with the city Department of Land Relations and the Aksai district police inspector, the exact location of the illegally created quarry near the necropolis of S. Ishan was established and special measures were taken. As a result, it was established that 2 quarries belong to persons who have a legal document for use by an individual entrepreneur “Aptikalikova R. T.” and LLP "Syr Kumy". Term: 23 years, 4 months. |
G. Yerkebay Zh. Seilov S. Abdykadyrov G. Omarov A. Zhanazarov (by agreement) |
|
Rural district of Karauyltobe |
||||
|
32. |
Consideration of the issue of conducting electric networks to newly populated settlements of the rural district |
October |
In order to conduct electric networks to newly populated areas of the rural district, documentation has been developed and a budget application has been submitted to the republican budget for a total amount of 366.0 million tenge. Currently, 100 thousand tenge has been allocated from the regional budget, the contracting organization is "ELCOM" LLP. Currently, the contractor is working on the installation of electrical wiring (60 thousand tenge has been allocated from the regional budget on a portable basis for 2022). |
G. Yerkebay Zh. Seilov E. Akhetov A. Anuar Zh. Fayzullayev G. Baymakhanova |
|
Rural district Akzharma |
||||
|
33. |
The issue of work on the return of undeveloped land in the Akzharma rural district to state ownership |
October |
The Government of the Republic of Kazakhstan has instructed the Kyzylorda region to return to the State Land Fund a plot of land with an area of 150,000 hectares of pasture lands for agricultural purposes, the city of Kyzylorda -12,000 hectares. On the use of agricultural pasture lands in the territory of the city of Kyzylorda, audit work was carried out on the use of 894 undeveloped land plots for pasture purposes. As a result, it was found that 677 land plots with an area of 50,437.72 hectares are used in accordance with their intended purpose, and 112 land plots with an area of 12,988.44 hectares (including 8 land plots with an area of 814.7 hectares of Akzharma rural district) are not used in accordance with their intended purpose, and returned to the state land fund. This is a 108 percent completion rate. |
G. Yerkebay Zh. Seilov S. Abdireyev G. Omarov G. Kozhakhmetov |
|
34. |
Issue of privatisation of dormitory tenants' flats in Taldyaral settlement |
September |
Buildings located at the address: Kyzylorda city, Akzharma rural district, Taldyaral village, Taldyaral Street No.25 "U" and Taldyaral-2 Street No. 38 "A", registered on the balance sheet of the municipal state institution "City Department of Housing and Communal Services, Passenger Transport and Highways" of the Akimat of Kyzylorda city transferred to the balance sheet municipal state institution "Akim's Office of the Akzharma rural district" (Order No. 59 of 09/15/2022). For information: in order to carry out further privatization work, it is necessary to rename the "dormitory" to "housing" and allocate funds for reconstruction. Documents for the budget application are currently being developed. About 192 thousand tenge is required. |
G. Yerkebay Zh. Seilov S. Abdireyev Zh. Fayzullayev S. Aimenov D. Bohaev |
|
Rural district of Kyzylozek |
||||
|
35. |
Consideration of building a children's playground in the rural district |
November |
A corresponding research work was carried out on the construction of a sports and children's playground and the site of the playground was determined along Dautbayev Street in the village of Karaozek. Currently, the design and estimate documentation and budget application have been developed and submitted to the city budget (for 2023). |
G. Yerkebay Zh. Seilov S. Abdyzhappar Zh. Fayzullayev G. Baymakhanova |
|
Rural district Talsuat |
||||
|
36. |
Consideration of the construction of a sidewalk between Orynbor and A. Kunanbayev streets of the rural district. |
October |
In the rural district, settlement works are being developed for the construction of a sidewalk between Orynbor Street and A. Kunanbayev Street with a length of 0.5 km . Relevant work is also underway to resolve the issue as soon as possible on the part of sponsors. |
G. Yerkebay Zh. Seilov A. Zhylkybay Zh. Fayzullayev G. Baymakhanova |
|
37. |
Consideration of the construction of a sidewalk from Abai street to the children's center for the provision of special social services No. 1 in the rural district |
October |
At the beginning of the year, the office of the akim of the Talsuat rural district presented design and survey calculations and a letter from the city Department of Housing and Communal Services, passenger Transport and highways (09.02.2022, N01-03/160) submitted a budget application for the development of design and estimate documentation with state expertise in the amount of 3.0 million tenge for lighting devices and the construction of sidewalks for 1 240 meters. The initiative was supported at a meeting of the city budget commission. In 2023, design and estimate documentation with expertise will be developed and a budget application will be submitted. |
G. Yerkebay Zh. Seilov A. Zhylkybay Zh. Fayzullayev G. Baymakhanova |
|
Rural district Aksuat |
||||
|
38. |
Digging and levelling areas excavated during the laying of the gas pipeline |
September |
Work is underway on filling, leveling and restoring the places that arose during the gas pipeline in the rural district by the contractor organization “Aliya Service” LLP. |
G. Yerkebay M. Akmyrzayev A. Anuar |
|
39. |
The issue of increasing the number of additional working groups (brigades) from the urban distribution hub to the Aksuat rural district |
September |
According to the Department of Urban electric networks, in addition to the specialist electrician assigned to the rural district of Aksuat, electricians on duty from the operational brigade of the electric grid in the village of Tasboget will be serviced on departure. |
G. Yerkebay M. Akmyrzayev Zh. Fayzullayev E. Kalenov (by agreement) |