The execution of the pLANand events
on implementation of proposals and comments of the population received during the reporting meetings
akims of rural districts and villagesand Novoshumnoye with the population in 2020 году
for the 3rd quarter of 2020
|
№ |
Expressed Comments/suggestions made |
Terms of performance and implementation measures remarks/suggestions |
Version |
|
1 |
2 |
3 |
4 |
|
1 |
Repair the road along Ordabayev street in the village of Fedorovka |
by 1.10.2020. |
Executed. Repaired 1.6 km of the road along the street. Ordabaevastreet . 42.2 million tenge was spent, and the works were completed in full. |
|
2 |
Complete lighting of the Central street of the village |
until 1.10.2020 of Karakop by 1.10.2020 |
Executed. Completed the street lighting in the village of Marakopa, installed 8 lamps for a total amount of 1 265,5 thousand tenge |