In Balkhash, construction of a new trunk network to the MKR has begun. Konyrat. After completion, in addition to konyratovtsy to the Central heating will be able to connect the working village, 64 block, partially the station Balkhash. Mayor of Balkhash oraz Taurbekov got acquainted with the progress of work.
⠀
Construction of heating networks in 17 km from the power plant to the MD.Konyrat will provide Central heating to residents of the district. The contractor purchased pre-insulated pipes with a diameter of 325 by 7 km, as well as bends. Under the contract, modular pumping stations, metal, and fittings will be delivered. Produced 80 pieces of railway support.
⠀
The contractor arrived at the construction site with a team. Excavation work started. At the end of 3.5 thousand residents of MKR.Konyrat will be connected to Central heating.
⠀
Recent years had problems with the heat in MD.Konyrat due to weak boiler equipment. The project is designed for 2 years.