📌On behalf of the Head of Statemeasures are being implemented in the country to develop the energy sector As part of this task, the autumnwinter period of 2024-2025 has been completed and preparations have begun for a large-scale renovation of infrastructure and the development of "green" energy
⚡️To pass the autumnwinter season in the heat supply10 power units 55 boilers and 45 turbines were overhauled which made it possible to begin the process of reducing the accumulated high wear of thermal power plants and heating networks
The measures taken have reduced the number of technological violations at power plants by 27% (from 1,070 to 782 cases) and cases of non-compliance with the temperature schedule by 67% (from 215 to 65)
🔷During the work carried out on 12 thermal power plants, the indicators changed 9 moved from the "red" zone to the "yellow" zone and 3 from the "yellow" to the "green" zone As a result10 thermal power plants remained in the "red" zone (there were 19) 17 in the "yellow" zone (there were 11) and 10 in the "green" zone (there were 7) Among them are Ekibastuz UstKamenogorsk Zhezkazagan Balkhash Atyrau Ridder Kentau and other stations Special attention was paid to the work of MAEK LLP Aktau heating networks as well as thermal power plants in Stepnogorsk and Temirtau
✔️In 2024771 MW of new capacity was commissioned including the restored Ekibastuz GRES1 unit (500 MW) a new turbine at Atyrau TPP (65 MW) and an upgraded boiler in Zhezkazgan (+43 MW) Renewable energy projects for 163.35 MW have also been launched
The Ministry of Energy has adjusted the marginal tariffs for electric energy increased the marginal tariff in the electric capacity market and increased the annual limit on returnable investments The measures taken in 2024 made it possible to increase the financing of repair work by 44% compared to the level of the previous year to 327 billion tenge
🔘At the same time, preparations for the next heating season have begun As part of this work, it is planned to repair 10 power units 63 boilers and 39 turbines at power plants some of the work is already underway Repairs and reconstruction of 53 boilers are planned for 66 boiler houses in the district heating area
⏩After the end of the cold weather, the renovation of 17 thousand km of power grids and 323 km of heating mains will begin
✔️Within the framework of the National Energy Modernization Project77.5 thousand km of electric grids and 1.6 thousand km of heating networks will be updated with a total budget of 4 trillion tenge By 2029this will reduce network wear by up to 45% and 42%respectively In the field of generation, it is planned to introduce 7.3 GW of new capacity including the modernization of existing plants and the construction of new ones It is planned to complete 29 projects by 2029 which will reduce the average wear of power plants by up to 40%
The development of renewable energy remains a priority In 2024153 facilities generated 7.58 billion kWhor 6.43% of total production 8 new stations (163.35 MW) have been commissioned, and 9 more renewable energy facilities (455.5 MW) will be operational by the end of 2025 For example in February1 wind farm project with a capacity of 50 MW was commissioned in the Karaganda region by Hyperborea LLP