EVENTS PLAN
on the implementation of proposals and comments from the population expressed during the meeting of the Akim of the Beimbet district Maylina with population in the first half of 2026
|
No. |
The question being raised |
Execution deadlines
|
Responsible executor |
|
1. |
Consideration of the issue of implementing the project "Construction of an additional water treatment plant, main water supply to the station of the second lift of the village of Tobol" |
December 31, 2026 |
Department of Architecture and Urban Development , Tobol settlement |
|
2. |
Develop design and estimate documentation for the "Reconstruction of the water drainage system in the village of Tobol" |
December 31, 2026 |
Department of Housing and Public Utilities PT and AD
|
|
3. |
Improvement of populated areas |
1.10.2026 |
Akims of rural districts, Tobol settlement |