The work of the regional operational headquarters to eliminate the consequences of the flood continues in the southern regions. All services are operating in enhanced mode. Akim of the region K.Aksakalov and the working commission monitor the situation around the clock on the ground and coordinate the actions of all involved structures.
As a result of the strong flow of meltwater, sections of highways were destroyed, as well as power lines in the Kostanay region.
About 27 villages of Amangelda and Dzhangelda districts were left without electricity.
"It is necessary to carry out all restoration work as quickly as possible. People without lights, connections. Our task is to resolve these issues immediately," K.Aksakalov instructed
The repair work is also complicated by the fact that the power lines are surrounded by water. Electricians have to work in difficult conditions, waist-deep in water.
At the same time, restoration work is underway. At the moment, power supply has been restored in 26 villages