The execution of the pLANand events
on implementation of proposals and comments of the population received during the reporting meetings
akims of rural и селdistricts and villages and Novoshumnoye with the population in 2020 году
for the 2ndquarter of 2020
|
№ |
Comments /suggestions made |
Terms of performance and implementation measures remarks/suggestions |
Version |
|
1 |
2 |
3 |
4 |
|
1 |
Repair the road along Ordabayev street in the village of Fedorovka by 1.10.2020 |
until 1.10.2020. |
For execution. The average repair of the street is planned for 2020. Ordabayev is 1.6 km long. According to the results of the competition, an agreement No. 40 was signed with IP Petoyan O. O., the final amount of works was: 42243.5 thousand tenge. As of 29.06.2020, the works were completed by 37%, i.e. the length of completedrepairs is 0.6km. 18 million tenge was spent on the repair of the street. Ordabaev's work continues . The works will be completed by 1.09.2020. |
|
2 |
Complete lighting of the Central street of |
the villageof Karakop by 1.10.2020 |
Executed. Completed the street lighting in the village of Marakopa, installed 8 lampsfor a total amount of 1 265,5 thousand tenge |