Quarterly monitoring of the implementation of local budget investment projects and budget investments through state participation in the authorized capital of legal entities, implemented at the expense of local and republican budgets for the first quarter of 2026

Quarterly Monitoring of the Implementation of Local Budget Investment Projects and Budget Investments through State Participation in the Authorized Capital of Legal Entities, Implemented at the Expense of Local and Republican Budget Funds
for the 1st Quarter of 2026
                                           
No. FGR ABP/MIO PP BP Name of BIP Project Implementation Period (Year/Half-Year) Initial Cost of BIP, According to Documentation, thousand tenge Adjusted Cost of BIP, According to Feasibility Study/PSD, thousand tenge Total Planned Funding Volume for BIP, thousand tenge Volume of Completed Works in Physical Terms According to Feasibility Study/PSD Volume of Completed Works in thousand tenge Reasons for Deviation Measures Taken (Being Taken) Number of Projects Note (Availability of Documentation), Reasons for Cost Increase
including Actual Prior to Reporting Year Plan for Reporting Period Actual for Reporting Period Unfulfilled Activities for Reporting Period Total BIP Funding from Start of Implementation For Reporting Period Total Being Implemented Planned for Completion Actually Completed Reasons for Non-Completion
RB MB Actual Plan for 2026 Total Plan RB+MB Actual Total Actual RB+MB Deviation Total Deviation RB+MB
RB MB RB MB RB MB RB, thousand tenge % MB, thousand tenge % thousand tenge %
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 18 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
1 07 466 058 028 Construction of an Additional Water Treatment Plant, Main Water Pipeline to the Second Lift Station in Tobol Village, Beimbet Mailin District, Kostanay Region 2023-2026 1,752,243.0   1,202,243.0 498,074.0 Execution of construction and installation works, water pipeline length 10.7 km Works not planned in the 1st quarter     1,202,243.00 148,703.00   349,371.00     0.00       -349,371.0       In which quarter is it planned to start work?     1     Expert Conclusion No. SNKP-0081/23 dated 03.05.2023
8 07 466 075 000 Construction of a 30-Meter High Antenna-Mast Structure in Maksut Village, Beimbet Mailin District, Kostanay Region (Reuse) 2025-2026 31,226.0     31,067.0 Development of PSD with Obtaining a Positive Conclusion Works not planned in the 1st quarter       2,970.00   28,097.0     0.0       -28,097.0       In which quarter is it planned to start work?     1     Conclusion No. EXKZ - 0096/25 dated 05.05.2025
10 07 466 075 000 Construction of a 40-Meter High Antenna-Mast Structure in Orenburgskoye Village, Beimbet Mailin District, Kostanay Region 2025-2026 72,885.0     74,232.0 Development of PSD with Obtaining a Positive Conclusion Works not planned in the 1st quarter       5,490.00   68,742.0     0.0       -68,742.0       In which quarter is it planned to start work?     1     Conclusion No. ZHAR -0114/25 dated 26.05.2025