Information on the implementation of the action plan on issues raised at the meetings of the Akim of the city of Kyzylorda in the II quarter with the population of the village subordinate to the city, rural district and city in accordance with the Decree of the President of the Republic of Kazakhstan dated March 3, 2022 No. 826

 

Information on the implementation of the action plan on issues raised at the meetings of the Akim of the city of Kyzylorda in the II quarter with the population of the village subordinate to the city, rural district and city

in accordance with the Decree of the President of the Republic of Kazakhstan dated March 3, 2022 No. 826

 

№

Content of the event

Time of execution

Progress of execution

Responsible officer

Kyzylorda city

1.    

Consideration of the construction of a polyclinic in the Titov residential area

December

The construction of the city polyclinic No. 5 which designed for 350 visits per shift will begin in the future. /Outgoing letter of the State Institution "Health Department of the Kyzylorda region" No. 11-19/2590/

At present, a DED has been developed and a budget application has been submitted to the Regional Department of Architecture and Urban Planning for obtaining a state expert opinion for 2023-2025.

A plot of land with an area of 1.5 hectares has been allocated for the construction of a polyclinic at the intersection of Zhankent and Zhetykol streets. Business-purpose land plots belonging to 3 citizens located on this land plot have been transferred to another territory in accordance with the requirements of the Land Code of the Republic of Kazakhstan. Currently, a letter from the customer is expected on the legalization of the land plot established for the polyclinic.

G. Yerkebay

A. Kasymova

Zh . Seilov

Zh . Fayzullaev

A. Anuar

G. Baymakhanova

G. Omarov

G. Kozhakhmetov

S. Pazilov

(by agreement)

2.    

Willow planting on both sides of A. Kashaubayev

October

Planting of trees on both sides of A. Kashaubayev Street will be carried out in the spring of 2023.

G. Yerkebay

Zh . Fayzullayev

3.    

Consideration of installing a bus stop on the road to school No. 10 on A. Kashaubayev Street

July

An application for the installation of 2 stops along A. Kashaubayev Street will be submitted to the city budget in 2023.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

4.    

Consider the lighting, paving and construction of a pavement on T. Bokin Street (near the school no. 173)

December

The development of design and estimate documentation for the construction of a pedestrian crossing along T. Bokin Street from M. Kokenov Street to A. Kashaubayev Street in Kyzylorda will require 1,271.0 thousand tenge.

In addition, 981.0 thousand tenge was allocated from the city budget for the development of design and estimate documentation and obtaining an expert opinion on the installation of night lighting fixtures on this street. A public procurement tender has been announced, an agreement has been concluded with “TM Proect” LLP. Design work is currently underway.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

5.    

Transfer of sports and playgrounds in the courtyard of the M. Eralieva House of Culture to the balance of the relevant institution.

July

The relevant work was carried out on the transfer of a sports and playground in the courtyard of the M. Yeralieva House of Culture to the balance of the state municipal state enterprise “City Houses of Culture, clubs and folk collectives”, in accordance with Article 36 of the Law of the Republic of Kazakhstan “On State Property” and the resolution of the Akimat of Kyzylorda dated May 30, 2018 No. 11174 city Finance Department Kyzylorda “On the approval of the regulations of the state institution “Department of Finance of the city of Kyzylorda” of the Akimat of the city of Kyzylorda.

Order No. 44 21.06.2022, on the acceptance of a sports and playground located on a plot of land with an area of 1187.0 square meters (cadastral number: 10:156:013:390) by the state municipal state enterprise “City Houses of Culture, clubs and folk collectives”. At the address: Kyzylorda region, Kyzylorda city, A. Kashaubayev Street, without a number.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

S. Aimenov

6.    

Consideration of a ditch water supply in the Al-Farabi neighbourhood

July

98 million tenge was allocated from the regional budget for the development of design and estimate documentation and state expertise for the establishment of 26 exploration production wells to provide ditch water supply to the city. A public procurement competition was held, according to the results of which the production cooperative "Kazgiprovodkhoz" was recognized as the winner. Currently, the development of design and estimate documentation for this project is underway.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

7.    

Issue of resumption of public transport on route No. 22 to the Al-Farabi Microdistrict

June

In order to solve the problem of public transport in the city, it is planned to purchase large-capacity buses. Relevant calculations have been prepared and documents have been drawn up and a proposal has been made. The proposal provides for a cardinal solution to the issue of covering the entire territory of the city.  Currently, an agreement has been concluded with the manufacturer "QazTehna" LLP (Karaganda) for the purchase of buses. At the moment, 82 buses have been delivered and serves the population of the city. At the same time, after the delivery of the remaining 68 buses, urban public transport along route No. 22 will be resumed.

G. Yerkebay

Zh. Fayzullayev

8.    

Consideration of the asphalting of Zelkildek Batyr Street

October

Zhelkildek Batyr Street is included in the list of streets of the city requiring road works. In the future, after the allocation of funds for the development of design and estimate documentation the relevant work will be carried out in stages.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

9.    

Consideration of the issue of asphalting Kamalov Lane (road to school No. 173)

October

A budget application for consideration of funds from the regional budget in the amount of 14,950 thousand tenge was submitted to the regional department of Passenger transport and Highways through the relevant program administrator.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

10.        

Carrying out average road repairs along Baiterek Street - 1,2

August

In 2022, 429.0 million tenge was allocated from the regional budget to start work on the average repair of the 1st arrival with a length of 4 km and the 2nd arrival with a length of 5 km in the residential area of Baiterek (Baiterek 1 - 197.0 million tenge, Baiterek 2-232.0 million tenge), an agreement was signed with “Kyzylorda Zholdary” LLP according to the results of the public procurement competition.

Currently, the work is fully completed.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

11.        

Installation of a traffic light at the intersection of Zhappasbai Batyr and Korkyt Ata Streets

July

Funds from the regional budget in the amount of 18,349 thousand tenge were allocated for the installation of a traffic light at the intersection of Zhappasbai Batyr Street with Korkyt Ata Street. A public procurement competition has been announced and the work has been carried out by the contractor institution IP "Koshekov".

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

12.        

Installation of light poles on Sagimbayev Street

July

6,882 thousand tenge was allocated from the city budget for the installation of night street lighting (1.0 km) from the “KazMunayGas” gas station along Sagimbayev Street to the Baiterek residential area.

Currently, the contractor organization IP "Koshekov" has completed the installation of light poles and has been put into operation.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

13.        

Construction of a bridge over the Kyzylzharma canal to the residential area of Baiterek

November

100.0 thousand tenge has been allocated from the regional budget to start the construction of a road bridge across the “On zhak Magistraldy” canal in the Baiterek residential area of the city of Kyzylorda. According to the results of the public procurement competition, an agreement was concluded with “Standard Oil” LLP. The necessary funds for the full completion of the project are 368.5 million tenge. To allocate the remaining funds, an application was submitted to the regional budget.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

14.        

Consideration of installing electrical poles on the second side of the Nysanbay Zhyrau Street in the Al-Farabi micro-district

November

On the issue of installing electric poles on the other side of Nysanbay Zhyrau street in the Al-Farabi microdistrict of the city of Kyzylorda, the Department of Urban Construction is conducting design and survey work. The necessary project is worth 2.5 million tenge and in the future a budget application will be submitted to the city budget.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

A. Anuar

15.        

Consideration of the construction of a sidewalk along Baikonur Street

August

Baikonur Street is included in the list of city streets that require the construction of sidewalks. In the future, after the allocation of funds for the development of design and estimate documentation, the relevant work will be carried out in stages.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

16.        

Conducting electricity networks in the Arai-Shugyla micro-district

December

89,376 thousand tenge was allocated from the republican budget for the electricity supply of the residential sector in the Arai Shugyla microdistrict of the city of Kyzylorda. According to the results of the public procurement competition, the Contractor "Elcom" LLP was determined as the winner. Currently, electric poles have been installed, cable laying has been carried out. In addition, work is underway on the distribution of electrical power, the assembly of internal parts of installations and their placement together with the Kyzylorda city institution of distribution nodes. After the complete placement of the TP installation, an appropriate 72-hour test time and full connection to the power grid will be carried out.

G. Yerkebay

Zh . Seilov

A.Anuar

G. Baymakhanova

17.        

Consideration of the issue of the construction of a bus stop on Kultekenov Street (intersection of Kultekenov and Khlebnaya streets)

July

Currently, the installation of a bus stop on Kultekenov Street is included in the list where stops around the city are required. In the future, after the allocation of funds, the relevant work will be carried out in stages.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

18.        

Naming and numbering of streets in the Arai-Shughyla micro-district

August

In accordance with the current legislation, proposals from individual citizens and residents of the city on the "Arai-Shugyla" microdistrict will be submitted and considered on the agenda of the working group of urban onomastics.

To date, documents of 7 streets from this territory have been developed and included in the agenda.

(Arai-Shugyla 1 street 1265 meters wide 6 meters, about 40 houses, Arai-Shugyla 2 street 1234 meters wide 6 meters, about 40 houses, Arai-Shugyla 3 street 450 meters wide 6 meters, about 25 houses, Arai-Shugyla 4 street 608 meters wide 6 meters, about 15 houses, Arai-Shugyla 5 street 540 meters width 6 meters, about 20 houses, Arai-Shugyla 6 street 180 meters width 6 meters, about 7 houses, Arai-Shugyla 7 street 220 meters width 6 meters, about 6 houses).

On September 9, 2022, a meeting of the city onomastics working group was held. At this meeting, 7 streets in the Arai-Shugyla microdistrict were discussed in detail, the initiative to rename Arai 1 and Arai 2 streets was supported, and relevant work is underway.

A. Kasymova

G. Kozhakhmetov

Zh . Fayzullaev

Zh . Tazhmakhanov

19.        

Consideration of the construction of a school in the Arai-Shugyla neighbourhood

December

Currently, the individual entrepreneur of “Bauyr group” LLP is working on the construction of a private school for 1200 places at its own expense in the Arai Shugyla microdistrict.

G. Yerkebay

Zh . Seilov

A. Anuar

G. Baymakhanova

20.        

The issue of not changing the route of public transport on route 11 to the Sayahat neighbourhood

July

Due to the arrival of new high-capacity buses in the city and in agreement with local residents, public transport along route No. 19 is carried out through the Sayahat microdistrict.

G. Yerkebay

Zh . Fayzullaev

M. Zhusip

21.        

Provide incentives for disabled people to travel free of charge on public transport

June

In order to consider benefits in urban public transport for the (blind) disabled of groups I-II in the city of Kyzylorda, special resolutions and decision documents have been developed and sent to the justice authorities.

Nowadays, through the institution "Kyzylorda Bus Park", special ticket cards are being developed.

G. Yerkebay

Zh . Fayzullaev

K. Kurakbayeva

22.        

Renovation of electric poles on Korkyt Ata Street No. 12 of the KBI micro-district

November

In order to update the electric poles along Korkyt ata Street No. 12 in the KBI microdistrict of the city of Kyzylorda, the city construction department is conducting design and survey work. The total cost of the project is 3.1 million tenge, a budget application has been sent to the city budget.

G. Yerkebay

Zh. Seilov

A. Anuar

Zh . Fayzullaev

G. Baymakhanova

E. Kalenov

(by agreement)

23.        

Reconstruction (modernisation) of apartment block No. 51 in the Shugyla micro-district

November

Within the framework of the state program of Housing and communal development “Nurly Zher” for 2020-2025 and the budget program "credit to the budgets of regions, cities of republican significance and the capital for the overhaul of the common property of condominium facilities", 99.5 million tenge was provided from the republican budget for 2022 for the overhaul of an apartment building No. 51 of the Shugyl microdistrict. At present, major repairs have been carried out. The contractor is “Zhansaya” LLP.

G. Yerkebay

Zh . Fayzullaev

T. Kulmaganbetov

24.        

Construction of a pavement road to schools No. 9, 136 of the Akmeshit micro-district

September

For the construction of sidewalk paths near school No. 9 from S. Romanov Street to Salamatov Street, an application was submitted for the allocation of funds from the city budget in the amount of 12,864 thousand tenge and a budget application was submitted for the allocation of funds from the regional budget for the construction of sidewalk paths from the street adjacent to school No. 136 from S. Romanov Street to Salamatov Street.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

25.        

Installation of a traffic light at the intersection of Tolybekov and Auezov Streets

July

19,543 thousand tenge was allocated from the regional budget for the installation of a traffic light at the intersection of Tolybekov Street with Auezov Street.

According to the results of the public procurement competition, an agreement was concluded with IP "Koshekov", construction and installation works were carried out and put into operation.

G. Yerkebay

Zh . Seilov

Zh . Fayzullaev

G. Baymakhanova

Tasboget village

26.        

Consideration of stone paving on Seyfullina Street in the township

July

Design and estimate documentation has been developed for paving 7 streets in the village (Seifullina, Muratbayev, Makhanbetov, Moldagulova, Maykanova, Duisenov, Oteuov), the results of the examination are positive.

An application has been submitted to the regional budget for the implementation of the project for a total amount of 251.9 million tenge.

G. Yerkebay

Zh . Seilov

S. Syzdykov

Zh . Fayzullaev

G. Baymakhanova

27.        

Continuation of the construction of a new cemetery in the village

October

In connection with the filling of the territory of the central cemetery in the village in 2018, 13.5 hectares of land were allocated for the construction of a new cemetery on the outskirts. In addition, the village administration has developed design and estimate documentation and received a positive expert opinion. Based on this, an application was submitted to the city budget for the implementation of a project worth 101.7 million tenge. According to the results of the public procurement competition, “SC Energia” LLP won with 84.7 million tenge. For the start of construction work in 2020, 20.0 million tenge was allocated from the city budget and fully utilized. In 2021, 20.0 million tenge was allocated for the continuation of the construction of the facility, but the contractor did not carry out the corresponding work, citing an increase in prices for construction materials. In this regard, on the basis of the contract, a lawsuit was filed, as a result of which the design and estimate documentation for the construction of the cemetery was recalculated and the court decided to make changes.

To date, at the expense of the saved funds of the akim's office of the village, the DED has been processed for 1.7 million tenge, a budget application for 81.8 million tenge has been submitted.

G. Yerkebay

Zh . Seilov

S. Syzdykov

A. Anuar

J. Fayzullaev

G. Baymakhanova

28.        

Carrying out cleaning works inside the ditches on Abai Street

June

To date, a complete cleaning of the ditches of this Abai street has been carried out.

G. Yerkebay

S. Syzdykov

Zh . Fayzullaev

29.        

Installation of the bus stop along Abai Street

October

2 stops were installed along Abai Street in the amount of 2.5 million tenge allocated from the city budget.

G. Yerkebay

Zh. Seilov

S. Syzdykov

G. Baymakhanova

30.        

Regulation of public transport interval to the dacha settlement /public transport in the direction of No. 28, No. 30/

June

In order to regulate the interval of intra-city public transport on route No. 28, “KadNur” LLP was instructed to take appropriate measures, as well as in order to regulate the interval of intra-city public transport on route No. 30, “Argymak” LLP was instructed to take appropriate measures.

G. Yerkebay

 S. Syzdykov

Zh. Fayzullayev

31.        

Lighting of courtyards of multi-storey residential buildings of the Nauryz microdistrict

September

0.8 million tenge has been allocated from the local government account to illuminate the courtyards of the Nauryz microdistrict in the village, currently the winner of the public procurement competition for the performance of relevant works has been determined /contractor “Innotech” LLP/ and street lighting has been installed.

G. Yerkebay

Zh. Seilov

S. Syzdykov

Zh. Fayzullayev

G. Baymakhanova

32.        

Repair of the roof of the house of culture named after S. Maykanova

September

3.2 million tenge was allocated from the local government account for the repair of the roof of the House of Culture named after S. Maykanova and repairs were carried out. Contractor organization is "Akparat Kyzylorda" LLP.

G. Yerkebay

Zh. Seilov

S. Syzdykov

G. Baymakhanova

33.        

Opening of a cash register to pay for drinking water services in Tasboget village

July

Starting from June 1, 2022, a cash register for the receipt of payments for drinking water and sewage services has been opened and has been operating on the 2nd floor of the “Ambebap" Shopping Centre, located at 36 Esenov Street, Tasboget village.

G. Yerkebay

S. Syzdykov

Zh. Fayzullayev

Belkul village

34.        

Establishing the operation of a filtration site for sewage discharge located within the boundaries of Abdikadyrov Street with Tasboget village

June

Together with local police inspectors, specialists of the Department of Ecology, specialists of the State Enterprise "Su Zhuyesi", employees of the akim's office of the village of Belkul, raid work is carried out on a regular basis on special equipment for the removal of sewage (sewage disposal).

G. Yerkebay

 Zh. Sadu

Zh. Fayzullayev

A. Zhanazarov

(by agreement)

35.        

Conducting inspections of the work of the medical waste disposal site located near the village of Belkul

June

According to the Department of laboratory and analytical control of the RSI "Department of Ecology of the Kyzylorda region", atmospheric air samples were taken from the sanitary protection zone of the medical waste disposal furnace, according to the results of which pollutants did not exceed the maximum permissible amounts, as well as according to the results of external control, inspection and study conducted by the department, it was established that the furnace disposal of medical waste LLP "Barsha and K", currently not functioning.

 

 

 

G. Yerkebay

Zh. Sadu

Zh. Fayzullaev

N. Umirserikuly

(by agreement)

36.        

Installation of night lighting fixtures on Abdikadyrov Street-3

July

2.5 million tenge was allocated from the city budget for the installation of night lighting fixtures on K. Abdikadyrov Street-3, lighting works were carried out. Contractor organization is "MK Service" LLP

G. Yerkebay

Zh. Seilov

Zh. Sadu

Zh. Fayzullayev

G. Baymakhanova

37.        

Replacement of the old sewer water supply in the courtyard of the multi-storey residential building No. 11

July

Currently, the administration of the village of Belkul, together with the Joint Directorate of the “Aral”, has carried out work on replacing old sewer water pipes in the courtyard of the multi-storey residential building No. 11.

G. Yerkebay

Zh. Sadu

Zh. Fayzullayev

38.        

Construction of a pedestrian bridge over the railway

October

251 million tenge was allocated from the regional budget for the construction of a pedestrian bridge over the railway in the Belkol settlement of the city of Kyzylorda. The contracting organization “Golden City” LLP won in the amount of 225.2 million tenge and construction work is currently underway.

G. Yerkebay

Zh. Seilov

Zh. Sadu

Zh. Fayzullayev

G. Baymakhanova

39.        

Development of the water distribution well of the village

July

14,799.8 thousand tenge was allocated from the republican budget for drilling of the technical water intake well No. 14-TC on Birkazan Street in the village of Belkul. According to the established schedule, well drilling has been completed in the Birkazan settlement and commissioning works are underway.

G. Yerkebay

Zh. Seilov

Zh. Sadu

Zh. Fayzullayev

G. Baymakhanova

Rural district Kyzylzharma

40.        

Installing a traffic light at the intersection of R. Batyrbayev and K. Seksenbayev streets

August

A public procurement competition was held for the installation of traffic lights at the intersection of R. Batyrbayev and K. Seksenbayev streets. The project cost is 11.9 million tenge. After determining the contracting institution, work will be carried out to install the traffic light.

G. Yerkebay

Zh. Seilov

M. Seilov

Zh. Fayzullayev

G. Baymakhanova

41.        

Development of a well for water supply to the rural district

July

Currently, for the purpose of water supply of the Kyzylzharma rural district, the city department of Housing and Communal Services, passenger transport and highways has carried out construction work and commissioned 3 pieces of drainage water intake wells:

1. on Ustabayev Street;

2. on N. Ilyasov Street;

3. in the back of school No. 144 named after S. Alzhikov.

G. Yerkebay

Zh. Seilov

M. Seilov

Zh. Fayzullayev

G. Baymakhanova

42.        

Carrying out average road repairs of Saylybayev and No. 4 A streets in the rural district (laying of stone)

July

According to the program "Development of regions" in the amount of 5.7 million tenge provided from the budget, the contractor “Universal Service” LLP carried out work on the average repair (laying of stone) of Saylybayev and No. 4 A streets.

G. Yerkebay

Zh. Seilov

M. Seilov

Zh. Fayzullayev

G. Baymakhanova

43.        

Laying rubble on the streets of Kyzylzharma-20, 21

October

190 million tenge is provided through the city construction department for the project worth 1 billion 642 million tenge for laying stone on 42 streets in the residential areas of Kyzylzharma-1 and Kyzylzharma-2, which are the outskirts of the district. Currently, these funds have been used to lay the stone of 8 streets (20.21 streets are included in this list). Contractor organization is "UAD" LLP.

G. Yerkebay

Zh. Seilov

M. Seilov

A. Anuar

G. Baymakhanova

44.        

Development and cleaning of borehole tunneling channels in the rural district

July

In the rural district, work has been carried out on cleaning intra-village channels, laying ditches along streets where ditches have not been carried out and laying pipes with a diameter of 300 in the amount of 5 pieces. The contracting organization is IP "Asanova".

G. Yerkebay

Zh. Seilov

M. Seilov

Zh. Fayzullayev

G. Baymakhanova

Rural district of Kosshynyrau

45.        

Consideration of the issue of gas supply to the rural population

December

In order to provide the rural district with blue fuel, design and estimate documentation has been developed, 11 million 688 thousand tenge has been allocated from the regional budget to obtain the conclusion of the state expertise, and public procurement work has been carried out.

According to the results of the purchase, the contractor organization “Stroy-Proect-Inventarizaciya” LLP was recognized as the winner, the design and estimate documentation was developed and provided to the competent authorities.

The project requires about 664,889 million tenge for construction work.

G. Yerkebay

Zh . Seilov

S. Abdikadyrov

Zh . Fayzullaev

A. Anuar

G. Baymakhanova

46.        

Consideration of the allocation of funds for the development of a DED for the demolition of the old emergency outpatient clinic in Abai village and the construction of an indoor sports complex on its site

August

An application has been submitted to the city budget for the development of a DED for the demolition of an emergency old outpatient clinic in the village of Abai and the construction of an indoor sports complex in its place.

A letter was sent to the regional health department for the construction of a sports complex with the demolition of an emergency old outpatient clinic in the village of Abai. Currently, documents on the recognition of the outpatient clinic's ownership are being drawn up.

G. Yerkebay

Zh . Seilov

S. Abdikadyrov

Zh . Fayzullaev

G. Baymakhanova

47.        

Installation of light poles from a cow farm to an outpatient clinic in a rural district

July

3.5 million tenge was allocated from the local budget for the installation of light poles from the cowsheds of the farm to the outpatient clinic in the rural district. By means of “MK Service LTD” LLP, light columns from the cowshed farm to the outpatient clinic in the rural district are fully installed.

G. Yerkebay

S. Abdikadyrov

Zh . Fayzullaev

 

48.        

Consideration of the construction of a medical post in Dosan village

December

The Regional Department of Construction, Architecture and Urban Planning has developed design and estimate documentation and received the conclusion of the state expertise for the construction of a medical post in Dosan village. The total cost of the project is 140,0 million tenge. A budget application has been submitted for the upcoming 2023 and construction is planned for 2024-2025.

G. Yerkebay

S. Abdykadyrov

S. Pazilov

(by agreement)

Rural district of Karauyltobe

49.        

Carrying out fencing works on the grave “Abdykalyk”

July

13,500 thousand tenge and 740 thousand tenge were allocated from the city budget for the execution of fencing works on the grave of “Abdykalyk” located on the territory of the settlement, currently the works have been fully completed by the contractor organization “OrdaMegaStroy” LLP.

G. Yerkebay

Zh. Seilov

E. Akhmetov

Zh . Fayzullaev

G. Baymakhanova

50.        

Purchase of borehole pump for irrigation of garden lands in the amount of 2 pieces

July

In order to irrigate garden lands, 800 thousand tenge was allocated from the city budget for the installation of a water pump. In order to determine the contractor, tender documents have been developed and a tender has been announced through the public procurement web portal.

G. Yerkebay

Zh. Seilov

E. Akhmetov

Zh . Fayzullaev

G. Baymakhanova

51.        

Development of a well for water supply to the rural district

July

Funds in the amount of 14,799.8 thousand tenge were allocated from the republican budget for drilling a technical water intake well into the newly settled territory and 14,799.8 thousand tenge for drilling a technical water intake well No. 6-TC on A. Imanov Street. Currently, work is underway on the placement.

G. Yerkebay

Zh. Seilov

E. Akhmetov

Zh . Fayzullaev

G. Baymakhanova

52.        

Construction of a typical project House of culture for 150 seats in a rural district

December

274.8 million tenge has been allocated from the republican budget, and a club for 150 seats is being built. The construction works are designed by "KREZ Service" LLP, conducted by "Umirzak" LLP. Currently, the contracting institution has completed work on weaving, installing windows, doors of the club, heating and roofing work is underway.

G. Yerkebay

Zh. Seilov

E. Akhmetov

A. Anuar

G. Baymakhanova

Rural district of Kyzylozek

53.        

Lighting of Zh. Zhabaev street in the rural district of Karaozek

July

In the amount of 3,588 million tenge, provided at the expense of the saved funds of the institution, the contractor “MK-SERVICE LTD” LLP installed night lights for the rest of Zh. Zhabayev Street in the village of Karaozek and fully illuminated the street.

G. Yerkebay

Zh. Seilov

S. Abdyzhappar

Zh. Fayzullayev

G. Baymakhanova

54.        

Installation of light poles on Ainakol streets-2,3,4,5

July

The contractor "Ai-Dar Service" LLP has fully completed the installation of lampposts for night lighting on the streets of Ainakol-2,3,4,5 at the expense of 3.6 million tenge allocated from the budget under the program "Regional Development".

G. Yerkebay

Zh. Seilov

S. Abdyzhappar

Zh. Fayzullayev

G. Baymakhanova

55.        

Development of a well water distribution well in a rural district

July

The republican budget allocated 14,799.8 thousand tenge for drilling of technical water intake well No. 18-TC on S. Seifullina Street, 14.8 million tenge for drilling of technical water intake well No. 19-TC on Zhanaryk Street, 14.8 million tenge for drilling of technical water intake well No. 19-TC on Sh. Ibraeva street of Karaozek village.

Currently, 3 wells have been drilled and put into operation.

In addition, in connection with the requests of residents, the 4th well has been dug in the village of Karaozek, along Argyn Street, and work is underway to connect to electricity.

G. Yerkebay

Zh. Seilov

S. Abdyzhappar

Zh. Fayzullayev

G. Baymakhanova

56.        

Digging and clearing the “Levaya Vetka” canal and the “Stalin canal” to the “Shegirtke” hayfield.

July

A letter of recommendation has been sent to the production site "Kyzylordasushar" to carry out work on digging and cleaning the canal from the “Levaya Vetka”  canal to the "Shegirtke" hayfield, solutions are being considered depending on the financial capabilities of the institution.

G. Yerkebay

Zh. Seilov

S. Abdyzhappar

Zh. Fayzullayev

G. Baymakhanova

57.        

Consideration of the issue of providing associated gas to three settlements of the Kyzylozek rural district

December

In order to develop design and estimate documentation for providing associated gas to three settlements of the Kyzylozek rural district to determine the estimated cost, design and research works were reconstructed and submitted to the regional Department of Energy and Housing and Communal Services through the city construction department.

In the near future, a phased gasification of settlements in the region is expected.

G. Yerkebay

Zh. Seilov

S. Abdyzhappar

Zh. Fayzullayev

A. Anuar

G. Baymakhanova

Rural district Talsuat

58.        

Development of a well for water supply to the rural district

July

Funds have been allocated from the republican budget for drilling a technical water intake well No. 10-TC on Nurmaganbetov Street in the amount of 14,799.8 thousand tenge and for drilling a technical water intake well No. 11-TC on Baykenzheyev Street of Talsuat rural district in the amount of 14,799.8 thousand tenge. Currently, 2 sewage wells have been dug in the Aksuat rural district, sewage water has been supplied to the residents of the rural district.

G. Yerkebay

Zh. Seilov

A.Zhylkybai

Zh. Fayzullayev

G. Baymakhanova

59.        

Development of design documentation for laying power lines in the area of newly inhabited Talsuat village as well as other 13 streets

October

In Talsuat rural district, 4.4 million tenge was allocated from the city budget for conducting electrical networks and installing electric supports, developing design estimates for Atyrau Streets, Street No. 7, Orynbor, Almaty, Astana, Akmeshit, Kazaly, Zhankent, Street No. 6, Seyhun, Syganak and Syrdarya. The customer is the city construction department. An agreement was signed with the project organization “Dimash Service” LLP.

The conclusion of the state examination with an estimated cost of 69.7 million tenge was received on 24.08.2022, No. MARAT-0053/22.

G. Yerkebay

Zh. Seilov

A.Zhylkybai

A. Anuar

G. Baymakhanova

60.        

Consideration of a way to address the quality of the newly constructed drinking water pipeline and transfer to the balance of the relevant institution

July

Currently, two wells have been cleaned. The customer which is the State Institution "Kyzylorda City Construction Department" has carried out work to bring the documents into compliance with the note of the institution that accepts on the balance sheet and submitted to the regional Department of Economics and Finance (No. 01-1/1630 dated 12.07.2022).

In addition, the customer, represented by the city construction department, filed a lawsuit in October against LLP "Asanas-Dar" for reconstruction of drinking water wells. In April 2023, one concept will be re-developed.

G. Yerkebay

Zh . Seilov

A. Zhylkybay

A. Anuar

Zh . Fayzullaev

S. Aimenov

N. Kordabai

(by agreement)

61.        

Installation of light poles on the streets of Kazaly and Kokshetau

July

Within the framework of the program "Development of Regions", 1.9 million tenge was allocated from the budget for street lighting of Kazaly, Kokshetau streets in Talsuat rural district. In the public procurement competition, the winner was determined along Kazaly Street by “INNO TECH” LLP and “MK – Service” LLP along Kokshetau Street. Currently, the work on street lighting is fully completed.

G. Yerkebay

Zh. Seilov

A.Zhylkybai

Zh. Fayzullayev

G. Baymakhanova

Rural district Akzharma

62.        

Development of a well for water supply to the rural district

July

The republican budget allocated 14,799.8 thousand tenge for drilling of technical water intake well No. 1-TC on N.Tasymov Street and 14,799.8 thousand tenge for drilling of technical water intake well No. 2-TC on Taldyaral Street of Taldyaral settlement.

The contracting organization is "Bak Bereke" LLP. Currently, work on the installation of a well in the settlement of Baymurat Batyr has been fully completed.

G. Yerkebay

Zh. Seilov

A. Musabaev act.

Zh. Fayzullaev

G. Baymakhanova

63.        

Conducting electricity networks in the Taldyaral settlement

July

4335 thousand tenge was allocated from the regional budget and 39 020 thousand tenge from the republican budget for the construction of electric networks of residential buildings in the Taldyaral settlement.

The project provides for an electric network with a length of VL-10 kV - 5.4 km, VL-0.4 kV - 2.1 km.

For the implementation of this project, a competition was organized and on 29.03.2022, by the method of open tender No. 7048563-OK1, the winner was recognized as the Construction Company “Er-Kanat Service” LLP.

Contract No. 44 dated 07.04.2022 for 39.5 million tenge was signed between the contracting institution and the Department of Urban Construction . The term of the contract is 3 months (08.07.2022).

For reference: at the beginning of July, the contractor supplied 60 pieces of electric poles, more than 2000 meters of cable. At the same time, a specialist of the city construction department and technical supervision visited the facility and confirmed the completion of work for 6.0 million tenge, payment was made to the contractor by account No. 4672506/22-577 dated 07/29/2022. Today, some materials (cable) are missing from the facility.

Warning letters were repeatedly sent to the contracting institution of “Er-Kanat Service” Construction Company LLP, due to the fact that construction and installation work under the contract was not carried out.

In addition, an instruction has been sent from “Asem Kurylys” LLP, which is the technical supervisory authority of the facility. But, since there was no result, the city construction department appealed to the specialized economic court of the Kyzylorda region with a statement of claim No. 01-1/622 dated 11.07.2022 (statement of claim: recognition of the contractor as an indefinite participant in public procurement and oblige to carry out construction work).

According to the statement of claim, by the decision of the Specialized Interdistrict Economic Court of the Kyzylorda Region No. 4360-22-00-2/1296 dated October 14, 2022, the contractor “Er-Kanat Service” Construction Company LLP was recognized as an indefinite participant in public procurement and is obliged to complete construction work.

To date, the court's decision on the part of the contractor is not being executed.

G. Yerkebay

Zh . Seilov

A. Anuar

Zh . Fayzullaev

S. Abdireev

G. Baymakhanova

64.        

Consideration of allocation of funds for gas works in the rural district

December

In 2022, to provide natural gas to the Akzharma rural district, the need for 37.6 million tenge was determined for the development of design and estimate documentation, a budget submission was submitted to the regional Department of Energy and Housing and Communal Services through the city construction department.

In the future, with a positive decision on the allocation of funds from the budget, this work will be carried out.

G. Yerkebay

Zh. Seilov

S. Abdireev

Zh. Fayzullaev

A. Anuar

G. Baymakhanova

65.        

Installation of street lighting on Tugai Street

July

2.5 million tenge was allocated from the city budget for the installation of street lighting for 500 meters along Togai Street in the village of Baymurat Batyr, according to the method of requesting price proposals of the law "On Public Procurement", the notification was submitted in June, the contractor organization “Energia Nur” LLP has completed the work.

G. Yerkebay

Zh. Seilov

S. Abdireev

Zh. Fayzullaev

G. Baymakhanova

Rural district Aksuat

66.        

Gas supply in the rural district

December

In order to provide natural gas to the Aksuat rural district, 2 billion 439 million tenge has been allocated for 2022, the contract organization "Aliya – Service" LLP is currently working on laying a gas pipeline and releasing pipes into residential buildings of 9.6 km of medium-pressure gas pipelines, 16.5 km of high-pressure gas pipelines and 123 km of low-pressure gas pipelines.

The total cost of the project is 4 billion 775 million tenge.

D. Yerkebay

Zh . Seilov

M. Akmyrzaev

A. Anuar

Zh . Fayzullaev

G. Baymakhanova

67.        

Purchase of a pump for irrigation systems (2 pieces)

July

In order to provide seasonal water supply to the newly settling population left without water supply in the rural district, at the expense of 29.6 million tenge provided from the republican budget, the contractor organization "Bak Bereke" installed wells on T. Bekmuratov St. and Sarykol St. and transferred for use.

D. Yerkebay

Zh . Seilov

M. Akmyrzaev

G. Baymakhanova

68.        

Installation of newly installed electric meter devices (smart meter) on electric speakers in an accessible place

July

On the issue of installing newly installed electric meter devices (smart meter) on electric poles in an accessible place, a meeting was organized with villagers and employees of the city distribution institution of electric networks. In accordance with the basic requirements of the villagers, work is currently underway to lower and place electric meter devices located in the upper part of electric poles on the walls of residential buildings, the completion date is 2023.

G. Yerkebay

M. Akmyrzaev

J. Fayzullaev

B. Karakozov

(by agreement)

 

 