Plan events
to address the most urgent proposals, the comments made during the reporting meetings of akims of villages, rural districts, with district population Niemi in January - February 2020 the year
in the Karabalyk district
|
No. |
Problematic issues (comments and suggestions) |
M eropriyatiya |
Term and completion |
Responsible (Full name and position)
|
|
1 |
Carry out an average repair of 5 streets of the village of Karabalyk |
P Started on average p Repairing in streets Fabrichnaya Proletarshaya Part Str. Nechipurenko within the boundaries of st. With . Kozhamkulova - Lermontov, Abay completed in full. |
Until September 1, 2020 |
Auzhanov A.K. Deputy Akim of Karabalyk District
Siitov B.K. - and about. Head of the State Institution “Department of Housing and Communal Services, Passenger Transport and Roads of the Akimat of the Karabalyk District”
|
|
2 |
Conduct facilities for warm toilets in 5 primary schools of the Karabalyk district |
Currently, about the arrangement of warm toilets in Yelshanskaya, Tselinnaya, Primagnay primary schools has been completed. |
Until September 1, 2020 |
Zhabulov A.T. , acting Deputy Akim of Karabalyk District
Sapanova D.S. - Head of the State Institution " Education Department of the Akimat of the Karabalyk District" |
|
3 |
To carry out the removal of the boiler room from the building of the Smirnov secondary school of the Karabalyk district |
With troitelno boiler installation works completed s , is currently undergoing work to install boilers and laying of heating main . |
Until September 1, 2020 |
Zhabulov A.T. and about. Deputy Akim of Karabalyk District
Sapanova D.S. - Head of the State Institution "Education Department of the Akimat of the Karabalyk District" |