As part of his visit to the Turkestan regionSungat Yessimkhanov reviewed the progress of reconstruction work at the Kentau Service CHP There are currently 4 boilers and 1 turbine in operation There are 2 more boilers in reserve The temperature schedule of the heating networks is observed It is planned to complete the reconstruction of 2 more boilers by the end of the year In addition the report of the head of Ontustik Zharyk Transit LLP on the progress of the heating season and planned repair work in 2025 was heard Following a meeting with representatives of the akimat of the region and the management of energy enterprises, the Vice Minister instructed to keep the course of the autumnwinter period under control observe the temperature schedule the standard of the operational fuel reserve The head of the Territorial Department of the Energy Supervision Committee was instructed to strengthen control over the work of energy enterprises in the region